Second Notice | | 1/20/2011 | 1/20/2011 | | DONE |
|
|
|
|
First Notice | | 1/6/2011 | 1/10/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/27/2010 | | DONE |
Barbara Stitt
|
|
|
|
BLD-Final | 12/21/2010 | 12/22/2010 | 12/22/2010 | A | PASS |
Jim Storey
|
|
|
Forrest ###-#### Note: Related FIR's passed final.
|
Print Occupancy Form | | | 12/22/2010 | | DONE |
Barbara Stitt
|
|
|
|
FIRE-Final Inspection | 12/21/2010 | 12/21/2010 | 12/21/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety final approved.
|
FIRE-Final Inspection | 12/20/2010 | 12/20/2010 | 12/20/2010 | P | PART |
Forrest France
|
|
|
Pending project attatched FIR permit.
|
BLD-Conference | 11/10/2010 | 12/10/2010 | 12/10/2010 | A | PASS |
Jim Storey
|
|
|
loyd said instal will happen tue and will follow up w/insp.
|
Check Permit for Holds | | | 11/29/2010 | | |
|
|
|
Do NOT ISSUE OCCUPANCY without payment of additional sewer fees. B_m
|
Office Staff conference/action | | | 11/10/2010 | | |
Barbara Stitt
|
|
|
Per Jim Storey they are waiting for a part to be made and shipped from the mid-west need to give them till 12-10-10.
|
BLD-Aging Inspection | 10/29/2010 | 10/29/2010 | 11/1/2010 | | PASS |
Jim Storey
|
|
|
loyd said that fire parts on ored and will be installed and insp. as soon as they arive.
|
BLD-Final | 8/17/2010 | 8/18/2010 | 8/18/2010 | A | PASS |
Jim Storey
|
|
|
loyd Phone #: ###-#### final ok for bld pending fire agreement. Temporary occupancy approved for a term of 30 days per M. Senteno. Note: System impairments beyond eight hours will require a fire watch.
|
Temporary Occupancy UNPAID FEE | | | 8/18/2010 | | |
|
|
|
|
FIRE-Final Inspection | 8/17/2010 | 8/17/2010 | 8/17/2010 | P | PART |
Forrest France
|
|
|
Temporary occupancy approved for a term of 30 days per M. Senteno. Note: System impairments beyond eight hours will require a fire watch.
|
BLD-Final | 8/13/2010 | 8/16/2010 | 8/17/2010 | A | NR |
Jim Storey
|
|
|
LLoyd - call 30 mins prior Phone #: ###-####
|
FIRE-Final Inspection | 8/13/2010 | 8/16/2010 | 8/16/2010 | A | PART |
Forrest France
|
|
|
Fire life safety final pending project related fire sprinkler work. Remainder of items completed and tested acceptable.
|
BLD-Conference | 8/9/2010 | 8/9/2010 | 8/9/2010 | P | PASS |
Jim Storey
|
|
|
Hollis Phone #: ###-####
|
BLD-Framing/Rough-in | 7/7/2010 | 7/7/2010 | 7/7/2010 | P | PASS |
Jim Storey
|
|
|
Hollis Phone #: ###-####
|
Plan assigned to (DRS) | 7/2/2010 | 7/2/2010 | 7/6/2010 | | PASS |
Dan Stuart
|
|
|
7/6/2010 10:14:30 DRS - activity updated through activity BLDA022 from case BLD10-01112.
|
Routing - PLAN CHECK | 7/2/2010 | | 7/6/2010 | | PASS |
Dan Stuart
|
|
|
Plan modifications inserted into plans; attached plan review comments / condititions modified to address scope change; copies of permit, plan mod app and building plan review attached to plans. routing to PW for fee adjustment.
