BLD-Final | 6/25/2010 | 6/28/2010 | 6/28/2010 | A | PASS |
Jim Sly
|
|
|
larry Phone #: ###-#### C/C issued
|
DOC - Permit Finaled | 6/28/2010 | 6/28/2010 | 6/28/2010 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 6/1/2010 | 6/1/2010 | 6/1/2010 | P | PASS |
Jim Sly
|
|
|
larry Phone #: ###-####
|
BLD-Framing/Rough-in | 5/27/2010 | 5/28/2010 | 5/28/2010 | A | PASS |
Jim Sly
|
|
|
Larry Phone #: ###-####
|
BLD-Footing | 5/11/2010 | 5/11/2010 | 5/11/2010 | P | PASS |
Jim Sly
|
|
|
Bill Phone #: ###-####
|
Issue PAID IN FULL permit | | | 5/10/2010 | | DONE |
|
|
|
|
OVERRIDE | | | 5/7/2010 | | |
|
|
|
|
Telephone call | | | 5/7/2010 | | DONE |
|
|
|
emailed mike - permit ready and fees given
|
Permit Ready to Issue | | | 5/7/2010 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 5/5/2010 | 5/5/2010 | 5/6/2010 | | PASS |
Perry Paine
|
|
|
5/6/2010 11:44:44 PEP - activity updated through activity BLDA022 from case BLD10-00785.
|
Case Summary (BLD) | | | 5/6/2010 | | |
|
|
|
|
1st review completed | | | 5/6/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/6/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/6/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | | | 5/6/2010 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/29/2010 | | 5/6/2010 | | PASS |
Carl D Madsen
|
|
|
|
Plan assigned to (CDM) | 4/13/2010 | 4/13/2010 | 5/5/2010 | | DEFR |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 4/29/2010 | | DONE |
|
|
|
contractor submitted whole new house plan
|
Routing - PLANNING | 4/29/2010 | | 4/29/2010 | | PASS |
Joshua Johnson
|
|
|
|
Route to Impact Fee Review | 4/13/2010 | 4/16/2010 | 4/23/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 4/21/2010 | | 4/21/2010 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 4/19/2010 | | 4/20/2010 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 4/15/2010 | | 4/20/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Plan resubmittals received | | | 4/19/2010 | | |
Tisha Gallop
|
|
|
received two 8 1/2" x 11" site plans and two full size site plans; inserted into plans by LEG and routed to addressing
|
Application received | | 4/13/2010 | 4/13/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 4/13/2010 | | PASS |
Tisha Gallop
|
|
|
|
Routing - Addressing | 4/13/2010 | | 4/13/2010 | | FAIL |
April Wing
|
|
|
Site plan does not match lot and block.
|