Routing PW Street Lights | 6/25/2010 | | 5/7/2014 | | PASS |
Hank Alarcon
|
|
|
Have called Ward Schwider on 06/28/2010 and advise him that a street lighting layout and power supply plan must be submitted for review by Boise City Public Works.
|
Third Notice | | 5/30/2011 | 9/23/2011 | | DONE |
|
|
|
final value given by Vertical Corp
|
Letter of compliance/Occupancy | | | 5/31/2011 | | DONE |
Barbara Stitt
|
|
|
|
Second Notice | | 5/20/2011 | 5/25/2011 | | DONE |
Christina Prado
|
|
|
Faxed 5-25-2011
|
First Notice | 5/5/2011 | 5/5/2011 | 5/10/2011 | | DONE |
Dave Hannah
|
|
|
|
BLD-Final | 5/5/2011 | 5/5/2011 | 5/5/2011 | P | PASS |
Dave Hannah
|
|
|
Dave Phone #: ###-####
|
DOC - Permit Finaled | 5/5/2011 | 5/5/2011 | 5/5/2011 | P | PASS |
Dave Hannah
|
|
|
|
Zoning Approval Temp | 5/3/2011 | 5/3/2011 | 5/3/2011 | | DONE |
Josh Wilson
|
|
|
30 Temp for installation of mechanical screens
|
FIRE-Final Inspection | 4/26/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Forrest France
|
|
|
Shell building fire life safety passed.
|
Inspection Record Card- Bld | | | 4/13/2011 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Sprinkler Rough-in | 4/4/2011 | 4/4/2011 | 4/4/2011 | A | PART |
Forrest France
|
|
|
Ref. FIR10-00569 for activity notes to date.
|
FIRE-Sprinkler Rough-in | 3/7/2011 | 3/7/2011 | 3/8/2011 | P | PART |
Forrest France
|
|
|
Regarding light fixtures at the east side first floor.
|
BLD-Framing/Rough-in | 1/14/2011 | 1/14/2011 | 1/17/2011 | P | PART |
Dave Hannah
|
|
|
Dave Phone #: ###-#### ok to cover ext walls
|
BLD-Other | 1/11/2011 | 1/11/2011 | 1/11/2011 | P | PART |
Dave Hannah
|
|
|
Dave Phone #: ###-#### shear wall ok to cover ext
|
BLD-Framing/Rough-in | 12/28/2010 | 12/29/2010 | 12/29/2010 | A | FAIL |
Dave Hannah
|
|
|
dave Phone #: ###-#### shear needs to renail over shot and used stapels
|
BLD-Foundation | 12/16/2010 | 12/17/2010 | 12/17/2010 | A | PART |
Dave Hannah
|
|
|
Dave Phone #: ###-#### bottom of elev pit ok to pour
|
BLD-Energy code compliance | 12/16/2010 | 12/17/2010 | 12/17/2010 | A | PART |
Dave Hannah
|
|
|
dave Phone #: ###-#### roof/deck ok to cover
|
BLD-Foundation | 11/4/2010 | 11/5/2010 | 11/5/2010 | A | PASS |
Dave Hannah
|
|
|
Dave Phone #: ###-#### slabs over column pads base plates grouted
|
BLD-Footing | 9/30/2010 | 10/1/2010 | 10/1/2010 | A | PART |
Dave Hannah
|
|
|
dave Phone #: ###-#### ok to pour 10 int ftgs/ column pads and 2 ftgs for cmu walls
|
Permit Ready to Issue | | | 9/23/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 9/23/2010 | | DONE |
Barbara Stitt
|
|
|
Called Ward Schwinder and told him that permit is ready & fees due on 9-23-10 @ 11:30am
|
Issue PAID IN FULL permit | | | 9/23/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/21/2010 | | DONE |
Barbara Stitt
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2010 | | DONE |
John Menard
|
|
|
|
Plan assigned to (JCM) | 5/13/2010 | | 9/21/2010 | | PASS |
John Menard
|
|
|
9/21/2010 08:36:32 JCM - activity updated through activity BLDA022 from case BLD10-01086.
|
Routing - PLAN CHECK | 9/15/2010 | | 9/16/2010 | | PASS |
John Menard
|
|
|
|
Plan Reviewer's activity | | | 9/16/2010 | | PASS |
John Menard
|
|
|
Reviewed and approved final structural and nonstructural resubmitted code revisions. JCM
|
Routing - FIRE | 9/13/2010 | | 9/15/2010 | | PASS |
Scott Arellano
|
|
|
Please, see attached comments.
There are annotations on the plans.
|
Routing - PUBLIC WORKS | 9/9/2010 | | 9/13/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Flood Plain | 9/10/2010 | | 9/10/2010 | | PASS |
Jim Wyllie
|
|
|
Drainage discharge to existing right-of-way approved by ACHD.
|
Routing PW Drainage | 9/10/2010 | | 9/10/2010 | | PASS |
Peter J. McCullough
|
|
|
JIM WYLIE APPROVED
|
Routing PW Solid Waste | 9/10/2010 | | 9/10/2010 | | PASS |
Peter J. McCullough
|
|
|
Revised enclosure passed, 12'x12'
|
Routing PW Sewer Rating | | | 9/10/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Erosion and Sediment | 9/8/2010 | | 9/9/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and the ESC permit conditions. ESC10-00397
|
Routing - PLAN CHECK | 8/31/2010 | | 9/8/2010 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 9/7/2010 | | DONE |
Tisha Gallop
|
|
|
received two copies of ESC-1 and one copy of narrative; inserted by Ward Schwider and taken back to John Menard
|
Plan resubmittals received | | | 9/2/2010 | | |
Tisha Gallop
|
|
|
received response, two copies of structural calcs, three copies of plan sheets A0.0, S2.1, S2.2, ST-1;inserted by Ward Schweider and taken back to John Menard
|
Routing - Erosion and Sediment | 8/30/2010 | | 8/31/2010 | | FAIL |
Steven Webb
|
|
|
Still no Erosion Control Plan, informed applicant.
