Case Summary (BLD) | | | 6/20/2012 | | DONE |
Tim L. Woodard
|
|
|
|
Second Notice | | 8/12/2010 | 8/12/2010 | | DONE |
|
|
|
|
First Notice | | 7/22/2010 | 8/2/2010 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 7/12/2010 | | DONE |
|
|
|
|
BLD-Final | 7/6/2010 | 7/7/2010 | 7/7/2010 | A | PASS |
Jim Sly
|
|
|
Marvin Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 7/7/2010 | 7/7/2010 | 7/7/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. The emergency lights have been repaired and the door mags have been addressed under a separate permit.
|
BLD-Final | 6/22/2010 | 6/23/2010 | 6/23/2010 | P | NR |
Jim Sly
|
|
|
marvin Phone #: ###-####
|
FIRE-Final Inspection | 6/22/2010 | 6/23/2010 | 6/23/2010 | A | FAIL |
Forrest France
|
|
|
Access-controlled egress doors must be in compliance with IFC sec. 1008.1.3.4. Also noted two non-functional EM lights. Remainder of life safety items appear satisfactory.
|
FIRE-Conference | 5/18/2010 | 5/19/2010 | 5/20/2010 | P | NH |
Forrest France
|
|
|
Marvin Phone ###-#### Phoned contact twice and left voice mail- no one on site and no return call.
|
FIRE-Conference | 5/17/2010 | 5/18/2010 | 5/19/2010 | P | CANC |
Troy Cobbley
|
|
|
Marvin Phone ###-####
|
FIRE-Final Inspection | 5/14/2010 | 5/17/2010 | 5/18/2010 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for tomorrow.
|
FIRE-Conference | 5/13/2010 | 5/14/2010 | 5/14/2010 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for monday per Marvin.
|
FIRE-Conference | 5/13/2010 | 5/13/2010 | 5/13/2010 | P | DONE |
Troy Cobbley
|
|
|
I spoke to marvin about the life safety requirements.
|
FIRE-Conference | 5/12/2010 | 5/12/2010 | 5/12/2010 | P | DONE |
Troy Cobbley
|
|
|
This conference was for fire sprinkler issues. It appears sprinkler protection is ok except for an existing sprinkler head that should have been demo'd with the old ceiling. This work will require a permit.
|
BLD-Framing/Rough-in | 5/11/2010 | 5/12/2010 | 5/12/2010 | A | PART |
Jim Sly
|
|
|
Marvin - call for access Phone #: ###-#### OK to cover framing.....After sprinkler inspection. Called Marvin to advise.
|
Issue PAID IN FULL permit | | | 4/9/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (SRZ) | 4/1/2010 | 4/1/2010 | 4/8/2010 | | PASS |
Sam Zahorka
|
|
|
4/8/2010 10:25:42 SRZ - activity updated through activity BLDA022 from case BLD10-00661.
|
Routing - PLAN CHECK | 4/7/2010 | | 4/8/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/8/2010 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 4/8/2010 | | DONE |
|
|
|
|
Telephone call | | | 4/8/2010 | | DONE |
|
|
|
left vm for kyle at ###-#### - permit ready and fees given - also need gc name, rce# and ACHD receipt
|
Permit Ready to Issue | | | 4/8/2010 | | DONE |
|
|
|
|
Routing - FIRE | 4/5/2010 | | 4/7/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 4/7/2010 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/2/2010 | | 4/5/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Sewer Rating | 4/5/2010 | | 4/5/2010 | | PASS |
Connie Baumgartner
|
|
|
|
(F) Reprint permit | | | 4/2/2010 | | DONE |
|
|
|
|
Routing - Addressing | 4/2/2010 | | 4/2/2010 | | PASS |
April Wing
|
|
|
|
Case Summary (BLD) | | | 4/2/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 4/1/2010 | | 4/2/2010 | | PASS |
Sam Zahorka
|
|
|
|
Pending Assignment by JCB | 3/30/2010 | | 4/1/2010 | | DONE |
Jason Blais
|
|
|
|
Application received | | 3/30/2010 | 3/30/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 3/30/2010 | | PASS |
Sam Zahorka
|
|
|
Borderline Minor T.I. - technicaly a change of occupancy from a M under the 97 UBC to a B occupancy.
|
Plans ACCEPTED BY PLAN TECH | | | 3/30/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/30/2010 | | DONE |
Tisha Gallop
|
|
|
|