Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD10-00880
StatusFinaled
Name K2 CONSTRUCTION
Site Address 4600 S APPLE ST
Project NameMotive Power
Customer Number 
ePlanReviewNo
Description
Motive Power - Locker Room Addition - To construct a 270 square foot, one story, metal framed locker addition on the north side of the existing 101,605 square foot locomotive repair facility. This permit also includes any associated site improvements. The certificate of occupancy is for the addition only. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 8/9/20108/16/2010 DONE
BLD-Final7/29/20107/30/20107/30/2010APASS
DetailsJim Sly
flloyd Phone #: ###-####
OK for Perm Occ.
Zoning Approval7/30/20107/30/20107/30/2010 PASS
DetailsAndrea Tuning
Permanent Occupancy UNPAID FEE  7/30/2010 DONE
DetailsTisha Gallop
FIRE-Final Inspection7/29/20107/29/20107/29/2010PPASS
DetailsForrest France
Fire life safety passed inspection. One additional fire extinguisher to be posted as discussed.
BLD-Energy code compliance7/19/20107/20/20107/20/2010APASS
DetailsJim Storey
FLOYD Phone #: ###-####
BLD-Framing/Rough-in7/8/20107/9/20107/9/2010APART
DetailsJim Storey
harvey Phone #: ###-#### ok to cover exterior/ need web stifner at bearring point for knock out to close to bearring point.
BLD-Foundation6/29/20106/29/20106/29/2010PPASS
DetailsJim Storey
harvey Phone #: ###-####
Issue PAID IN FULL permit  6/24/2010 DONE
DetailsTisha Gallop
Routing - FIRE6/18/2010 6/18/2010 PASS
DetailsScott Arellano
Attached updated IFC comments to plans
Routing - PLAN CHECK6/18/2010 6/18/2010 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  6/18/2010 DONE
DetailsJohn Menard
Inspection Record Card- Bld  6/18/2010 DONE
Print Occupancy Form  6/18/2010 DONE
DetailsTisha Gallop
Print Occupancy Form  6/18/2010 DONE
DetailsTisha Gallop
Telephone call  6/18/2010 DONE
DetailsTisha Gallop
called Rocky and left message permit is ready and fee and need ACHD.
Permit Ready to Issue  6/18/2010 DONE
DetailsTisha Gallop
Plan assigned to (JCM)4/26/2010 6/18/2010 PASS
DetailsJohn Menard
6/18/2010 13:26:15 JCM - activity updated through activity BLDA022 from case BLD10-00880.
Routing - PLAN CHECK5/12/2010 6/18/2010 PASS
DetailsJohn Menard
Plan resubmittals requested  6/4/2010 DONE
DetailsJohn Menard
E-mailed the architect requesting the required alternate or upgrade agreement letter. JCM
Plan resubmittals received  6/3/2010 DONE
received 1 reply letter and 2 copies of sheets A0.1,A0.1,A1.1 A2.1,EN1.1 taken to John M
Route to Impact Fee Review5/10/20105/13/20105/17/2010 PASS
DetailsCindy M. Gould
Routing - FIRE5/10/20105/10/20105/12/2010 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
1st review completed  5/12/2010 FAIL
Failed Plan Check, Fire
Plan resubmittals requested  5/10/2010 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK4/29/2010 5/10/2010 FAIL
DetailsJohn Menard
John Menard
Route to Impact Fee Review4/26/20104/29/20105/6/2010 PASS
DetailsCindy M. Gould
Routing - PLANNING4/29/2010 4/29/2010 PASS
DetailsAndrea Tuning
czc10-00037 Andrea
Routing - Erosion and Sediment4/28/2010 4/29/2010 PASS
DetailsSteven Webb
ESC10-00336 plan waiver approved with attached conditions.
Routing - PUBLIC WORKS4/27/2010 4/28/2010 PASS
DetailsBeverly Mountain
Routing - PLANNING Land Div4/26/2010 4/27/2010 PASS
DetailsTodd Tucker
Routing - Addressing4/27/2010 4/27/2010 PASS
DetailsApril Wing
Application received 4/23/20104/26/2010 DONE
DetailsTisha Gallop
Pending Assignment by JCM4/26/2010 4/26/2010 BLDA
DetailsJohn Menard
4/26/2010 10:15:30 JCM - activity updated through activity BLDA166 from case BLD10-00880.
Plans ACCEPTED BY PLAN TECH  4/23/2010 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  4/23/2010 DONE
DetailsTisha Gallop