Third Notice | | 10/11/2010 | 9/28/2010 | | DONE |
|
|
|
|
Third Notice | | 8/31/2010 | 9/27/2010 | | DONE |
|
|
|
mailed
|
Second Notice | | 8/9/2010 | 8/26/2010 | | DONE |
|
|
|
|
First Notice | | 7/26/2010 | 7/30/2010 | | DONE |
|
|
|
|
BLD-Final | 7/14/2010 | 7/15/2010 | 7/16/2010 | P | DONE |
Dave Hannah
|
|
|
Cal Meyer Phone #: ###-####
|
BLD-Final | 7/15/2010 | 7/16/2010 | 7/16/2010 | A | PASS |
Dave Hannah
|
|
|
Cal Phone #: ###-####
|
FIRE-Final Inspection | 7/15/2010 | 7/16/2010 | 7/16/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
Permanent Occupancy UNPAID FEE | | | 7/16/2010 | | |
|
|
|
|
FIRE-Final Inspection | 7/14/2010 | 7/15/2010 | 7/15/2010 | A | FAIL |
Troy Cobbley
|
|
|
The lever hardware on the office and restroom doors does not override the lock, the new storefront door out the north side of the tenant has not been installed. There is an exit sign/emergency light above the location now. I told Cal and his son that the door/hardware needs to be installed per plan or a plan modification with Tim Woodard will be needed showing the door removed from the plans.
|
Zoning Approval | 7/14/2010 | 7/14/2010 | 7/14/2010 | | PASS |
Andrea Tuning
|
|
|
|
BLD-Framing/Rough-in | 7/9/2010 | 7/12/2010 | 7/12/2010 | A | PASS |
Jim Sly
|
|
|
rick - ceiling grid - please call 1/2 hr prior so they can meet you there Phone #: ###-#### Grid OK.
|
BLD-Framing/Rough-in | 6/22/2010 | 6/23/2010 | 6/23/2010 | P | PASS |
Jim Sly
|
|
|
cal Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/14/2010 | | DONE |
|
|
|
|
OVERRIDE | | | 6/11/2010 | | |
|
|
|
|
Telephone call | | | 6/11/2010 | | DONE |
|
|
|
left vm for cal at ###-#### - permit ready and fees given - also need rp name
|
Permit Ready to Issue | | | 6/11/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/10/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 5/28/2010 | | 6/10/2010 | | PASS |
Tim L. Woodard
|
|
|
6/10/2010 15:47:27 TLW - activity updated through activity BLDA022 from case BLD10-01047.
|
Routing - PLAN CHECK | 6/3/2010 | | 6/9/2010 | | PASS |
Tim L. Woodard
|
|
|
Tim Woodard - Plans are approved with redlines and a plan review report. Lighting and Mechanical Compliances attached to the front of plans.
|
Routing - Addressing | 5/28/2010 | | 6/9/2010 | | PASS |
April Wing
|
|
|
april approved plans on Public Works Routing sheet. TLW
|
Routing - FIRE | | | 6/9/2010 | | PASS |
Tim L. Woodard
|
|
|
Field Verify
|
1st review completed | | | 6/9/2010 | | FAIL |
Tim L. Woodard
|
|
|
Plans are approved pending the alternate being approved through the building official. Alternate is to allow access to restroom from the rear entrance. TLW
|
Routing - Erosion and Sediment | 6/9/2010 | | 6/9/2010 | | PASS |
Tim L. Woodard
|
|
|
Waiver Approved. Applicant is to comply with all attached conditions. TLW
|
Case Summary (BLD) | | | 6/9/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | | | 6/3/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | 6/2/2010 | | 6/2/2010 | | PASS |
Walt Baumgartner
|
|
|
Reviewed, no cooking on site, no grease abatement.
|
Routing PW Sewer Rating | 6/2/2010 | | 6/2/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 5/28/2010 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/28/2010 | | DONE |
Barbara Stitt
|
|
|
|
Application received | | 5/11/2010 | 5/11/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 5/11/2010 | | FAIL |
Tim L. Woodard
|
|
|
Need planning approval and signature on Registered Design Proffessional form. TLW
|