BLD-Final | 10/7/2010 | 10/7/2010 | 10/7/2010 | P | PASS |
Mike Jordan
|
|
|
kelly Phone #: ###-####
|
DOC - Permit Finaled | 10/7/2010 | 10/7/2010 | 10/7/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 8/31/2010 | 8/31/2010 | 8/31/2010 | P | PASS |
Mike Jordan
|
|
|
kelly Phone #: ###-####
|
BLD-Framing/Rough-in | 8/31/2010 | 8/31/2010 | 8/31/2010 | P | PASS |
Mike Jordan
|
|
|
kelly Phone #: ###-####. Egress window sill height has been corrected.
|
BLD-Framing/Rough-in | 8/26/2010 | 8/27/2010 | 8/27/2010 | A | PART |
Jim Storey
|
|
|
kelly Phone #: ###-#### egress window sil to high. c/n posted ok to insulate.
|
BLD-Framing/Rough-in | 8/24/2010 | 8/24/2010 | 8/24/2010 | P | NR |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Needs to complete airseal package prior to framing inspection. Correction notice posted.
|
BLD-Foundation | 7/23/2010 | 7/23/2010 | 7/23/2010 | P | PASS |
Mike Jordan
|
|
|
jerry Phone #: ###-####. Stemwall for additional scope of work ok.
|
BLD-Footing | 7/22/2010 | 7/22/2010 | 7/22/2010 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 7/22/2010 | | DONE |
Tisha Gallop
|
|
|
picked up and paid for plan modification
|
OVERRIDE | | | 7/19/2010 | | |
|
|
|
|
Routing - PLAN CHECK | 7/14/2010 | | 7/19/2010 | | PASS |
Perry Paine
|
|
|
|
Inspection Record Card- Bld | | | 7/19/2010 | | DONE |
Tisha Gallop
|
|
|
new card per modification to plan
|
Telephone call | | | 7/19/2010 | | DONE |
Tisha Gallop
|
|
|
called and left vm for Kelly Perryman modified plans approved and fees due.
|
Permit Ready to Issue | | | 7/19/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
received full set of revised plans to change from two car garage to three car garage; routed to planning.
|
Routing - PLANNING | 7/14/2010 | | 7/14/2010 | | PASS |
Colleen T Carroll
|
|
|
|
BLD-Foundation | 6/16/2010 | 6/16/2010 | 6/16/2010 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Footing | 6/15/2010 | 6/15/2010 | 6/15/2010 | P | PASS |
Mike Jordan
|
|
|
jerry Phone #: ###-####. All ESC issues were resolved.
|
BLD-Footing | 6/14/2010 | 6/15/2010 | 6/15/2010 | A | PEND |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. Footing ok. No esc measures established. No concrete allowed at this time until esc issues resolved.
|
OVERRIDE | | | 6/11/2010 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/11/2010 | | DONE |
Tisha Gallop
|
|
|
|
Telephone call | | | 6/11/2010 | | DONE |
|
|
|
left vm for kelly at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/11/2010 | | DONE |
|
|
|
|
Route to Impact Fee Review | 6/10/2010 | 6/15/2010 | 6/10/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (PEP) | 6/10/2010 | 6/10/2010 | 6/10/2010 | | PASS |
Perry Paine
|
|
|
6/10/2010 13:00:23 PEP - activity updated through activity BLDA022 from case BLD10-01177.
|
Plan assigned to (CDM) | 5/27/2010 | 5/27/2010 | 6/10/2010 | | DEFR |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/2/2010 | | 6/10/2010 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 6/10/2010 | | |
|
|
|
|
1st review completed | | | 6/10/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/10/2010 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 5/28/2010 | | 6/10/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing - PLANNING | | | 6/2/2010 | | PASS |
Colleen T Carroll
|
|
|
Garage interior needs to be 20' x 20'
|
Routing - Addressing | 5/27/2010 | | 5/28/2010 | | PASS |
April Wing
|
|
|
|
Routing - Erosion and Sediment | 5/28/2010 | | 5/28/2010 | | PASS |
Clint A Smith
|
|
|
ESC10-00440 plan approved with attached conditions.
|
Application received | | 5/26/2010 | 5/27/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 5/27/2010 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/27/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/27/2010 | | DONE |
Tisha Gallop
|
|
|
|