First Notice | | 7/24/2010 | 7/30/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 7/6/2010 | 7/7/2010 | 7/7/2010 | P | PASS |
Tom Arcoraci
|
|
|
lance Phone #: ###-####
|
FIRE-Final Inspection | 7/6/2010 | 7/7/2010 | 7/7/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. I spoke to the store manager about relocating product that had been set up in front of the west most exit doors.
|
BLD-Final | 7/6/2010 | 7/6/2010 | 7/6/2010 | P | NR |
Mike Jordan
|
|
|
Lance Phone #: ###-####. Needs life/safety final.
|
BLD-Final | 5/17/2010 | 5/18/2010 | 5/18/2010 | P | PART |
Tom Arcoraci
|
|
|
shelby Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 5/17/2010 | 5/18/2010 | 5/18/2010 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Steve Keiters permission until the third exit that was to be infilled is provided with approved single action hardware.
|
FIRE-Final Inspection | 5/14/2010 | 5/17/2010 | 5/17/2010 | A | FAIL |
Troy Cobbley
|
|
|
The east most double exit doors that are shown to be removed and infilled have been left as existing. They will need single action hardware installed or approval is needed from the plan reviewer to leave as is or to remove them as an exit all together.
|
FIRE-Final Inspection | 5/10/2010 | 5/11/2010 | 5/11/2010 | A | FAIL |
Troy Cobbley
|
|
|
Shelby Phone #: ###-#### Phone calls weren't returned from Shelby and official was on site. I spoke to a Honk's employee and he stated that the fire extinguishers had not received their annual inspection yet. Also there is a project related fire alarm permit that has not been addressed yet.
|
FIRE-Conference | 5/4/2010 | 5/4/2010 | 5/4/2010 | P | DONE |
Troy Cobbley
|
|
|
I went over life safeyt requirements with Shelby. I noted a blocked sprinkler pendant in the rear exit corridor and a non-functional exit sign/emergency light in the same area.
|
FIRE-Alarm Testing | 5/3/2010 | 5/4/2010 | 5/4/2010 | A | PASS |
Troy Cobbley
|
|
|
Fire alarm is non-applicable for this permit.
|
BLD-Conference | 5/3/2010 | 5/3/2010 | 5/3/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 4/30/2010 | 5/3/2010 | 5/3/2010 | A | PART |
Tom Arcoraci
|
|
|
Please call Shelby before you go. Phone #: ###-#### will meet at 1 pm
|
CHANGE STATUS TO (ISS) | | | 4/8/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 4/8/2010 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 3/26/2010 | | 3/31/2010 | | PASS |
Tim L. Woodard
|
|
|
3/31/2010 10:30:19 TLW - activity updated through activity BLDA022 from case BLD10-00383.
|
Routing - PLAN CHECK | 3/26/2010 | | 3/31/2010 | | PASS |
Tim L. Woodard
|
|
|
Plan modification approved. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/31/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 3/31/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Telephone call | | | 3/31/2010 | | DONE |
|
|
|
left vm for craig at ###-#### - permit (plan mod) ready and fees given
|
Plan Modification Accepted | | | 3/26/2010 | | DONE |
|
|
|
plan modification excepted for BLD10-00383 for the increased tenant area to include existing tenant 5212 (approximately 1,240 sf) the demising wall will be removed to create one large sales area,and the corridor from tenant space 5212 to the common restrooms will be deleted from scope of work.overall the tenant increases from 8,941 sf to 10,103 sf.the construction value does not change. sheets G0.1,A2.0,A2.1,& A6.1 will be affected.routed to Tim Woodard
|
Issue PAID IN FULL permit | | | 3/15/2010 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 2/25/2010 | | 3/5/2010 | | PASS |
Tim L. Woodard
|
|
|
3/5/2010 14:37:12 TLW - activity updated through activity BLDA022 from case BLD10-00383.
|
Routing - PLAN CHECK | 2/26/2010 | | 3/5/2010 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines and Plan Review Report. TLW
|
Routing - FIRE | | | 3/5/2010 | | PASS |
Tim L. Woodard
|
|
|
Field Verify
|
1st review completed | | | 3/5/2010 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 3/5/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 3/5/2010 | | DONE |
Rita DeYoung
|
|
|
|
Telephone call | | | 3/5/2010 | | DONE |
Rita DeYoung
|
|
|
Craig ###-####
|
Permit Ready to Issue | | | 3/5/2010 | | DONE |
Rita DeYoung
|
|
|
|
Routing - PUBLIC WORKS | | | 2/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 2/26/2010 | | 2/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 2/25/2010 | 2/25/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Routing - Addressing | 2/25/2010 | | 2/25/2010 | | PASS |
April Wing
|
|
|
|