Second Notice | | 9/19/2010 | 9/24/2010 | | DONE |
|
|
|
|
First Notice | | 9/3/2010 | 9/9/2010 | | DONE |
|
|
|
|
BLD-Final | 8/24/2010 | 8/24/2010 | 8/24/2010 | P | PASS |
Tony Young
|
|
|
don Phone #: ###-####
|
Permanent Occupancy | | | 8/24/2010 | | DONE |
|
|
|
|
Zoning Approval | 8/18/2010 | 8/19/2010 | 8/23/2010 | | PASS |
Andrea Tuning
|
|
|
|
BLD-Final | 7/27/2010 | 7/28/2010 | 7/28/2010 | A | PASS |
Tony Young
|
|
|
all permits paid
|
Temporary Occupancy UNPAID FEE | | | 6/14/2010 | | |
|
|
|
|
Temporary Occupancy UNPAID FEE | | | 6/14/2010 | | DONE |
|
|
|
|
BLD-Final | 6/10/2010 | 6/11/2010 | 6/11/2010 | P | PART |
Tony Young
|
|
|
don Phone #: ###-####,, need zoning, ACHD,, temp ok,, need address facing State st.
|
FIRE-Final Inspection | 6/11/2010 | 6/11/2010 | 6/11/2010 | P | PASS |
Forrest France
|
|
|
Reinspection passed for noted correction items. Comments # 10 and 11 on the fire code review are not applicable- building is not equipped with a fire alarm system. HVAC units are below min. cfm to require duct detectors.
|
FIRE-Final Inspection | 6/10/2010 | 6/11/2010 | 6/11/2010 | A | FAIL |
Forrest France
|
|
|
Missing building address numbers per review note #2, one exit sign per plan review red-lines needs to be relocated. EM lighting passed.
|
BLD-Other | 4/13/2010 | 4/14/2010 | 4/14/2010 | A | PASS |
Tony Young
|
|
|
Don Phone #: ###-####,, ok to cover now,,
|
BLD-Framing/Rough-in | 4/13/2010 | 4/13/2010 | 4/13/2010 | P | PART |
Tony Young
|
|
|
Don Phone #: ###-####,, frame ok but need plumbing signed off in walls
|
BLD-Footing | 3/23/2010 | 3/24/2010 | 3/24/2010 | P | PASS |
Tony Young
|
|
|
don Phone #: ###-#### 2 interior pad ftgs,, one bearing wall int footing ok
|
Telephone call | | | 3/16/2010 | | DONE |
|
|
|
t/c w robert at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/16/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 3/16/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 3/12/2010 | | 3/15/2010 | | DONE |
Carl Westfall
|
|
|
Plans came back from ESC.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/15/2010 | | |
|
|
|
|
Print Occupancy Form | | | 3/15/2010 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 2/11/2010 | | 3/15/2010 | | PASS |
Carl Westfall
|
|
|
3/15/2010 14:39:47 CJW - activity updated through activity BLDA022 from case BLD10-00257.
|
Routing - Addressing | 2/11/2010 | | 3/15/2010 | | PASS |
April Wing
|
|
|
|
Routing - PLAN CHECK | 3/1/2010 | | 3/12/2010 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
Routing - Erosion and Sediment | | | 3/12/2010 | | PASS |
Steven Webb
|
|
|
ESC plan waiver is approved according to the ESC permit's attached conditions. ESC10-00115
|
Plan resubmittals received | | | 3/12/2010 | | |
Tisha Gallop
|
|
|
received transmittal, ACHD letter, two copies of plan sheet AS-101; taken to Carl Westfall
|
Plan resubmittals received | | | 3/9/2010 | | |
Tisha Gallop
|
|
|
received transmittal, architects response, engineers response, two copies of (2)SGS reports, supplemental structural calculations and plan sheets G-001, G-002, AS-101, AD-101, A-101, A-102, A-202, A-301, A-501, A-601, S-101; taken to Carl Westfall
|
Routing - FIRE | 2/25/2010 | 2/25/2010 | 3/1/2010 | | PASS |
Scott Arellano
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/1/2010 | | FAIL |
|
|
|
Failed Plan Check and ESC
|
Route to Impact Fee Review | 2/25/2010 | 3/2/2010 | 2/25/2010 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no fees
|
Routing - PLAN CHECK | 2/16/2010 | | 2/25/2010 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on February 22, 2010 and finished on February 25, 2010. Revised drawings were required. See the plan review report.
|
Routing - Design Review | 2/16/2010 | | 2/16/2010 | | PASS |
Andrea Tuning
|
|
|
Andrea Tuning - DRH10-00010
|
Routing - Erosion and Sediment | 1/12/2010 | | 2/16/2010 | | FAIL |
Steven Webb
|
|
|
ESC permit application does not include a certified RP.
|
Routing PW Sewer Rating | 2/12/2010 | | 2/12/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 2/11/2010 | | 2/12/2010 | | PASS |
Beverly Hall
|
|
|
|
Pending Assignment by JCB | 2/10/2010 | | 2/11/2010 | | DONE |
Jason Blais
|
|
|
|
Application received | | 2/9/2010 | 2/10/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/10/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/10/2010 | | DONE |
Tisha Gallop
|
|
|
|