Permit Information
Permit NumberBLD10-00831
StatusFinaled
Name ROCKY MOUNTAIN MANAGEMENT
Site Address 805 W IDAHO ST
Project NameBOISE CITY NATL BANK BLDG
Customer Number 
ePlanReviewNo
Description
(BOISE CITY NATIONAL BANK BUILDING - CORE REMODEL) (8-18-10 PLAN MODIFICATION TO INSTALL AN EXTERIOR ENTRANCE DOOR FROM THE 1ST STORY MAIN ENTRANCE COMMON LOBBY TO THE OUTSIDE AT IDAHO STREET. THE DOOR WILL BE RECESSED SO THAT IT WILL NOT SWING INTO THE PUBLIC WAY. WORK INCLUDES EXTERIOR WALLS WITH R-13 INSULATION AND AN EXTERIOR STUCCO SYSTEM. THE EXTERIOR CANOPY IS NOT COVERED UNDER THIS PERMIT.) The fire sprinkler system substitutes for the 1-hr fire-resistance-rating of the building structure. To remodel the core areas within an existing 5 story building (basement, 4 stories above grade plane, and enclosed mezzanine above the 4th story). Work is to include an interior non-fire-resistance-rated exit discharge on the ground floor to serve an existing stairway enclosure, a non-fire-resistance-rated corridor on the 2nd story to connect stairway enclosures, new suspended ceilings within some core areas, and new finishes in existing restrooms. Two new doorways will be created in existing masonry walls. Steel headers and trimmers will be provided. Common restrooms on the 1st story, 2nd story, 3rd story, and 4th story are required to be accessible to the disabled as defined by current standards, unless technically infeasible. Upgrades will be done where necessary to ensure compliance to the maximum extent possible. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. Some of the trade-offs permitted because this building is fully fire sprinklered are (1) egress from an enclosed stairway is allowed through an interior non-fire-resistance-rated lobby on the ground floor and (2) non-fire-resistance-rated corridors are allowed on all levels. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. Existing fire sprinkler heads will be replaced with quick-response sprinklers in the future on a floor by floor basis as allowed by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Agreement of Future work5/6/2010 6/12/2014 DONE
DetailsScott Arellano
Refer to IFC plan review comments under BLD10-00831 for details of the Fire Protection upgrade progression.
Third Notice 3/30/20124/17/2012 DONE
Third Notice 3/6/20123/15/2012 DONE
mailed to Rocky Mountain Development attn: Matthew Witt.(Rita ok'd to send to applicant)
Telephone call  3/7/2012  
3-7-12 called Scott Gordan from Pacific Sierra Construction about a returned second notice. he said to call Rocky Mountain Management @###-#### and get with Matt Whitt x 218(project Manager) or Chris Pealand for final job values
Second Notice 2/26/20123/1/2012 DONE
First Notice 2/12/20122/16/2012 DONE
BLD-Aging Inspection12/22/201112/23/201112/29/2011APASS
DetailsDave Hannah
Zoning Approval12/29/201112/29/201112/29/2011 DONE
DetailsSarah Schafer
DOC - L/C Approved  12/29/2011 DONE
DetailsBarbara Stitt
FIRE-Final Inspection11/22/201111/22/201111/22/2011PPASS
DetailsForrest France
Noted correction items verified for completion. Fire life safety finaled.
BLD-Aging Inspection3/17/20113/17/20113/21/2011 PASS
DetailsDave Hannah
BLD-Conference1/6/20111/6/20111/6/2011PPASS
DetailsDave Hannah
BLD-Aging Inspection1/6/20111/6/20111/6/2011 PASS
DetailsDave Hannah
BLD-Framing/Rough-in11/1/201011/1/201011/1/2010PPASS
DetailsDave Hannah
Brocl Nelson-Steel Stud framing inspection please Phone #: ###-####
BLD-Other10/21/201010/21/201010/21/2010APASS
DetailsDave Hannah
crew working on new section of hallway talked about walls and how to sheetrock
BLD-Aging Inspection10/21/201010/21/201010/21/2010 PASS
DetailsDave Hannah
CHANGE STATUS TO (ISS)  8/25/2010 DONE
DetailsTisha Gallop
picked up and paid for plan mod
Plan assigned to (CJW)8/10/2010 8/23/2010 PASS
DetailsCarl Westfall
8/23/2010 09:08:17 CJW - activity updated through activity BLDA022 from case BLD10-00831.
Routing - PLAN CHECK8/19/2010 8/23/2010 DONE
DetailsCarl Westfall
PLANS/APPL TAKEN TO FRONT DESK  8/23/2010 DONE
Inspection Record Card- Bld  8/23/2010 DONE
Permit Ready to Issue  8/23/2010 DONE
Telephone call  8/23/2010 DONE
DetailsBarbara Stitt
Called and told David Ruby plan mod is ready and fees due on 8-23-10 @ 2:05pm BAS
Routing - PLANNING8/18/2010 8/19/2010 PASS
DetailsJosh Wilson
OK per CZC10-00125
Routing - PLAN CHECK8/11/2010 8/17/2010 PASS
DetailsCarl Westfall
Routed to Sarah.
