Permit NumberBLD10-00813
StatusFinaled
Name MARK POFFENBERGER
Site Address 10552 W GARVERDALE CT
Project NameValley Vision Care
Customer Number 
ePlanReviewNo
Description
(VALLEY VISION - Five Mile Professional Park - Building #3 - Ste# 906) Permit is to remodel and combine two spaces to create a new 1,785 square feet office space. Approval contingent upon adhering to the approved plans on file. Work to include: [construction of interior non-bearing walls to create a new fully accessible bathroom, a new break room, two exam rooms, a new contact lens room, and a pre-test room], demolition of existing non-bearing wall to combine a 624 sf space and a 1,161 sf space, installation of new accessible bathroom fixtures, installation of new hand sink, relocate existing lighting, installation of new sinks, and finishes in compliance with chapter 8 of the 2006 IBC. This building is not fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 8/24/20108/19/2010 DONE
Second Notice 8/9/20108/19/2010 DONE
First Notice 7/24/20107/30/2010 DONE
BLD-Final7/13/20107/14/20107/14/2010APASS
DetailsJim Sly
debbie Phone #: ###-####
OK for Perm Occ.
Permanent Occupancy  7/14/2010 DONE
DetailsTisha Gallop
FIRE-Final Inspection6/23/20106/28/20106/28/2010APASS
DetailsTroy Cobbley
The thumb turn lock that has been installed on the main entry/exit has been defurred to the building inspector. I notified debbie, at the vision office, of what needs to be done. I also notified Jim Sly about this follow up.
FIRE-Final Inspection6/22/20106/23/20106/23/2010PFAIL
DetailsForrest France
The main entry/exit door is equipped with a manual thumbturn. See plan review notes for details pertaining.
FIRE-Final Inspection5/25/20105/25/20105/25/2010PFAIL
DetailsTroy Cobbley
The door hardware on both of the exit doors had been changed to thumbturns. I went over acceptable hardware with Debbie.
BLD-Final5/14/20105/17/20105/17/2010PNR
DetailsJim Sly
richard Phone #: ###-####
Need Fire Final
FIRE-Final Inspection5/14/20105/17/20105/17/2010AFAIL
DetailsTroy Cobbley
Provide single action hardware and remove the thumbturn deadbolt on the north exit door and mount the fire extinguisher. I spoke with the owner about doors that are swinging the wrong way as marked in red on the plans.
BLD-Final5/13/20105/14/20105/14/2010PNR
DetailsJim Sly
Kurt Phone #: ###-####
Need Fire final.
BLD-Conference4/21/20104/22/20104/22/2010ADONE
DetailsJim Sly
Kurt Olson Phone #: ###-####
Plan assigned to (TLW)4/16/2010 4/21/2010 PASS
DetailsTim L. Woodard
4/21/2010 08:42:15 TLW - activity updated through activity BLDA022 from case BLD10-00813.
Routing - PLAN CHECK4/20/2010 4/21/2010 PASS
DetailsTim L. Woodard
Plans approved with multible redlines. Refer to plan review report. TLW
Routing - FIRE  4/21/2010 PASS
DetailsTim L. Woodard
1st review completed  4/21/2010 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  4/21/2010 DONE
DetailsTim L. Woodard
Case Summary (BLD)  4/21/2010 DONE
DetailsTim L. Woodard
Print Occupancy Form  4/21/2010 DONE
Telephone call  4/21/2010 DONE
left vm for mark at ###-#### - permit ready and fees given - also need gc name, rce# and a revised cert of value
Telephone call  4/21/2010 DONE
left vm for liz cooper at ###-####x4 - permit ready and fees given - also need gc name, rce# and a revised cert of value
Permit Ready to Issue  4/21/2010 DONE
Details
Issue PAID IN FULL permit  4/21/2010 DONE
Routing - PUBLIC WORKS4/16/2010 4/20/2010 PASS
DetailsConnie Baumgartner
Routing PW Sewer Rating4/19/2010 4/19/2010 PASS
DetailsConnie Baumgartner
Application received 4/16/20104/16/2010 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  4/16/2010 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  4/16/2010 DONE
DetailsTisha Gallop