Third Notice | | 11/5/2010 | 11/24/2010 | | DONE |
|
|
|
|
Third Notice | | 10/11/2010 | 10/22/2010 | | DONE |
|
|
|
faxed
|
Third Notice | | 9/20/2010 | 9/27/2010 | | DONE |
|
|
|
faxed
|
Second Notice | | 9/5/2010 | 9/15/2010 | | DONE |
|
|
|
|
First Notice | | 8/22/2010 | 8/26/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 8/12/2010 | | DONE |
|
|
|
|
BLD-Final | 5/19/2010 | 5/21/2010 | 5/21/2010 | A | PASS |
Jim Sly
|
|
|
Contact is Wes Smith ###-####. Inspection requested from web by: Scott Henderson Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 5/20/2010 | 5/20/2010 | 5/20/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 5/19/2010 | 5/20/2010 | 5/20/2010 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the two exit signs have been connected to the emergency light circuit.
|
BLD-Conference | 5/13/2010 | 5/14/2010 | 5/14/2010 | A | DONE |
Jim Sly
|
|
|
Wes Smith Phone #: ###-####
|
BLD-Framing/Rough-in | 3/29/2010 | 3/29/2010 | 3/29/2010 | P | PART |
Jim Sly
|
|
|
wes Phone #: ###-#### Focus rooms and dead net room only ...OK
|
Plan assigned to (DRS) | 2/4/2010 | | 3/26/2010 | | PASS |
Dan Stuart
|
|
|
3/26/2010 09:20:47 DRS - activity updated through activity BLDA022 from case BLD10-00197.
|
Routing - PLAN CHECK | 3/22/2010 | | 3/26/2010 | | PASS |
Dan Stuart
|
|
|
Resubmittal sheets of 3/25/10 inserted into plans by Scott Wendell. Plans to permit desk to issue.
|
Plan resubmittals received | | | 3/26/2010 | | DONE |
|
|
|
Submitted and inserted by Scott Wendell, LCA
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/26/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/26/2010 | | DONE |
|
|
|
t/c w scott wendell at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/26/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/26/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/5/2010 | | 3/22/2010 | | FAIL |
Dan Stuart
|
|
|
To fire code analyst for review.
3/22/10 - Changed pass to fail. Accessibility upgrades need to be addressed for all three floors before permits are issued. Copy of plan review e-mailed to architects.
|
Routing - FIRE | 3/19/2010 | | 3/22/2010 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans.
|
Plan resubmittals received | | | 3/22/2010 | | |
Tisha Gallop
|
|
|
received two copies of plan sheet A00.62; taken to Dan Stuart
|
Plan resubmittals requested | | | 3/22/2010 | | FAIL |
|
|
|
Accessibility upgrades not addressed. Copy of plan review e-mailed to architect.
|
Routing - PLAN CHECK | 3/3/2010 | | 3/19/2010 | | PEND |
Dan Stuart
|
|
|
Routing back to fire code analys for review of architects response.
|
Plan resubmittals received | | | 3/18/2010 | | |
Tisha Gallop
|
|
|
received transmittal, memo, copy of Boise City Plan Review and Fire Code Review, Tol-Brace Seismic Calcs (2pgs); taken to Dan Stuart
|
1st review completed | | | 3/3/2010 | | FAIL |
|
|
|
Failed Fire
|
Routing - FIRE | 2/26/2010 | | 3/3/2010 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
Routing PW Environmental | 2/5/2010 | | 2/8/2010 | | PASS |
Walt Baumgartner
|
|
|
No pretreatment or discharge permit issues. Office remodel only.
|
Routing PW Sewer Rating | 2/5/2010 | | 2/5/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 2/4/2010 | | 2/4/2010 | | PASS |
April Wing
|
|
|
Break Room Sink
|
Pending Assignment by JCB | 2/3/2010 | | 2/4/2010 | | DONE |
Jason Blais
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/3/2010 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/3/2010 | | DONE |
|
|
|
|
Application received | | 2/3/2010 | | | |
|
|
|
|