BLD-Final | 6/14/2010 | 6/14/2010 | 6/14/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hr before. Thanks Jim Inspection requested from web by: James Larkin Phone #: ###-####
|
DOC - Permit Finaled | 6/14/2010 | 6/14/2010 | 6/14/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy was issued.
|
Zoning Approval | 6/14/2010 | 6/14/2010 | 6/14/2010 | | DONE |
Sarah Schafer
|
|
|
|
BLD-Final | 6/10/2010 | 6/11/2010 | 6/11/2010 | P | NR |
Mike Jordan
|
|
|
please call 1/2 hr before.thanks Jim Inspection requested from web by: James Larkin Phone #: ###-####. Needs zoning.
|
BLD-Energy code compliance | 5/7/2010 | 5/7/2010 | 5/7/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hour before. Thanks! Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 5/6/2010 | 5/6/2010 | 5/6/2010 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. ok to insulate.
|
BLD-Framing/Rough-in | 4/21/2010 | 4/21/2010 | 4/21/2010 | P | PASS |
Mike Jordan
|
|
|
Firewall construction "Overbuilds" Inspection requested from web by: James Larkin Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. fire wall at ceiling to underside of roof deck and at overbuilds.
|
BLD-Framing/Rough-in | 4/20/2010 | 4/20/2010 | 4/20/2010 | P | PASS |
Mike Jordan
|
|
|
Firewall construction-Jim Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. firewall at overbuild.
|
BLD-Framing/Rough-in | 4/19/2010 | 4/19/2010 | 4/19/2010 | P | PASS |
Mike Jordan
|
|
|
JIM\\FIRE WALL CONSTRUSTION Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. firewalls, 2nd. floor both sides.
|
BLD-Framing/Rough-in | 4/15/2010 | 4/15/2010 | 4/15/2010 | P | NR |
Mike Jordan
|
|
|
firewall construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/14/2010 | 4/14/2010 | 4/14/2010 | P | NR |
Mike Jordan
|
|
|
Jim-Fire wall inspection please Phone #: ###-####
|
BLD-Framing/Rough-in | 4/13/2010 | 4/13/2010 | 4/13/2010 | P | NR |
Mike Jordan
|
|
|
firewall Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 | P | PASS |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. firewall, remaining side, 1st. floor.
|
BLD-Framing/Rough-in | 4/7/2010 | 4/7/2010 | 4/7/2010 | P | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. fire wall, one side only, 1st. floor.
|
BLD-Framing/Rough-in | 4/6/2010 | 4/6/2010 | 4/6/2010 | P | NR |
Mike Jordan
|
|
|
firewall Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/2/2010 | 4/5/2010 | 4/5/2010 | A | NR |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Footing | 3/19/2010 | 3/19/2010 | 3/19/2010 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Interior footings
|
BLD-Energy code compliance | 3/16/2010 | 3/16/2010 | 3/16/2010 | A | PASS |
Mike Jordan
|
|
|
Foundation Insulation Inspection requested from web by: James Larkin Phone #: ###-####. Rigid insulation at interior side of stemwall.
|
BLD-Foundation | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Footing | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####
|
OVERRIDE | | | 3/8/2010 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/8/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 3/8/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/8/2010 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 3/5/2010 | 3/5/2010 | 3/5/2010 | | DONE |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 3/5/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2010 | | |
|
|
|
|
Routing - PLAN CHECK | 3/2/2010 | | 3/5/2010 | | PASS |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 2/11/2010 | 2/17/2010 | 3/4/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PUBLIC WORKS | 2/26/2010 | | 3/2/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 2/11/2010 | | 2/26/2010 | | PASS |
Matthew A Halitsky
|
|
|
Routed to Matt H
|
Routing - Addressing | 2/11/2010 | | 2/11/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 2/11/2010 | | | |
|
|
|
|