Case Summary (BLD) | | | 6/23/2011 | | DONE |
|
|
|
|
Second Notice | | 7/25/2010 | 7/29/2010 | | DONE |
|
|
|
|
First Notice | 7/7/2010 | 7/7/2010 | 7/15/2010 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 7/7/2010 | 7/7/2010 | 7/7/2010 | A | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 7/7/2010 | 7/7/2010 | 7/7/2010 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 7/6/2010 | 7/6/2010 | 7/6/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety for the vanilla shell sutie 130 passed. See BLD10-01076 for adjacent suite 132.
|
BLD-Final | 7/2/2010 | 7/6/2010 | 7/6/2010 | A | NR |
Dave Hannah
|
|
|
Ben Roper Phone #: ###-#### needs fire finals
|
BLD-Final | 7/1/2010 | 7/2/2010 | 7/2/2010 | P | DEFR |
Jim Storey
|
|
|
Ben Roper Phone #: ###-#### to 425 for 7/6
|
FIRE-Final Inspection | 7/1/2010 | 7/2/2010 | 7/2/2010 | P | NR |
Forrest France
|
|
|
Missing address numbers, site work in progress, need demo and project related fire sprinkler permit finals first.
|
BLD-Framing/Rough-in | 6/9/2010 | 6/10/2010 | 6/10/2010 | P | PART |
Dave Hannah
|
|
|
Ben Phone #: ###-#### ok to cover rest rooms
|
CHANGE STATUS TO (ISS) | | | 5/25/2010 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 5/17/2010 | | 5/24/2010 | | PASS |
Tim L. Woodard
|
|
|
5/24/2010 09:09:20 TLW - activity updated through activity BLDA022 from case BLD10-01004.
|
Routing - PLAN CHECK | 5/24/2010 | | 5/24/2010 | | PASS |
Tim L. Woodard
|
|
|
Approved with redlines refer to revised plan review report.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 5/24/2010 | | DONE |
Tim L. Woodard
|
|
|
|
(F) Reprint permit | | | 5/24/2010 | | DONE |
Rita DeYoung
|
|
|
|
Inspection Record Card- Bld | | | 5/24/2010 | | DONE |
|
|
|
|
Received Certificate of Value | | | 5/18/2010 | | DONE |
Barbara Stitt
|
|
|
Plan mod accepted with new cert of value
|
Plan Modification Accepted | | | 5/17/2010 | | |
|
|
|
Plan modification accepted for enlarging rest rooms for ADA compliance. Submitted 2 copies of sheet Two with a new cert of value, routed to Tim Woodard
|
BLD-Conference | 5/13/2010 | 5/14/2010 | 5/14/2010 | A | PASS |
Dave Hannah
|
|
|
ben Phone #: ###-####
|
Routing - Addressing | 5/14/2010 | | 5/14/2010 | | PASS |
April Wing
|
|
|
|
Permit Ready to Issue | | | 5/13/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 5/13/2010 | | DONE |
Barbara Stitt
|
|
|
Called and told permit is ready, fees due and need GC name & # @ 11:00am on 5-13-10 BAS
|
Issue PAID IN FULL permit | | | 5/13/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/13/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (TLW) | 5/6/2010 | | 5/12/2010 | | PASS |
Tim L. Woodard
|
|
|
5/12/2010 16:27:14 TLW - activity updated through activity BLDA022 from case BLD10-01004.
|
Routing - PLAN CHECK | 5/6/2010 | | 5/12/2010 | | PASS |
Tim L. Woodard
|
|
|
Approved with plan review report. TLW
|
Routing - FIRE | | | 5/12/2010 | | PASS |
Tim L. Woodard
|
|
|
Field Verify. TLW
|
Case Summary (BLD) | | | 5/12/2010 | | DONE |
Tim L. Woodard
|
|
|
|
1st review completed | | | 5/12/2010 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/12/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | 5/6/2010 | 5/6/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Intake Approval | | | 5/6/2010 | | FAIL |
Tim L. Woodard
|
|
|
Need planning approval for new entry door. TLW Everything else was ok.
|
Plans ACCEPTED BY PLAN TECH | | | 5/6/2010 | | DONE |
|
|
|
|
Intake Approval | | | 5/6/2010 | | PASS |
Tim L. Woodard
|
|
|
|