First Notice | | 2/6/2011 | 2/7/2011 | | DONE |
|
|
|
This permit finaled on the web by Brandon Byington
|
Permanent Occupancy | | | 1/27/2011 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 1/18/2011 | 1/18/2011 | 1/18/2011 | P | PASS |
Mike Jordan
|
|
|
andy Phone #: ###-####Ok for perm. occ.
|
BLD-Final | 12/6/2010 | 12/7/2010 | 12/7/2010 | P | PART |
Mike Jordan
|
|
|
andy Phone #: ###-####. Ok for temp. occ. Need final letter from special inspection agency.
|
FIRE-Final Inspection | 12/6/2010 | 12/7/2010 | 12/7/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
Temporary Occupancy | 12/7/2010 | 3/7/2011 | 12/7/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 12/3/2010 | 12/6/2010 | 12/6/2010 | P | NR |
Mike Jordan
|
|
|
Andy Phone #: ###-####. Life/safety failed.
|
FIRE-Final Inspection | 12/3/2010 | 12/6/2010 | 12/6/2010 | A | FAIL |
Troy Cobbley
|
|
|
Provide indicator at the keyed hardware on the main exit door, repire the inactive leaf locking hardware on the double doors to the service bay and provide "No parking fire lane " signs as discussed.
|
Zoning Approval | 12/1/2010 | 12/1/2010 | 12/1/2010 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 11/18/2010 | 11/19/2010 | 11/19/2010 | A | PASS |
Mike Jordan
|
|
|
ANDY Phone #: ###-####. Ceiling grid ok.
|
BLD-Energy code compliance | 9/21/2010 | 9/22/2010 | 9/22/2010 | A | PASS |
Mike Jordan
|
|
|
Andy Phone #: ###-####
|
BLD-Framing/Rough-in | 9/16/2010 | 9/17/2010 | 9/17/2010 | P | PASS |
Mike Jordan
|
|
|
Andy Phone #: ###-####. Interior steel stud framed walls only.
|
BLD-Framing/Rough-in | 9/2/2010 | 9/3/2010 | 9/3/2010 | A | PART |
Mike Jordan
|
|
|
Andy Phone #: ###-####. Exterior curtain walls only, pending electrical rough in inspection.
|
BLD-Concrete | 8/11/2010 | 8/12/2010 | 8/12/2010 | A | PART |
Mike Jordan
|
|
|
Andy-pouring at 7:00am Phone #: ###-####. Concrete placement in progress for slab on grade. All reinforcement inspected by MTI.
|
BLD-Foundation | 7/26/2010 | 7/27/2010 | 7/27/2010 | A | PASS |
Jim Storey
|
|
|
Bob Phone #: ###-####
|
BLD-Foundation | 7/23/2010 | 7/26/2010 | 7/26/2010 | P | PART |
Jim Sly
|
|
|
BOB Phone #: ###-#### OK pending MTI special inspection, tests and approvals.
|
BLD-Foundation | 7/21/2010 | 7/22/2010 | 7/22/2010 | P | PASS |
Mike Jordan
|
|
|
bob - mud at 2:00 Phone #: ###-####. West stemwall, interior and perimeter column pedestals.
|
BLD-Footing | 7/20/2010 | 7/21/2010 | 7/21/2010 | P | PASS |
Mike Jordan
|
|
|
Bob Phone #: ###-####. Interior comlumn pad footings, perimeter column pad footings and west footing. Noted project will have special inspection.
|
Print Occupancy Form | | | 7/14/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/14/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 7/14/2010 | | DONE |
|
|
|
Spoke with Pat Walsh and told him that permit is ready, fees due, need ACHD information and need Kreizenbeck Constructors to sign GC form
|
Issue PAID IN FULL permit | | | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Received Certificate of Value | | | 7/13/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (JCM) | 5/5/2010 | | 7/13/2010 | | PASS |
John Menard
|
|
|
7/13/2010 14:57:56 JCM - activity updated through activity BLDA022 from case BLD10-00988.