Plan Modification Accepted  8/11/2010  
DetailsCarl Westfall
Rec'd plan mod to add the main entrance door and adjacent side lights - sheet a2.11
BLD-Final8/6/20108/6/20108/7/2010PNR
DetailsDave Hannah
scott Phone #: ###-####
FIRE-Final Inspection8/6/20108/6/20108/6/2010PFAIL
DetailsForrest France
Corrections items include; repair one exit sign, one EM light and provide directional arrow at one exit sign per plan on the third floor. Repair one exit/EM light at the second floor. Scope of work per the permit description for the new exit discharge at the ground floor SW corner has not been done, item #15 per the fire code review is not yet provided.
FIRE-Final Inspection8/3/20108/4/20108/5/2010PNR
DetailsForrest France
Scott - life safety Phone #: ###-####
BLD-Final8/5/20108/5/20108/5/2010PNR
DetailsDave Hannah
BLD-Final8/4/20108/5/20108/5/2010ANR
DetailsDave Hannah
Scott Phone #: ###-####
BLD-Other7/28/20107/29/20107/29/2010APASS
DetailsJim Storey
scott - 1st floor - ok to cover Phone #: ###-#### 1st floor ok
BLD-Other7/15/20107/19/20107/19/2010APART
DetailsDave Hannah
Scott - ceiling Phone #: ###-#### ok to cover ceiling on second floor
FIRE-Conference6/22/20106/23/20106/23/2010PDONE
DetailsForrest France
On site visit regarding fire life safety requirements. Noted fire alarm and sprinkler contractors have commenced work without issued permits- double fees will apply. A stop work order may be applied if work continues without authorization.
BLD-Framing/Rough-in6/22/20106/22/20106/22/2010PPASS
DetailsDave Hannah
ok to cover front lobby
BLD-Footing6/21/20106/22/20106/22/2010ACANC
DetailsDave Hannah
Scott Phone #: ###-####
Issue PAID IN FULL permit  5/20/2010 DONE
Telephone call  5/18/2010 DONE
left vm for david at ###-#### - permit ready and fees given
Permit Ready to Issue  5/18/2010 DONE
Details
Plan assigned to (CJW)4/19/2010 5/17/2010 PASS
DetailsCarl Westfall
5/17/2010 11:12:59 CJW - activity updated through activity BLDA022 from case BLD10-00831.
Routing - PLAN CHECK5/6/2010 5/17/2010 PASS
DetailsCarl Westfall
Drawings approved after the resubmittal review.
Routing - PLANNING5/17/2010 5/17/2010 PASS
DetailsSarah Schafer
Approved per the zoning certificate. All work to be interior with this permit. No changes to the main exterior doors along Idaho Street.
PLANS/APPL TAKEN TO FRONT DESK  5/17/2010 DONE
Inspection Record Card- Bld  5/17/2010 DONE
Routing - FIRE4/30/20104/30/20105/6/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  5/6/2010 FAIL
Failed Planning, Plan Check
Plan resubmittals received  5/5/2010 DONE
DetailsTisha Gallop
received two copies of response and plan sheets a0.01, a0.03, a6.11; taken to Carl Westfall
Route to Impact Fee Review4/30/20105/5/20105/4/2010 PASS
DetailsCindy M. Gould
Tenant improvement
Routing - PLAN CHECK4/22/2010 4/30/2010 FAIL
DetailsCarl Westfall
The IBC plan review was started on April 23, 2010 and finished on April 30, 2010. Revised drawings were required. See the plan review report.
Routing - Design Review4/22/2010 4/22/2010 FAIL
DetailsSarah Schafer
Sarah Schafer - One existing exterior door to be replaced with window and existing windows to be replaced with new entry door into lobby - See sheets A2.01 and A2.11.

The zoning certificate has not yet been filed. David Ruby has been contacted. I have let him know that I will need that application prior to being able to sign off on the building permit.
Routing - PUBLIC WORKS4/20/2010 4/22/2010 PASS
DetailsConnie Baumgartner
Routing PW Sewer Rating4/21/2010 4/21/2010 PASS
DetailsConnie Baumgartner
Routing - Addressing4/20/2010 4/20/2010 PASS
DetailsApril Wing
Plans ACCEPTED BY PLAN TECH  4/19/2010 DONE
Recd Pcfee & Taken To Pln CK  4/19/2010 DONE
Pending Assignment by JCB4/19/2010 4/19/2010 DONE
DetailsJason Blais
Application received 4/16/20104/16/2010 DONE
DetailsAlexandra L. DeYoung
Intake Approval  4/16/2010 PASS