BLD-Final | 12/15/2010 | 12/15/2010 | 12/15/2010 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 12/15/2010 | 12/15/2010 | 12/15/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy was issued.
|
BLD-Final | 12/15/2010 | 12/15/2010 | 12/15/2010 | P | CANC |
Mike Jordan
|
|
|
Please call Scott for access. Thanks. Phone #: ###-#### >> Inspection requested via web by Scott Zierler
|
BLD-Wall cover | 10/29/2010 | 11/1/2010 | 11/1/2010 | A | PASS |
Mike Jordan
|
|
|
reinspection Phone #: ###-#### >> Inspection requested via web by Scott Zierler
|
BLD-Wall cover | 10/27/2010 | 10/28/2010 | 10/28/2010 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Zierler. Romove wood penetrations an dprovide addotional screws.
|
BLD-Energy code compliance | 10/21/2010 | 10/22/2010 | 10/22/2010 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Zierler
|
BLD-Framing/Rough-in | 10/21/2010 | 10/21/2010 | 10/21/2010 | A | PASS |
Mike Jordan
|
|
|
Reinspection. Please call for onsite visit. Thanks. Phone #: ###-#### >> Inspection requested via web by Scott Zierler
|
BLD-Energy code compliance | 10/21/2010 | 10/21/2010 | 10/21/2010 | A | PASS |
Mike Jordan
|
|
|
Reinspection. Please call for onsite visit. Thanks. Phone #: ###-#### >> Inspection requested via web by Scott Zierler
|
BLD-Framing/Rough-in | 10/18/2010 | 10/19/2010 | 10/19/2010 | A | PART |
Mike Jordan
|
|
|
Reinspect Phone #: ###-#### >> Inspection requested via web by Scott Zierler. Work in progress on repairs.
|
BLD-Framing/Rough-in | 10/13/2010 | 10/14/2010 | 10/14/2010 | P | FAIL |
Mike Jordan
|
|
|
Call for onsite meeting. Thanks! Phone #: ###-#### >> Inspection requested via web by Scott Zierler. Nail off all hangars, complete fire blocking and draft stops.
|
BLD-Energy code compliance | 10/13/2010 | 10/14/2010 | 10/14/2010 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Scott Zierler
|
BLD-Aging Inspection | 8/19/2010 | 8/19/2010 | 8/19/2010 | | PASS |
Mike Jordan
|
|
|
work in progress.
|
BLD-Framing/Rough-in | 5/18/2010 | 5/18/2010 | 5/18/2010 | A | PART |
Mike Jordan
|
|
|
Provided preliminary framing inspection so that contractor could start repairing any outstanding issues prior to doing any rough ins. Contractor will make any repairs discussed and recall for formal framing inspection once all rough ins are completed and inspected.
|
BLD-Footing | 3/10/2010 | 3/11/2010 | 3/11/2010 | A | PART |
Mike Jordan
|
|
|
bill Phone #: ###-####. Footing ok. Needs to remove gas line from footing.
|
BLD-Wall cover | 3/3/2010 | 3/4/2010 | 3/4/2010 | A | PART |
Mike Jordan
|
|
|
Inspection of OSB replacement and Fire Wall Sheetrock replacement. Please call Scott for site visit. Thanks! Inspection requested from web by: Scott Zierler Phone #: ###-####. Met with contractor on site and went over engineering, approved plans as well as propertyline walls that still need to be reated.
|
BLD-Conference | 3/3/2010 | 3/4/2010 | 3/3/2010 | P | CANC |
Mike Jordan
|
|
|
Inspection of OSB replacement and Fire Wall Sheetrock replacement. Please call Scott for site visit. Thanks! Inspection requested from web by: Scott Zierler Phone #: ###-#### Inspection cancelled from web by: Scott Zierler
|
Issue PAID IN FULL permit | | | 2/25/2010 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 2/22/2010 | | |
|
|
|
|
Telephone call | | | 2/22/2010 | | DONE |
Tisha Gallop
|
|
|
called and left vm for Pat McMonigle permit is ready
|
Permit Ready to Issue | | | 2/22/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (CDM) | 2/3/2010 | 2/3/2010 | 2/19/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 2/8/2010 | | 2/19/2010 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 2/19/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/19/2010 | | |
Tisha Gallop
|
|
|
|
Route to Impact Fee Review | 2/4/2010 | 2/9/2010 | 2/9/2010 | | PASS |
Cindy M. Gould
|
|
|
Impact fees paid when shell was built
|
Routing - PUBLIC WORKS | | | 2/8/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 2/4/2010 | | 2/5/2010 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 2/4/2010 | | 2/4/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 2/3/2010 | 2/3/2010 | | DONE |
Tisha Gallop
|
|
|
|