|
Routing - PLAN CHECK | 7/1/2010 | | 7/13/2010 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 7/13/2010 | | PASS |
John Menard
|
|
|
Reviewed and approved plan revisions. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2010 | | DONE |
John Menard
|
|
|
|
Plan resubmittals received | | | 7/12/2010 | | DONE |
Tisha Gallop
|
|
|
received two coipes of response, three copes of plan sheets G-002, A-111V, A-113V, A-121V, A-213V, A-312V, A-111A, A-213A, A-301A, A-601A, P-001, P-111, M-111; inserted into plans by arch. rep. and taken back to John Menard.
|
Routing - FIRE | 6/28/2010 | 6/28/2010 | 7/1/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 7/1/2010 | | FAIL |
|
|
|
Failed Public Works, Plumbing
|
Route to Impact Fee Review | 6/28/2010 | 7/1/2010 | 6/29/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals requested | | | 6/28/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing - PLAN CHECK | 6/18/2010 | | 6/28/2010 | | FAIL |
John Menard
|
|
|
|
Routing Off Site - STRUCTURAL | 6/14/2010 | | 6/21/2010 | | PASS |
John Menard
|
|
|
Received letter from consulting structural engineer approving structural revisions. JCM
|
Routing - PLUMBING | 6/16/2010 | | 6/18/2010 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 6/15/2010 | | 6/16/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Solid Waste | 6/16/2010 | | 6/16/2010 | | PASS |
Peter J. McCullough
|
|
|
New enclosure approved
|
Plan resubmittals received | | | 6/15/2010 | | DONE |
Tisha Gallop
|
|
|
received three coipes of sheet A-101and Trach enclosure detail; inserted by arch. rep. and taken back to JCM
|
Routing - PLAN CHECK | 5/20/2010 | | 6/15/2010 | | |
John Menard
|
|
|
|
Telephone call | | | 6/14/2010 | | DONE |
Tisha Gallop
|
|
|
called action couriers for pick up of structural resubs
|
Plan resubmittals received | | | 6/11/2010 | | DONE |
Tisha Gallop
|
|
|
received transmittal, three copies of plumbing response, structural response, supplemental calculations and plan sheets P-111, P-113, P-411, S-001, S-202V, S-301V, S-101A, S-201A, S-202A, S-203A, S-302A; inserted into plans by arch. rep. and taken back to John Menard on 6/14/10.
|
Routing Off Site - STRUCTURAL | 5/6/2010 | | 5/27/2010 | | FAIL |
John Menard
|
|
|
Received comment list from consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 5/27/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLUMBING | 5/18/2010 | | 5/20/2010 | | FAIL |
Bill VanDegrift
|
|
|
R.P. not required on the eyewash/shower in VW shop. fixtureschedule shows 1 1/4' hot and cold water to eyewash/shower- no hot water shown on the plan. flammable liquids interceptors require a ventfrom the vapor chamber to roof. see attached detail. hotsy may need backflow protection. hose bibs in Audi service bay require an r.p. note 5 on page P113, rough in for sink, no water shown. Audi side shows DGBP-1, not listed on fixture schedule.
|
Routing - PLANNING | 5/20/2010 | | 5/20/2010 | | PASS |
Josh Wilson
|
|
|
DRH10-00002
|
Routing - PUBLIC WORKS | | | 5/18/2010 | | FAIL |
|
|
|
|
Routing - Erosion and Sediment | 5/18/2010 | | 5/18/2010 | | PASS |
Steven Webb
|
|
|
|
Routing PW Drainage | 5/7/2010 | | 5/18/2010 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Rating | | | 5/18/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | | | 5/14/2010 | | PASS |
Walt Baumgartner
|
|
|
Rvwed by Brett. West Boise Sewer Dist. Plans indicate 1500 gal interceptor for service area. Approved flammable design required by City Plumbing Dept.
|
Routing PW Solid Waste | 5/13/2010 | | 5/13/2010 | | FAIL |
Peter J. McCullough
|
|
|
No trash enclosure shown on plans; access to container not adequate.
|
Routing - Addressing | 5/7/2010 | | 5/7/2010 | | PASS |
April Wing
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/6/2010 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 5/6/2010 | | 5/6/2010 | | PASS |
Dave Abo
|
|
|
|
Application received | | 5/5/2010 | 5/5/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Pending Assignment by JCM | 5/5/2010 | | 5/5/2010 | | BLDA |
John Menard
|
|
|
5/5/2010 15:50:55 JCM - activity updated through activity BLDA166 from case BLD10-00988.
|