Second Notice | | 4/10/2011 | 4/27/2011 | | DONE |
Christina Prado
|
|
|
Faxed 4/27/11. Received 4-28-2011
|
First Notice | | 3/18/2011 | 3/31/2011 | | DONE |
|
|
|
|
BLD-Final | 3/7/2011 | 3/8/2011 | 3/8/2011 | A | PASS |
Mike Jordan
|
|
|
matt Phone #: ###-####. ok for perm. occ.
|
FIRE-Final Inspection | 3/4/2011 | 3/7/2011 | 3/8/2011 | A | PASS |
Forrest France
|
|
|
Fire life safety passed.
|
Permanent Occupancy UNPAID FEE | | | 3/8/2011 | | DONE |
|
|
|
|
BLD-Final | 3/4/2011 | 3/4/2011 | 3/4/2011 | P | NR |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Neeeds life/safety finals.
|
BLD-Framing/Rough-in | 2/24/2011 | 2/24/2011 | 2/24/2011 | P | PASS |
Mike Jordan
|
|
|
MATT Phone #: ###-####. Interior steel stud wall. Noted no rough ins in this wall.
|
Issue PAID IN FULL permit | | | 2/23/2011 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/2/2011 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/2/2011 | | DONE |
|
|
|
|
Telephone call | | | 2/2/2011 | | |
|
|
|
2-2-11 called Matt Rhees permit ready and fee given Also need ACHD ///dld
|
Routing - PLANNING | 1/29/2011 | | 2/1/2011 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 2/1/2011 | | 2/1/2011 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 2/1/2011 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2011 | | |
|
|
|
|
Routing - PLAN CHECK | 1/24/2011 | | 1/29/2011 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 1/24/2011 | | 1/24/2011 | | PASS |
David Moser
|
|
|
CUP10-00031; OK
|
Plan resubmittals received | | | 1/19/2011 | | |
Barbara Stitt
|
|
|
Received 3 copies of A3.0 and taken to Carl Madsen
|
Extend Review Timeline | | | 10/22/2010 | | DONE |
Jason Blais
|
|
|
|
Routing - PLAN CHECK | 8/10/2010 | | 8/10/2010 | | FAIL |
Carl D Madsen
|
|
|
Site Plan showing compliance with the CZC and CUP is required 8-10-10 CDM
|
Plan resubmittals received | | | 8/4/2010 | | |
Carl D Madsen
|
|
|
rec'd two copies of condition use report and zoning cert report - taken to Carl M
|
Routing - PLANNING | 5/13/2010 | | 5/13/2010 | | FAIL |
Cody Riddle
|
|
|
Office use requires CUP approval in M-1 zone.
|
Plan assigned to (CDM) | 4/22/2010 | 4/22/2010 | 5/12/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 4/26/2010 | | 5/12/2010 | | FAIL |
Carl D Madsen
|
|
|
Use does not comply with the land use zone CDM
|
1st review completed | | | 5/12/2010 | | FAIL |
|
|
|
Use does not comply with the land use zone
|
Routing PW Sewer Rating | 4/26/2010 | | 4/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 4/22/2010 | | 4/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 4/23/2010 | | 4/23/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 4/22/2010 | 4/22/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/22/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/22/2010 | | DONE |
Tisha Gallop
|
|
|
|