Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD10-01120
StatusFinaled
Name HC COMPANY INC
Site Address 11311 W CHINDEN BLVD
Project NameHP#5 ADDITION
Customer Number410001-4004
ePlanReviewNo
Description
(HEWLETT PACKARD)(BUILDING 5SS - INDIGO LABS) Remodel within a 4,200 sq. ft. area in existing building for relocated/reconfigured Indigo lab test chamber, presses and support areas; to add enclosed area of 207 sq. ft. to include new reinforced concrete footing/piers & slab; steel columns, beams & roof deck; standing metal seam roof & insulated perimeter wall panels; construct interior walls to create Toner Collection room, Mechanical Room, Indigo Lab Chamber and Press Room; to add new doors & hardware or modify existing doors and hardware; interior wall, floor & ceiling finishes; upgrade of electrical, mechanical, plumbing, sprinkler & alarm systems; all per approved plans. Mechanical equipment / ducting modifications / additions are to serve the needs of the Indigo Testing Lab and support areas environmental requirements. NOTE: This building fully fire sprinklered for allowable area increase, unlimited area with 60' all around. Separate applications, plans, approvals and permits are required before any work can be performed on the sprinkler and alarms systems as regulated by the Fire Department. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice11/19/201011/19/201012/8/2010 DONE
DetailsJim Sly
BLD-Final11/18/201011/19/201011/19/2010APASS
DetailsJim Sly
Gene Phone #: ###-####
C/C issued
DOC - Permit Finaled11/19/201011/19/201011/19/2010PPASS
DetailsJim Sly
FIRE-Final Inspection11/15/201011/15/201011/15/2010APASS
DetailsForrest France
Fire life safety inspection passed.
FIRE-Final Inspection11/12/201011/12/201011/15/2010PPASS
DetailsForrest France
Fire life safety is satisfactory pending approved style door hardware at the exit from the new enclosed 207ft2 addition is provided. Project related FIR permits are finaled.
BLD-Other11/5/201011/5/201011/5/2010PPASS
DetailsJim Sly
GENE Phone #: ###-####
Grid OK
BLD-Conference10/12/201010/14/201010/26/2010PPART
DetailsDave Hannah
jeff Phone #: ###-#### talked about bld no. 7 T/Is
BLD-Other10/21/201010/21/201010/21/2010PPASS
DetailsJim Sly
###-#### Gene Ceiling grid OK
BLD-Framing/Rough-in10/20/201010/21/201010/21/2010ACANC
DetailsJim Sly
gene - ceiling grid Phone #: ###-####
Re-sched PM
FIRE-Conference10/19/201010/19/201010/20/2010PDONE
DetailsForrest France
Regarding project completion schedule.
FIRE-Conference10/7/201010/8/201010/8/2010ADONE
DetailsForrest France
On site conference regarding project schedule.
BLD-Framing/Rough-in9/21/20109/21/20109/21/2010PPART
DetailsJim Sly
Ceiling grid inspection for cover please-Gene Phone #: ###-####
Select ceiling grid at toner lab East end.
BLD-Framing/Rough-in8/20/20108/23/20108/23/2010APART
DetailsJim Sly
Gene Phone #: ###-####
Hall and Mech room.....
BLD-Framing/Rough-in8/10/20108/10/20108/10/2010PPART
DetailsJim Sly
Gene-Toner room please Phone #: ###-####.....OK
Issue PAID IN FULL permit  6/24/2010 DONE
Inspection Record Card- Bld  6/22/2010 DONE
Telephone call  6/22/2010 DONE
t/c w john at ###-#### - permit ready and fees given
Permit Ready to Issue  6/22/2010 DONE
Details
Plan assigned to (DRS)5/21/2010 6/21/2010 PASS
DetailsDan Stuart
6/21/2010 16:00:22 DRS - activity updated through activity BLDA022 from case BLD10-01120.
Routing - FIRE6/15/2010 6/21/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  6/21/2010 PASS
Routing - PLAN CHECK6/21/2010 6/21/2010 PASS
DetailsDan Stuart
Routing - PLANNING6/21/2010 6/21/2010 PASS
DetailsAndrea Tuning
CZC10-00115
PLANS/APPL TAKEN TO FRONT DESK  6/21/2010 PASS
Routing - PLAN CHECK6/4/2010 6/15/2010 PASS
DetailsDan Stuart
No resubmittals required. Routing to fire code analyst for review.
Routing - PLUMBING6/2/2010 6/4/2010 PASS
DetailsBill VanDegrift
additional cross connection protection may be required. indirect waste receptors are not to be located with in cabinets.
Routing - Erosion and Sediment6/1/2010 6/2/2010 PASS
DetailsSteven Webb
ESC plan waiver is approved according to the ESC Permit attached conditions. ESC10-00419
Routing - PUBLIC WORKS5/24/2010 6/1/2010 PASS
DetailsBeverly Mountain
Routing PW Environmental6/1/2010 6/1/2010 PASS
DetailsWalt Baumgartner
Reviewed by PW Pretreatment staff
Routing - Addressing5/27/2010 5/27/2010 PASS
DetailsApril Wing
Intake Approval  5/24/2010 PASS
DetailsJason Blais
Received ESC application and Plan Waiver Request Letter.
Plan resubmittals received  5/24/2010 DONE
DetailsJason Blais
Received ESC application and Plan Waiver Request Letter.
Telephone call  5/21/2010 DONE
DetailsJason Blais
Left message for architect John Reseigh to submit an Erosion & Sediment Control application and Plan Waiver Request Letter. Needed for the extensive sawcutting and patching of concrete slab for underslab piping.
Intake Approval  5/21/2010 FAIL
DetailsJason Blais
Needs an Erosion & Sediment Control application and Plan Waiver Request Letter. Needed for the extensive sawcutting and patching of concrete slab for underslab piping.
Pending Assignment by JCB5/20/2010 5/21/2010 DONE
DetailsJason Blais
Plans ACCEPTED BY PLAN TECH  5/20/2010 DONE
Application received 5/19/2010