Second Notice | | 8/26/2010 | 8/17/2010 | | DONE |
|
|
|
|
First Notice | | 7/31/2010 | 8/16/2010 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/21/2010 | 7/21/2010 | 7/21/2010 | P | PASS |
Forrest France
|
|
|
Correction items verified for completion, fire life safety passed.
|
BLD-Final | 7/19/2010 | 7/21/2010 | 7/21/2010 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
Permanent Occupancy UNPAID FEE | | | 7/21/2010 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Conference | 7/1/2010 | 7/1/2010 | 7/1/2010 | A | DONE |
Forrest France
|
|
|
Regarding project related fire alarm permit work.
|
FIRE-Final Inspection | 6/3/2010 | 6/4/2010 | 6/3/2010 | A | FAIL |
Forrest France
|
|
|
Inspection completed early, 6/3/10- see activity notes for details.
|
FIRE-Final Inspection | 6/3/2010 | 6/3/2010 | 6/3/2010 | P | FAIL |
Forrest France
|
|
|
A fire alarm permit will be necessary for modifications made to the existing system due to remodel work within the scope of BLD permit. Also noted one exit sign/EM light at the south exit to be repaired.
|
BLD-Framing/Rough-in | 5/3/2010 | 5/4/2010 | 5/4/2010 | A | PASS |
Dave Hannah
|
|
|
Perry Phone #: ###-####
|
BLD-Foundation | 4/14/2010 | 4/14/2010 | 4/14/2010 | P | PASS |
Dave Hannah
|
|
|
john Phone #: ###-#### ok to pour wall for chair lift
|
BLD-Concrete | 4/9/2010 | 4/12/2010 | 4/12/2010 | A | PART |
Dave Hannah
|
|
|
Dave Mortenson Phone #: ###-####-after 10 if possible please ok to pour ftg for chair lift
|
BLD-Framing/Rough-in | 3/26/2010 | 3/29/2010 | 3/29/2010 | A | PASS |
Dave Hannah
|
|
|
Perry Phone #: ###-####
|
BLD-Framing/Rough-in | 3/16/2010 | 3/17/2010 | 3/17/2010 | A | PART |
Dave Hannah
|
|
|
perry Phone #: ###-#### ok to cover demis wall
|
BLD-Framing/Rough-in | 3/10/2010 | 3/10/2010 | 3/10/2010 | P | PART |
Jim Sly
|
|
|
perry Phone #: ###-#### OK to cover walls in room 102
|
Issue PAID IN FULL permit | | | 2/12/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/9/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/9/2010 | | DONE |
|
|
|
|
Telephone call | | | 2/9/2010 | | DONE |
|
|
|
called left message with Bruce Poe for Cory Nelson permit ready and fee given 2-9-10 dld
|
Case Summary (BLD) | | | 2/8/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 2/2/2010 | | 2/5/2010 | | PASS |
Tim L. Woodard
|
|
|
2/5/2010 16:11:37 TLW - activity updated through activity BLDA022 from case BLD10-00174.
|
Routing - PLAN CHECK | 2/2/2010 | | 2/5/2010 | | PASS |
Tim L. Woodard
|
|
|
Plans approved with plan review report. TLW
|
Routing - FIRE | | | 2/5/2010 | | PASS |
Tim L. Woodard
|
|
|
FIELD VERIFY.
|
1st review completed | | | 2/5/2010 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/2/2010 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/2/2010 | | DONE |
|
|
|
|
Application received | | 2/1/2010 | 2/1/2010 | | DONE |
Tisha Gallop
|
|
|
|