|
Routing - PUBLIC WORKS | 7/6/2010 | | 7/6/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Override - Parcel Holds | | | 7/6/2010 | | |
|
|
|
|
Routing - PLAN CHECK | 7/6/2010 | | 7/6/2010 | | PASS |
|
|
|
Plan Mod approved and routed to permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/6/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 7/6/2010 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 7/6/2010 | | |
|
|
|
|
Permit Ready to Issue | | | 7/6/2010 | | DONE |
|
|
|
|
Telephone call | | | 7/6/2010 | | DONE |
|
|
|
7-6-10 called let Billy know permit ready and fee given ///dld
|
CHANGE STATUS TO (ISS) | | | 7/6/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/6/2010 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 7/2/2010 | | DONE |
Tisha Gallop
|
|
|
Plan modification accepted for Bld10-01112 (Sage International School) for the addition of two lavatories in existing restroom; submitted on revised certificate of value and plan sheets D-1.1, A-1.1, A-1.2, A-4.1, A-6.1, M1.0; routed to Dan Stuart
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2010 | | PASS |
|
|
|
Permit issued pending final disposition of Building Official concering alternate request for reduction in required number of LAVS in Women's restrooms.
|
Print Occupancy Form | | | 6/30/2010 | | DONE |
|
|
|
|
Telephone call | | | 6/30/2010 | | DONE |
|
|
|
t/c w peter at ###-#### - permit ready and fees given - also need gc name, rce#, rp name, and ACHD receipt
|
Permit Ready to Issue | | | 6/30/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/30/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/29/2010 | | 6/30/2010 | | PASS |
Dan Stuart
|
|
|
Plans were approved for issue based on correspondence between Pete Rockwell, Architect; Don Keller, Principle - Superintendant of Sage International School of Boise; and Jenifer Gilliland, Building Division Manager, stating that the architect and tenant agree to resubmit plans showing compliance with decision of Building Official and his action on thier Alternate Request Letter concerning occupant load to be used to determine plumbing fixture's for Women's restrooms. Permit to permit desk to issue. Copy of correspondence attached to plans and to permit.
|
Plan assigned to (DRS) | 5/18/2010 | | 6/30/2010 | | PASS |
Dan Stuart
|
|
|
6/30/2010 07:34:15 DRS - activity updated through activity BLDA022 from case BLD10-01112.
|
Routing - PUBLIC WORKS | 6/29/2010 | | 6/29/2010 | | PASS |
Connie Baumgartner
|
|
|
Routing back to PW for fee consideration based on added fixtures.
|
Telephone call | | | 6/29/2010 | | DONE |
|
|
|
Called Pete Rockwell to let him know the resubmittals were received 6/28/10 and that the Alternate Request Letter was on Jason Blais' desk for his review. We also discussed the drinking fountain clarifying that (2) front approach accessible wheel chair unit were required and (2) staning accessible units and that I would red-line plans to clarify the requirements and he would follow up with contractor.
Pete wanted to move ahead with getting permit if possible before Jason will be back in office and said he would provide a letter to Jenifer Gilliland requesting the permit be issued and acknowledginh that if the alternate was denied or other corrections needed, appropriate plans for corrections would be provided and changes made to plans and in the field for code compliance.
|
Plan Reviewer's activity | | | 6/29/2010 | | DONE |
|
|
|
Copied Angela Brosious, project manager on status of permit and copied her with letter from Pete to Jenifer.
|
Routing - PLAN CHECK | 6/23/2010 | | 6/29/2010 | | FAIL |
Dan Stuart
|
|
|
Waiting for approval of alternate concerning restroom fixture requirements of approval from Jenifer Gilliland to issue the permit based on letter from Pete Rockwell stating if alternate is not approved they will submit plans and make changes in field to provide code compliance.
|
Plan resubmittals received | | | 6/28/2010 | | |
Dan Stuart
|
|
|
rec'd response letter and 2 copies of sheet A-1.1 - taken to Dan S
|
Routing - PLAN CHECK | 6/22/2010 | | 6/23/2010 | | FAIL |
Dan Stuart
|
|
|
Resubmittals of 6/22/10 were incomplete in response to plan review of 5/26/10. Copy of 2nd review e-mailed to architect, Jason Blais & Angie Brosious.
