Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD10-00407
StatusFinaled
Name GREGORY LAND & DEVELOPMENT INC
Site Address 921 S ORCHARD ST
Project NameAdvanced Drug Testing
Customer Number 
ePlanReviewNo
Description
(ADVANCED DRUG DETECTION - Orchard Professional Center - Ste A) Permit is to remodel an existing 1,186 square foot office space. Approval contingent upon adhering to the approved plans on file including all redlining and attached details. Work to include: construction of interior non-bearing walls to create three urinal stalls, installation of two new sinks, installation of three new urinals, and finishes in compliance with chapter 8 of the 2006 IBC. This building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 8/17/20108/4/2010 DONE
Third Notice 7/20/20108/3/2010 DONE
faxed
Second Notice 7/3/20107/15/2010 DONE
First Notice6/16/20106/16/20106/23/2010 DONE
DetailsTom Arcoraci
BLD-Final6/15/20106/16/20106/16/2010PPASS
DetailsTom Arcoraci
DOC - Permit Finaled6/16/20106/16/20106/16/2010PPASS
DetailsTom Arcoraci
BLD-Aging Inspection6/15/20106/15/20106/15/2010 PASS
DetailsTom Arcoraci
FIRE-Final Inspection4/14/20104/15/20104/15/2010PPASS
DetailsTroy Cobbley
life safety passed
BLD-Final4/14/20104/15/20104/15/2010PPASS
DetailsTom Arcoraci
Scott. Phone #: ###-####
FIRE-Final Inspection4/15/20104/15/20104/15/2010PFAIL
DetailsTroy Cobbley
Provide approved single action hardware for the new doors.
BLD-Framing/Rough-in3/12/20103/12/20103/12/2010PPASS
DetailsTom Arcoraci
BLD-Framing/Rough-in3/11/20103/12/20103/12/2010APART
DetailsTom Arcoraci
Scott Phone #: ###-####
Telephone call  3/9/2010 DONE
Details
t/c w scott at ###-#### - permit ready and fees given - also need gc name and rce#
Permit Ready to Issue  3/9/2010 DONE
Details
Issue PAID IN FULL permit  3/9/2010 DONE
Routing - PLAN CHECK3/3/2010 3/8/2010 PASS
DetailsTim L. Woodard
Plans approved with redlining and attached plan review report. TLW
Plan assigned to (TLW)3/1/2010 3/8/2010 PASS
DetailsTim L. Woodard
3/8/2010 13:58:49 TLW - activity updated through activity BLDA022 from case BLD10-00407.
Routing - FIRE  3/8/2010 PASS
DetailsTim L. Woodard
1st review completed  3/8/2010 PASS
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  3/8/2010 DONE
DetailsTim L. Woodard
Case Summary (BLD)  3/8/2010 DONE
DetailsTim L. Woodard
Print Occupancy Form  3/8/2010 DONE
Details
Routing - PUBLIC WORKS3/2/2010 3/3/2010 PASS
DetailsConnie Baumgartner
Routing PW Sewer Rating3/3/2010 3/3/2010 PASS
DetailsConnie Baumgartner
Routing - Addressing3/2/2010 3/2/2010 PASS
DetailsApril Wing
Application received 3/1/20103/1/2010 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  3/1/2010 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  3/1/2010 DONE
DetailsTisha Gallop