|
Routing - PUBLIC WORKS | 8/31/2010 | | 8/31/2010 | | FAIL |
Connie Baumgartner
|
|
|
Still failed by Jim Wylie ###-#### for drainage and Peter McCullough ###-#### for solid waste
|
Routing PW Street Lights | 8/31/2010 | | 8/31/2010 | | PASS |
Hank Alarcon
|
|
|
|
Route to Impact Fee Review | 8/25/2010 | 8/30/2010 | 8/30/2010 | | PASS |
Cindy M. Gould
|
|
|
Replacement of building distroyed in fire, no impact fees.
|
Routing - FIRE | 8/25/2010 | 8/25/2010 | 8/30/2010 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 8/30/2010 | | FAIL |
|
|
|
Failed Public Works, Erosion & Soil Control, Fire
|
Routing - PLAN CHECK | 6/28/2010 | | 8/25/2010 | | FAIL |
John Menard
|
|
|
|
Plan resubmittals requested | | | 8/25/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the plan review requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 8/9/2010 | | 8/18/2010 | | FAIL |
John Menard
|
|
|
called for pick up - Received comment list from consulting structural engineer requesting additional revisions. JCM
|
Plan resubmittals requested | | | 8/18/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the fourth structural review requesting additional revisions. JCM
|
Plan resubmittals received | | | 8/9/2010 | | |
John Menard
|
|
|
rec'd response letter, calcs and 3 copies of sheets S2.0; S2.1; S2.2; ST-1; A4.0 - inserted and taken back to John M
|
Plan resubmittals requested | | | 8/2/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the third structural review requesting additional revisions. JCM
|
Routing Off Site - STRUCTURAL | 7/19/2010 | | 7/30/2010 | | FAIL |
John Menard
|
|
|
called Action Couriers for pick up - Received comment list from consulting structural engineer requesting revisions. JCM
|
Plan resubmittals received | | | 7/16/2010 | | |
John Menard
|
|
|
Rec'd response letter, calcs, and three copies of sheets S2.0; S2.1; S2.2; A3.0; A4.0; ST-1; ST-2 - inserted by architect - taken back to John M
|
Plan resubmittals requested | | | 7/7/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a letter requesting more complete plans before doing the plan review. JCM
|
Routing PW Sewer Design | 6/28/2010 | | 6/28/2010 | | PASS |
Jon R. Gunnerson
|
|
|
No changes to sewer service.
|
Routing PW Solid Waste | 6/28/2010 | | 6/28/2010 | | FAIL |
Peter J. McCullough
|
|
|
Trash Enclosure does not meet required specifications. Contact: Peter McCullough, ###-####
|
Routing - PUBLIC WORKS | 6/23/2010 | | 6/28/2010 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | 6/23/2010 | | 6/25/2010 | | FAIL |
Jim Wyllie
|
|
|
|
Plan resubmittals requested | | | 6/24/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural comments requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 6/7/2010 | | 6/24/2010 | | FAIL |
John Menard
|
|
|
called Action Couriers for pick up
Received comment list from consulting structural engineer requesting revisions. JCM
|
Routing - PLAN CHECK | 6/3/2010 | | 6/23/2010 | | |
John Menard
|
|
|
|
Plan resubmittals received | | | 6/7/2010 | | DONE |
Tisha Gallop
|
|
|
received response letter, two copies of structural calcs, and three copies of plan sheets A0.0, A2.1, A2.2, A4.0, ST-1; inserted by Ward Schwider and taken back to JCM
|
Routing - PLANNING | 6/2/2010 | | 6/3/2010 | | PASS |
Josh Wilson
|
|
|
DRH10-00085
|
Routing - PLUMBING | 6/1/2010 | | 6/2/2010 | | PASS |
Bill VanDegrift
|
|
|
no plumbing
|
Plan resubmittals requested | | | 6/1/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Routing - Erosion and Sediment | 5/27/2010 | | 6/1/2010 | | FAIL |
Steven Webb
|
|
|
Need ESC plan, informed contractor, (Vertical Construction) via voice mail. ESC10-00397
|
Routing Off Site - STRUCTURAL | 5/13/2010 | | 5/28/2010 | | FAIL |
John Menard
|
|
|
Received comment list from consulting structural engineer requestng revisions. JCM
|
Routing - PUBLIC WORKS | 5/14/2010 | | 5/27/2010 | | FAIL |
Beverly Mountain
|
|
|
|
Routing PW Drainage | 5/17/2010 | | 5/27/2010 | | FAIL |
Brian Murphy
|
|
|
NO DRAINAGE PLAN OR TREATMENT SYSTEM. BRIAN MURPHY ###-#### CONTACTED WARD SCHWIDER BY PHONE.
|
Routing - Addressing | 5/17/2010 | | 5/17/2010 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 5/13/2010 | | 5/14/2010 | | PASS |
Todd Tucker
|
|
|
|
Application received | | 5/13/2010 | 5/13/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Pending Assignment by JCM | 5/13/2010 | | 5/13/2010 | | BLDA |
John Menard
|
|
|
5/13/2010 13:57:21 JCM - activity updated through activity BLDA166 from case BLD10-01086.
|
Plans ACCEPTED BY PLAN TECH | | | 5/13/2010 | | DONE |
|
|
|
|
Intake Approval | | | 5/13/2010 | | PASS |
John Menard
|
|
|
|