|
Plan resubmittals requested | | | 6/23/2010 | | DONE |
|
|
|
Copy of 2nd plan review for items remaining to be addressed for code compliance e-mailed to architect.
|
Plan resubmittals received | | | 6/22/2010 | | |
Dan Stuart
|
|
|
rec'd response letter, strucrual calcs and 2 copies of sheets CVR; A-0.1; D-1.1; A-1.1; A-1.2; A-1.4; A-6.1; M1.0; M2.0 - taken to Dan S
|
Routing - PLAN CHECK | 5/28/2010 | | 6/22/2010 | | FAIL |
Dan Stuart
|
|
|
Routing back to Planning for re-review. Josh Wilson & Josh Johnson
|
Routing - PLANNING | 6/22/2010 | | 6/22/2010 | | PASS |
Josh Wilson
|
|
|
DR Pass with redlines sheet A-0.1- fence must be solid wood or vinyl.
|
Routing - PLANNING | 6/22/2010 | | 6/22/2010 | | PASS |
Joshua Johnson
|
|
|
|
Route to Impact Fee Review | 5/27/2010 | 6/2/2010 | 5/28/2010 | | PASS |
Cindy M. Gould
|
|
|
Remodel, on impact fees
|
Routing - FIRE | 5/27/2010 | 5/27/2010 | 5/28/2010 | | PASS |
Scott Arellano
|
|
|
Please, see attached comments.
Approved but with comments.
|
1st review completed | | | 5/28/2010 | | DONE |
|
|
|
Failed - Planning, Plan Check
|
Plan resubmittals requested | | | 5/27/2010 | | DONE |
|
|
|
Copy of plan review e-mailed to architect. Architect responded that he had received them.
|
Routing - PLAN CHECK | 5/20/2010 | | 5/27/2010 | | FAIL |
Dan Stuart
|
|
|
Copy of plan review requirements e-mailed to Pete Rockwell. Plans routing to fire code analyst for review.
|
Routing - Erosion and Sediment | 5/19/2010 | | 5/20/2010 | | PASS |
Steven Webb
|
|
|
ESC plan waiver is approved according to the ESC permit's attached conditions. ESC10-00405
|
Routing - PLANNING | 5/20/2010 | | 5/20/2010 | | FAIL |
Joshua Johnson
|
|
|
Required CUP and CZC not yet approved JGW
Josh Johnson - CUP10-00016
|
Routing - Design Review | 5/20/2010 | | 5/20/2010 | | FAIL |
Josh Wilson
|
|
|
Required CUP and CZC not yet approved
Josh Wilson - CZC???
|
Routing PW Sewer Rating | 5/19/2010 | | 5/19/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 5/18/2010 | | 5/19/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 5/17/2010 | 5/18/2010 | | DONE |
Tisha Gallop
|
|
|
"green tag" per JCB
|
Pending Assignment by JCB | 5/18/2010 | | 5/18/2010 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 5/18/2010 | | DONE |
Jason Blais
|
|
|
E-mailed architect letting him know to contact ACHD and submit any needed documents for review. Verification letter from ACHD on approval and if any additional impact fees are required is needed prior to issuance of the building permit.
|
Routing - Addressing | 5/18/2010 | | 5/18/2010 | | PASS |
April Wing
|
|
|
|
Intake Approval | | | 5/17/2010 | | PASS |
Jason Blais
|
|
|
Special case since P&Z hearing was cancelled last month. Permission granted to accept building permit application for review only while CUP process is still underway. A Zoning Certificate application to Planning is also required. Applicant will also need to pursue a lot line adjustment for the east property line.
|
Plans ACCEPTED BY PLAN TECH | | | 5/17/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/17/2010 | | DONE |
Tisha Gallop
|
|
|
|