Permit Information
Permit NumberBLD10-00385
StatusFinaled
Name CAFCO INC
Site Address 1216 S BROADWAY AVE
Project NameJamaca Me Tan
Customer Number 
ePlanReviewNo
Description
(JAMACA ME TAN - Broadway Plaza) Permit is to occupy and build out a "Vanilla Finish" done under BLD09-01450. Approval contingent upon adhering to the approved plans on file including all redlining and the Plan Review Report. Work to include: construction of interior non-bearing walls to create 17 tanning stations, 2 offices, and 3 storage rooms, installation of new accessible doors, installation of new accessible hardware, and finishes in compliance with chapter 8 of the 2006 IBC. This building is not fire sprinklered. Racking that exceeds 8 ft. in height requires a separate Building Permit be submitted and approved before installation. **TLW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  9/15/2011  
Third Notice 7/7/20108/31/2010 DONE
DetailsTisha Gallop
See Rita and Tisha for final value.
Third Notice 6/9/20106/23/2010 DONE
faxed (didn't go through) so mailed
Second Notice 6/4/20106/4/2010 DONE
First Notice 5/21/20105/25/2010 DONE
Permanent Occupancy UNPAID FEE  5/11/2010 DONE
FIRE-Final Inspection5/3/20105/3/20105/3/2010PPASS
DetailsForrest France
Noted correction items field verified for completion, life safety passed.
BLD-Final4/30/20105/3/20105/3/2010APASS
DetailsJim Storey
final ok
BLD-Final4/30/20104/30/20104/30/2010ADEFR
DetailsJim Storey
Darrin @###-#### per Jim Storey to monday am
FIRE-Final Inspection4/30/20104/30/20104/30/2010PFAIL
DetailsForrest France
Hardware at several doors serving individual tanning rooms does not meet adopted code, missing plans on site, need permit status changed to "issued" prior to final- (currently "under review"), noted jobsite is not in condition for final at this time due to finishes in progress. Discussed issues with contractor- final to be scheduled Mon. 5/3 as agreed.
Plan assigned to (301)4/30/20104/30/20104/30/2010 DONE
DetailsJim Storey
Plan Modification Accepted  4/30/2010 DONE
PLANS/APPL TAKEN TO FRONT DESK  4/30/2010 DONE
Tim out of the office had talked with him last week and needed to change to approved to get insp. of all other trades ok. Reception area is ok per his red lines on this resubmital. 301
CHANGE STATUS TO (ISS)  4/30/2010 DONE
(F) Reprint permit  4/2/2010 DONE
BLD-Framing/Rough-in3/12/20103/15/20103/15/2010APASS
DetailsJim Storey
darrin Phone #: ###-#### need reception counter to be added to plan to meet ada chapter 11 of the ibc
BLD-Framing/Rough-in3/10/20103/11/20103/11/2010ANR
DetailsJim Storey
darrin Phone #: ###-#### ele failled
BLD-Framing/Rough-in3/5/20103/8/20103/8/2010APART
DetailsJim Storey
Darren Phone #: ###-#### need ele aproval to cover ok to one side and do not cover ele for insp.
Case Summary (BLD)  3/5/2010 DONE
DetailsTim L. Woodard
Print Occupancy Form  3/5/2010 DONE
Permit Ready to Issue  3/5/2010 DONE
Telephone call  3/5/2010 DONE
called Everett permit ready and fee given 3-5-10 dld
Issue PAID IN FULL permit  3/5/2010 DONE
Plan assigned to (TLW)2/26/2010 3/4/2010 PASS
DetailsTim L. Woodard
3/4/2010 15:52:45 TLW - activity updated through activity BLDA022 from case BLD10-00385.
Routing - PLAN CHECK2/26/2010 3/4/2010 PASS
DetailsTim L. Woodard
Plans approved with redlines and a Plan Review Report. TLW
Routing - FIRE  3/4/2010 PASS
DetailsTim L. Woodard
Field Verify
1st review completed  3/4/2010 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  3/4/2010 DONE
DetailsTim L. Woodard
Plans ACCEPTED BY PLAN TECH  2/26/2010 DONE
ok per Tim Woodard to take is as a level 1
Application received 2/25/20102/25/2010 DONE
DetailsDarla L Downs
Routing - PLAN CHECK4/19/2010    
DetailsTim L. Woodard