Third Notice | | 2/18/2011 | 2/9/2011 | | DONE |
|
|
|
|
Third Notice | | 2/4/2011 | 2/4/2011 | | DONE |
|
|
|
faxed to EKC and Scott Oliver/applicant
|
Telephone call | | | 2/4/2011 | | DONE |
Tisha Gallop
|
|
|
received call from Scott Oliver/CCDC, he said GC should have these values, told him no response from EKC on first and second notices. He said will call them and get values to fill out form.
|
Third Notice | | 1/12/2011 | 1/21/2011 | | DONE |
|
|
|
faxed
|
Second Notice | | 1/2/2011 | 1/7/2011 | | DONE |
|
|
|
|
First Notice | | 1/17/2011 | 12/23/2010 | | DONE |
Barbara Stitt
|
|
|
|
Permanent Occupancy | | | 11/29/2010 | | DONE |
|
|
|
|
BLD-Final | 11/23/2010 | 11/23/2010 | 11/23/2010 | P | PASS |
Tony Young
|
|
|
dale Phone #: ###-####
|
Zoning Approval | 11/23/2010 | 11/23/2010 | 11/23/2010 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 11/19/2010 | 11/19/2010 | 11/22/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety passed 11/19.
|
BLD-Final | 11/19/2010 | 11/22/2010 | 11/22/2010 | A | FAIL |
Tony Young
|
|
|
dale Phone #: ###-####,, called contractor ,, no answer,, correction posted on back of signoff sheet,, need zoning also
|
FIRE-Final Inspection | 11/18/2010 | 11/18/2010 | 11/19/2010 | P | PASS |
Forrest France
|
|
|
Items on correction notice verified for completion. Fire life safety finaled.
|
FIRE-Final Inspection | 11/9/2010 | 11/9/2010 | 11/9/2010 | P | FAIL |
Forrest France
|
|
|
Post max occupant load sign, repair one exit sign/EM light, provide test for the two new duct detectors, fire extinguishers are overdue certification.
|
BLD-Framing/Rough-in | 9/14/2010 | 9/14/2010 | 9/14/2010 | P | PASS |
Tony Young
|
|
|
dale Phone #: ###-####
|
BLD-Concrete | 9/1/2010 | 9/2/2010 | 9/2/2010 | A | PASS |
Dave Hannah
|
|
|
dale Phone #: ###-#### ok to pour stairs
|
BLD-Framing/Rough-in | 8/30/2010 | 8/30/2010 | 8/30/2010 | P | PART |
Tom Arcoraci
|
|
|
Dale ###-#### epoxy bolts ok in 2 hr wall
|
Issue PAID IN FULL permit | | | 8/17/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 6/17/2010 | | 7/23/2010 | | PASS |
Carl Westfall
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/23/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/23/2010 | | DONE |
|
|
|
|
Telephone call | | | 7/23/2010 | | DONE |
|
|
|
Called Doung Cooper and told him permit is ready, fees due and need GC info on 7-23-10 @ 4:15pm
|
Plan assigned to (CJW) | 5/21/2010 | | 7/23/2010 | | PASS |
Carl Westfall
|
|
|
7/23/2010 09:24:46 CJW - activity updated through activity BLDA022 from case BLD10-01139.
|
Received Certificate of Value | | | 7/19/2010 | | DONE |
Tisha Gallop
|
|
|
received revised cert of value, see scanned document
|
Plan resubmittals received | | | 7/16/2010 | | |
Carl Westfall
|
|
|
rec'd response letter and two copies of sheets A0.1; A0.2; A2.0; A2.1; A2.2; A5.0 - taken to Carl W
|
Routing - FIRE | 6/15/2010 | 6/15/2010 | 6/17/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/17/2010 | | FAIL |
|
|
|
Failed Plan Check
|
Route to Impact Fee Review | 6/15/2010 | 6/18/2010 | 6/15/2010 | | PASS |
Cindy M. Gould
|
|
|
Existing building no impact fees
|
Routing - PLAN CHECK | 5/28/2010 | | 6/15/2010 | | FAIL |
Carl Westfall
|
|
|
The IBC plan review was started on June 9, 2010 and was finished on June 15, 2010. Revised drawings were required. See the plan review report.
|
Routing - PUBLIC WORKS | 5/21/2010 | | 5/28/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 5/28/2010 | | 5/28/2010 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - New fence/gate enclosing patio - CZC09-00138
|
Routing - Addressing | 5/27/2010 | | 5/27/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 5/21/2010 | 5/21/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/21/2010 | | DONE |
|
|
|
|
Pending Assignment by JCB | 5/21/2010 | | 5/21/2010 | | DONE |
Jason Blais
|
|
|
|