Third Notice | | 3/17/2011 | 3/16/2011 | | DONE |
|
|
|
|
Third Notice | | 2/22/2011 | 3/3/2011 | | DONE |
|
|
|
faxed
|
Second Notice | | 2/14/2011 | 2/17/2011 | | DONE |
|
|
|
|
First Notice | | 1/28/2011 | 2/4/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/18/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Aging Inspection | 11/26/2010 | 11/26/2010 | 11/30/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 9/21/2010 | 9/23/2010 | 9/23/2010 | A | PASS |
Dave Hannah
|
|
|
Daryl Phone #: ###-####
|
FIRE-Final Inspection | 9/22/2010 | 9/22/2010 | 9/22/2010 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
FIRE-Final Inspection | 9/21/2010 | 9/21/2010 | 9/21/2010 | P | PASS |
Forrest France
|
|
|
Correction items completed, fire life safety final approved.
|
FIRE-Final Inspection | 9/20/2010 | 9/21/2010 | 9/21/2010 | A | FAIL |
Forrest France
|
|
|
Missing ceiling tile at one fire sprinkler head in a mechanical closet, two exit signs need repaired, dust covers at smoke detectors are to be removed.
|
BLD-Framing/Rough-in | 9/1/2010 | 9/2/2010 | 9/2/2010 | A | PASS |
Dave Hannah
|
|
|
Daryl-Ceiling inspection please Phone #: ###-#### ok to cover ceiling
|
FIRE-Sprinkler Rough-in | 8/27/2010 | 8/27/2010 | 8/27/2010 | P | PART |
Forrest France
|
|
|
Okay to cover overhead fire sprinkler system modifications at the grid ceilings.
|
BLD-Framing/Rough-in | 7/13/2010 | 7/16/2010 | 7/16/2010 | A | PASS |
Dave Hannah
|
|
|
kelly Phone #: ###-####
|
Issue & PRINT to be Invoiced | | | 4/5/2010 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 2/25/2010 | | 3/26/2010 | | PASS |
Dan Stuart
|
|
|
3/26/2010 11:37:13 DRS - activity updated through activity BLDA022 from case BLD10-00373.
|
Routing - PUBLIC WORKS | 2/25/2010 | | 3/26/2010 | | PASS |
Beverly Hall
|
|
|
|
Routing - PLAN CHECK | 3/22/2010 | | 3/26/2010 | | PASS |
Dan Stuart
|
|
|
Resubmittals inserted into plans by representative of ZGA Architects. Discussion with Josh Howa concerning Door(s) 115A for minimum clear door leaf widht. Not changed on plans. Per Josj, I will red-line plans to show 3'-6" single leaf & in door scheduel. He will follow up wiith written addendum for change.
|
Telephone call | | | 3/26/2010 | | DONE |
|
|
|
Called Josh Howa, ZGZ. Resubmittal cover letter indicates that door(s) 115A was modified to provide minimum 32" clear width for at least one leaf. This was not done on the plans or in the door schedule. Josh determined to use one door leaf of 3' - 6" and I told him I would red line plans and door schedule to allow the permit to be issued. A written addendum will be provided by Josh.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/26/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/26/2010 | | DONE |
|
|
|
|
Telephone call | | | 3/26/2010 | | DONE |
|
|
|
tc/ w tom at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 3/26/2010 | | DONE |
|
|
|
|
Plan resubmittals received | | | 3/25/2010 | | |
|
|
|
received 2 copies of sheets a-101,a-102,a-202,a-601,am-101,e2.0,e3.0,e4.0, 1 transmittal letter,1 plan review comment. inserted by Sara from ZGA Architects. Taken back to Dan S.
|
Routing - FIRE | 3/17/2010 | 3/17/2010 | 3/22/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 3/22/2010 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 3/17/2010 | 3/22/2010 | 3/18/2010 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Plan resubmittals requested | | | 3/17/2010 | | DONE |
|
|
|
E-mail plan review comments to architect.
|
Routing - PLAN CHECK | 3/1/2010 | | 3/17/2010 | | FAIL |
Dan Stuart
|
|
|
Copy of plan review e-mailed to Tom Zabala Architect for response. routing plans to fire code analyst for review.
|
Routing - PLUMBING | 2/26/2010 | | 3/1/2010 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing PW Sewer Rating | 2/26/2010 | | 2/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Pending Assignment by JCB | 2/24/2010 | | 2/25/2010 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 2/25/2010 | | 2/25/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 2/24/2010 | 2/24/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/24/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/24/2010 | | DONE |
Tisha Gallop
|
|
|
|