BLD-Final | 6/2/2010 | 6/3/2010 | 6/3/2010 | P | PASS |
Mike Jordan
|
|
|
call for access code// Brett ###-####
|
DOC - Permit Finaled | 6/3/2010 | 6/3/2010 | 6/3/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy was issued.
|
BLD-Aging Inspection | 6/2/2010 | 6/2/2010 | 6/2/2010 | | CANC |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 4/2/2010 | 4/2/2010 | 4/2/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 4/2/2010 | 4/2/2010 | 4/2/2010 | P | PASS |
Mike Jordan
|
|
|
Framing issues have been resolved. Received truss fix from engineer via e-mail. ok to insul.
|
BLD-Framing/Rough-in | 4/2/2010 | 4/2/2010 | 4/2/2010 | A | FAIL |
Mike Jordan
|
|
|
Noted A1 trusses were reversed when installed. Provide truss engineering for repair. ok to insul.
|
BLD-Framing/Rough-in | 4/1/2010 | 4/1/2010 | 4/1/2010 | P | FAIL |
Tom Arcoraci
|
|
|
Brett needs electric rough in
|
CHANGE STATUS TO (ISS) | | | 3/26/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/26/2010 | | DONE |
|
|
|
|
OVERRIDE | | | 3/24/2010 | | |
|
|
|
|
Plan assigned to (PEP) | 3/24/2010 | 3/24/2010 | 3/24/2010 | | PASS |
Perry Paine
|
|
|
3/24/2010 09:14:13 PEP - activity updated through activity BLDA022 from case BLD10-00225.
|
1st review completed | | | 3/24/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/24/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/24/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/24/2010 | | DONE |
|
|
|
t/c w tanya at ###-#### - permit (resubmittal) ready and fees given
|
Permit Ready to Issue | | | 3/24/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 3/24/2010 | | |
|
|
|
|
Routing - PLAN CHECK | 3/24/2010 | | 3/24/2010 | | PASS |
Perry Paine
|
|
|
|
Plan resubmittals received | | | 3/24/2010 | | PASS |
|
|
|
|
Plan resubmittals received | | | 3/23/2010 | | |
Tisha Gallop
|
|
|
received full revised set of plans due to room rearrangement, plot plan has not changed. routed to Perry Paine
|
1st review completed | | | 3/23/2010 | | FAIL |
|
|
|
resubmittal requires copy of the approved plans also. 3-23-2010 pep
|
BLD-Foundation | 3/19/2010 | 3/19/2010 | 3/19/2010 | P | PASS |
Mike Jordan
|
|
|
Ryan Phone #: ###-####
|
BLD-Foundation | 3/18/2010 | 3/18/2010 | 3/18/2010 | P | PASS |
Mike Jordan
|
|
|
ryan - foundation footing Phone #: ###-####
|
Issue PAID IN FULL permit | | | 3/5/2010 | | DONE |
|
|
|
|
OVERRIDE | | | 2/22/2010 | | |
|
|
|
|
Case Summary (BLD) | | | 2/22/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/22/2010 | | DONE |
|
|
|
|
Telephone call | | | 2/22/2010 | | DONE |
|
|
|
t/c w tanya at 2###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 2/22/2010 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 2/19/2010 | 2/19/2010 | 2/19/2010 | | PASS |
Perry Paine
|
|
|
2/19/2010 16:31:20 PEP - activity updated through activity BLDA022 from case BLD10-00225.
|
Route to Impact Fee Review | 2/5/2010 | 2/10/2010 | 2/19/2010 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 2/19/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/9/2010 | | 2/19/2010 | | PASS |
Perry Paine
|
|
|
|
Routing - PUBLIC WORKS | 2/8/2010 | | 2/9/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 2/5/2010 | | 2/8/2010 | | PASS |
Susan Riggs
|
|
|
Routed to Susan Riggs (CUP05-129)
|
Routing - Addressing | 2/5/2010 | | 2/5/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 2/5/2010 | | | |
|
|
|
|
Routing - PLAN CHECK | 3/23/2010 | | | | FAIL |
Perry Paine
|
|
|
Approved plans are required with the resubmittals
|