BLD-Final | 8/5/2010 | 8/6/2010 | 8/7/2010 | P | PASS |
Dave Hannah
|
|
|
Kenji--late afternoon if possible please Phone #: ###-####
|
DOC - Permit Finaled | 8/7/2010 | 8/7/2010 | 8/7/2010 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 7/8/2010 | 7/9/2010 | 7/9/2010 | A | PASS |
Jim Sly
|
|
|
Kenji Phone #: ###-####
|
BLD-Framing/Rough-in | 7/2/2010 | 7/6/2010 | 7/6/2010 | P | PASS |
Dave Hannah
|
|
|
kengi Phone #: ###-####
|
OVERRIDE | | | 6/29/2010 | | |
|
|
|
|
Routing Walk-In (Zoning) | 6/29/2010 | 6/29/2010 | 6/29/2010 | A | PASS |
David Moser
|
|
|
6/29/2010 11:23:09 DEM - activity updated through activity BLDI252 from case BLD10-01154. Approved as per CAA10-00127 for ADU
|
Routing Walk-In (BLD) | 6/29/2010 | 6/29/2010 | 6/29/2010 | A | DONE |
Perry Paine
|
|
|
6/29/2010 12:46:47 PEP - activity updated through activity BLDA022 from case BLD10-01154.
|
Case Summary (BLD) | | | 6/29/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2010 | | |
|
|
|
|
1st review completed | | | 6/29/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/29/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/29/2010 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/29/2010 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/29/2010 | | DONE |
|
|
|
|
BLD-Foundation | 6/9/2010 | 6/9/2010 | 6/10/2010 | P | PASS |
Dave Hannah
|
|
|
Kenji Phone #: ###-####
|
BLD-Footing | 6/3/2010 | 6/3/2010 | 6/3/2010 | P | PASS |
Dave Hannah
|
|
|
kenji Phone #: ###-####
|
PubWorks Subgrade Approval | 6/3/2010 | 6/3/2010 | 6/3/2010 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Routing Walk-In (BLD) | 6/2/2010 | 6/2/2010 | 6/2/2010 | A | DONE |
Perry Paine
|
|
|
6/2/2010 09:42:35 PEP - activity updated through activity BLDA022 from case BLD10-01154.
|
Case Summary (BLD) | | | 6/2/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/2/2010 | | |
|
|
|
|
1st review completed | | | 6/2/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2010 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/2/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing Walk-In (BLD) | 5/24/2010 | 5/25/2010 | 5/25/2010 | P | FAIL |
Perry Paine
|
|
|
3-hours
|
Routing Walk-In (PW Hillside) | 5/24/2010 | 5/24/2010 | 5/24/2010 | P | DONE |
Colleen T Carroll
|
|
|
footing subgrade must be approved by the applicants geotechnical engineer prior to scheduling footing inspection.
|
Routing Walk-In (Zoning) | 5/24/2010 | 5/24/2010 | 5/24/2010 | P | PASS |
Joshua Johnson
|
|
|
|
Application received | | 5/24/2010 | | | |
|
|
|
|