First Notice | 11/17/2010 | 11/17/2010 | 11/24/2010 | | DONE |
Jim Sly
|
|
|
|
BLD-Final | 11/16/2010 | 11/17/2010 | 11/17/2010 | A | PASS |
Jim Sly
|
|
|
call 30 min prior to meet//Wes Smith Phone #: ###-#### C/C issued.
|
DOC - Permit Finaled | 11/17/2010 | 11/17/2010 | 11/17/2010 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 9/9/2010 | 9/10/2010 | 9/10/2010 | A | PART |
Jim Sly
|
|
|
Wes smith Phone #: ###-#### OK for Temp Occ. Waiting for doors and glass on order for 3 rooms.
|
FIRE-Final Inspection | 9/9/2010 | 9/10/2010 | 9/9/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed again. Jim Sly will cover the missing doors and hardware.
|
BLD-Framing/Rough-in | 9/2/2010 | 9/3/2010 | 9/3/2010 | A | PASS |
Jim Sly
|
|
|
Wes Phone #: ###-#### All framing which was added to original plans.....OK
|
Print Occupancy Form | | | 9/2/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/2/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/2/2010 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 8/27/2010 | 8/27/2010 | 9/1/2010 | | PASS |
Dan Stuart
|
|
|
9/1/2010 09:22:33 DRS - activity updated through activity BLDA022 from case BLD10-00198.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/1/2010 | | PASS |
|
|
|
|
FIRE-Final Inspection | 8/30/2010 | 8/31/2010 | 8/31/2010 | A | CANC |
Troy Cobbley
|
|
|
Cancel per wes Phone #: ###-####
|
BLD-Final | 8/30/2010 | 8/31/2010 | 8/31/2010 | P | CANC |
Jim Sly
|
|
|
temp only plan mod underway. Wes ###-####
|
Routing - PLAN CHECK | 8/27/2010 | | 8/31/2010 | | PASS |
Dan Stuart
|
|
|
Plan Modification reviewed. Original permit, plan review and red-lined notes changed to include plan mod changes.
|
Override - Parcel Holds | | | 8/30/2010 | | |
|
|
|
|
Override - Parcel Holds | | | 8/30/2010 | | |
|
|
|
|
Plan Modification Accepted | | | 8/27/2010 | | DONE |
|
|
|
Plan modification excepted for BLD10-00198 to relocate and rotate conferance room ,focus room and print room modules. Add two anditional focus rooms, one comferance room and one print room in the south west corner of the building. Sheets a00.00,a00.1,a00.10,a00.33,a00.35,a00.41,a00.63,a01.03,a02.03,a04.03,a05.03,a06.03,a08.30a,a08.03b,aa11.02,a11.03,a12.00,a12.01,a12.10,a12.20,m00.01,m00.20,m01.03b,m01.03d,m02.03a,m02.03b,m02.03c,,e00.00,e01.03,e02.03,e03.03,e04.03,e05.01,e06.03b
|
BLD-Conference | 7/27/2010 | 7/27/2010 | 7/27/2010 | P | DONE |
Jim Sly
|
|
|
wes Phone #: ###-#### Change on approved plan requires plan modification.
|
BLD-Framing/Rough-in | 7/12/2010 | 7/12/2010 | 7/12/2010 | P | PASS |
Jim Sly
|
|
|
wes Phone #: ###-####
|
BLD-Final | 6/21/2010 | 6/23/2010 | 6/23/2010 | A | NR |
Jim Sly
|
|
|
Wes Phone #: ###-#### NR
|
BLD-Final | 6/7/2010 | 6/8/2010 | 6/8/2010 | P | NR |
Jim Sly
|
|
|
Wes Phone #: ###-####
|
FIRE-Final Inspection | 6/7/2010 | 6/8/2010 | 6/8/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 5/20/2010 | 5/21/2010 | 5/21/2010 | A | CANC |
Jim Sly
|
|
|
wes Phone #: ###-#### NR
|
FIRE-Final Inspection | 5/20/2010 | 5/20/2010 | 5/20/2010 | P | FAIL |
Troy Cobbley
|
|
|
Life safety can be passed when the project related fire alarm permit is passed. The two exit signs have been repaired.
|
FIRE-Final Inspection | 5/19/2010 | 5/20/2010 | 5/20/2010 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when the two exit signs have been connected to the emergency light circuit and the project related fire alarm permit is finaled.
|
BLD-Conference | 5/13/2010 | 5/14/2010 | 5/14/2010 | A | DONE |
Jim Sly
|
|
|
Wes Smith Phone #: ###-####
|
BLD-Framing/Rough-in | 3/29/2010 | 3/29/2010 | 3/29/2010 | P | PART |
Jim Sly
|
|
|
wes Phone #: ###-#### Training rooms only ...OK
|
Routing - PLAN CHECK | 3/25/2010 | | 3/26/2010 | | PASS |
Dan Stuart
|
|
|
Resubmittals inserted into plans by Scott Wendell. Plans to permit desk to issue.
|
Plan assigned to (DRS) | 2/5/2010 | | 3/26/2010 | | PASS |
Dan Stuart
|
|
|
3/26/2010 10:19:51 DRS - activity updated through activity BLDA022 from case BLD10-00198.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/26/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/26/2010 | | DONE |
|
|
|
t/c w scott wendell at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/26/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/26/2010 | | DONE |
|
|
|
|
Routing - FIRE | 3/22/2010 | | 3/25/2010 | | PASS |
Scott Arellano
|
|
|
Attached updated IFC comments to plans
|
Plan resubmittals received | | | 3/25/2010 | | DONE |
|
|
|
Plan resubmittals inserted into plans by Sclott Wendell, LCA.
|
Plan resubmittals requested | | | 3/22/2010 | | DONE |
|
|
|
Plan Review e-mailed to architect.
|
Routing - PLAN CHECK | 3/3/2010 | | 3/22/2010 | | FAIL |
Dan Stuart
|
|
|
Accessibility upgrades not addressed in resubmittals. Copy of plan review to architect. Routing plans to fire code analyst for review.
|
Plan resubmittals received | | | 3/18/2010 | | |
Tisha Gallop
|
|
|
received memo for response, copy of City of Boise Plan Review and Fire Code Review, two copies of plan sheets A00.00, A00.33, A00.63, A01.03, A02.03, A08.0c, A11.01, A11.02, A12.00; taken to Dan Stuart
|
Routing - FIRE | 2/26/2010 | | 3/3/2010 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 3/3/2010 | | FAIL |
|
|
|
Failed Plan Check, Fire
|
Plan resubmittals requested | | | 2/26/2010 | | DONE |
|
|
|
E-mail copy of plan review to architect.
|
Routing - PLAN CHECK | 2/5/2010 | | 2/26/2010 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. copy of plan review e-mailed to architect for response. Routing to fire code analyst.
|
Pending Assignment by JCB | 2/3/2010 | | 2/5/2010 | | DONE |
Jason Blais
|
|
|
|
Application received | | 2/3/2010 | 2/3/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/3/2010 | | DONE |
|
|
|
|
Received partial PAYMENT | | | 2/3/2010 | | DONE |
|
|
|
|