Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD10-00180
StatusFinaled
Name PARADIGM CONSTRUCTION COMPANY LLC
Site Address 663 S BLUE PINE LN
Project NamePinetree Village
Customer Number 
ePlanReviewNo
Description
Permit for the construction of a new 1,728 sq. ft., two story (First story 762 sq. ft., second story 966 sq. ft.) Townhouse with 3 bedrooms, 2 1/2 bathrooms and a 488 sq. ft. attached garage. All work to be done per the approved plans, plan review report and any notations. R-2D zoning, DRH08-00043 and setbacks per planning. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/6/201010/7/201010/7/2010PPASS
DetailsMike Jordan
please call 1/2 hour before. thanks jim Phone #: ###-#### >> Inspection requested via web by James Larkin
DOC - Permit Finaled10/7/201010/7/201010/7/2010PPASS
DetailsMike Jordan
Certifiacte of occupancy issued.
BLD-Final8/27/20108/27/20108/27/2010PNR
DetailsJim Sly
please call 1/2 hour before. Thanks jim Phone #: ###-#### >> Inspection requested via web by James Larkin
Need electr and Plumbing final.
BLD-Aging Inspection8/23/20108/23/20108/23/2010 PASS
DetailsMike Jordan
Work in progress.
Zoning Approval8/20/20108/20/20108/20/2010 PASS
DetailsSarah Schafer
BLD-Aging Inspection6/21/20106/21/20106/21/2010 PASS
DetailsMike Jordan
work in progress.
BLD-Other4/21/20104/21/20104/21/2010PPART
DetailsMike Jordan
House Wrap Inspection requested from web by: James Larkin Phone #: ###-####. Insected installation of exterior weather membrane.
BLD-Energy code compliance4/19/20104/19/20104/19/2010PPASS
DetailsMike Jordan
JIM Phone #: ###-####
BLD-Framing/Rough-in4/19/20104/19/20104/19/2010PPASS
DetailsMike Jordan
JIM Phone #: ###-####. All framing issues were resolved.
BLD-Energy code compliance4/16/20104/16/20104/16/2010PNR
DetailsMike Jordan
Inspection requested from web by: James Larkin Phone #: ###-####
BLD-Energy code compliance4/15/20104/15/20104/15/2010PNR
DetailsMike Jordan
Inspection requested from web by: James Larkin Phone #: ###-####. Framing issues have not yet been resolved.
BLD-Framing/Rough-in4/14/20104/14/20104/14/2010PFAIL
DetailsMike Jordan
Jim Phone #: ###-####. Provide 36 inches at landings, bearing blocks at girder in garage, nail off all simpson hangars, complete lateral bracing. Provide 4 8d nails on all straps installed on either side. Complete the double layer of 5/8 type x rock at soffit.
BLD-Framing/Rough-in4/13/20104/13/20104/13/2010PNR
DetailsMike Jordan
firewall Inspection requested from web by: James Larkin Phone #: ###-####
BLD-Framing/Rough-in4/8/20104/8/20104/8/2010ACANC
DetailsMike Jordan
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
BLD-Framing/Rough-in4/2/20104/5/20104/5/2010APASS
DetailsMike Jordan
Firewall in overbuilds Inspection requested from web by: James Larkin Phone #: ###-####. Base and face layers of 5/8 typex rock for 2hr. fire wall, both sides, from ceiling to roof deck. Also verified installation of fire rated plywood at laydown parapet locations.
BLD-Framing/Rough-in3/29/20103/29/20103/29/2010PCANC
DetailsMike Jordan
firewall Inspection requested from web by: James Larkin Phone #: ###-####
BLD-Framing/Rough-in3/29/20103/29/20103/29/2010APASS
DetailsMike Jordan
Base and face layers of 5/8 type x rock for 2hr firewall, 2nd. floor, remaining side.
BLD-Framing/Rough-in3/25/20103/26/20103/26/2010APART
DetailsMike Jordan
Firewall construction Inspection requested from web by: James Larkin Phone #: ###-####. base and face layer of 5/8 typex rock, one side, 2nd. floor.
BLD-Framing/Rough-in3/24/20103/24/20103/24/2010PNR
DetailsMike Jordan
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
BLD-Framing/Rough-in3/19/20103/19/20103/19/2010PPASS
DetailsMike Jordan
Jim Fire wall construction Phone #: ###-####.base and face layers of 2hr. firewall, 1st. floor.
BLD-Framing/Rough-in3/17/20103/17/20103/17/2010PPASS
DetailsMike Jordan
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####. Meeting with framing contractor to discuss firewall transition from single story to two story units.
BLD-Framing/Rough-in3/16/20103/16/20103/16/2010APART
DetailsMike Jordan
Fiewall Construction Inspection requested from web by: James Larkin Phone #: ###-####. 5/8 type x rock, base layer , one side only for 2hr. firewall.
BLD-Footing3/10/20103/11/20103/11/2010APASS
DetailsMike Jordan
bill Phone #: ###-####. Interior footings and column pad footings.
BLD-Energy code compliance3/8/20103/8/20103/8/2010PPASS
DetailsMike Jordan
foundation insulation at garage wall Inspection requested from web by: James Larkin Phone #: ###-####
BLD-Energy code compliance3/4/20103/4/20103/4/2010PFAIL
DetailsMike Jordan
Foundation Insulation Inspection requested from web by: James Larkin Phone #: ###-####. Needs to instaal rigid foam insulation at common wall with garge.
BLD-Foundation2/26/20103/2/20103/2/2010PPASS
DetailsMike Jordan
James Phone #: ###-####
BLD-Footing2/26/20103/1/20103/1/2010PPASS
DetailsMike Jordan
James Phone #: ###-####
BLD-Footing2/25/20102/26/20103/1/2010PNR
DetailsMike Jordan
Inspection requested from web by: James Larkin Phone #: ###-####
Issue PAID IN FULL permit  2/25/2010 DONE
OVERRIDE  2/19/2010  
Telephone call  2/19/2010 DONE
t/c w james at ###-#### - permit ready and fees given - also faxed to him
Permit Ready to Issue  2/19/2010 DONE
Details
Inspection Record Card- Bld  2/18/2010 DONE
Details
Plan assigned to (CDM)2/17/20102/17/20102/17/2010 DONE
DetailsCarl D Madsen
Route to Impact Fee Review2/1/20102/4/20102/17/2010 PASS
DetailsCindy M. Gould
Case Summary (BLD)  2/17/2010 DONE
PLANS/APPL TAKEN TO FRONT DESK  2/17/2010  
Routing - PLAN CHECK2/4/2010 2/17/2010 PASS
DetailsCarl D Madsen
Plan resubmittals received  2/10/2010  
DetailsTisha Gallop
received two copies of structural calcs, and plan sheets A2.1(foundation) & A4.1(framing); taken to Carl Madsen
Routing - PUBLIC WORKS2/3/2010 2/4/2010 PASS
DetailsConnie Baumgartner
Routed to Public Works 2/3/2010.
Routing - PLANNING2/2/2010 2/3/2010 PASS
DetailsMatthew A Halitsky
Routed to Mat H. (DRH08-43)
Routing - Addressing2/2/2010 2/2/2010 PASS
DetailsApril Wing
Application received 2/1/2010