BLD-Final | 12/16/2010 | 12/16/2010 | 12/16/2010 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by Robert Hunter
|
DOC - Permit Finaled | 12/16/2010 | 12/16/2010 | 12/16/2010 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 12/13/2010 | 12/13/2010 | 12/16/2010 | | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 10/11/2010 | 10/12/2010 | 10/12/2010 | A | PART |
Dave Hannah
|
|
|
bob Phone #: ###-#### walls ok ceiling still needs to be blowen
|
BLD-Energy code compliance | 10/5/2010 | 10/6/2010 | 10/6/2010 | A | PART |
Tom Arcoraci
|
|
|
bob Phone #: ###-#### framing ok
|
BLD-Foundation | 8/16/2010 | 8/16/2010 | 8/17/2010 | P | PART |
Dave Hannah
|
|
|
jay Phone #: ###-#### walls ok
|
BLD-Foundation | 7/26/2010 | 7/26/2010 | 7/26/2010 | P | PASS |
Dave Hannah
|
|
|
Jay Phone #: ###-####
|
BLD-Footing | 7/21/2010 | 7/22/2010 | 7/22/2010 | A | PASS |
Dave Hannah
|
|
|
jay Phone #: ###-####
|
PubWorks Subgrade Approval | 7/16/2010 | 7/16/2010 | 7/16/2010 | | DONE |
Terry Records
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 7/8/2010 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 6/10/2010 | | DONE |
|
|
|
|
Telephone call | | | 6/10/2010 | | DONE |
|
|
|
left message w jan at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 6/10/2010 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 6/1/2010 | 6/1/2010 | 6/9/2010 | | DONE |
Perry Paine
|
|
|
|
Routing - PLAN CHECK | 6/8/2010 | | 6/9/2010 | | PASS |
Perry Paine
|
|
|
|
Case Summary (BLD) | | | 6/9/2010 | | |
|
|
|
|
1st review completed | | | 6/9/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/9/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | | | 6/9/2010 | | PASS |
Perry Paine
|
|
|
|
Routing - FIRE | 6/8/2010 | | 6/8/2010 | | PASS |
Scott Arellano
|
|
|
Modified (all rooms and one line of sprinklers in the garage) NFPA 13D sprinkler system is required in all building per letter dated 11-28-05 from David Miller.
|
Routing - Erosion and Sediment | 6/7/2010 | | 6/8/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and the ESC permit conditions. ESC10-00448
|
Routing - PLANNING | 6/4/2010 | | 6/7/2010 | | PASS |
Joshua Johnson
|
|
|
Route to Josh J. CAA10-00053
|
Routing - PUBLIC WORKS | 6/1/2010 | | 6/4/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 6/1/2010 | | 6/3/2010 | | PASS |
April Wing
|
|
|
|
Route to Impact Fee Review | 5/28/2010 | 6/3/2010 | 6/1/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Walk-In (PW Hillside) | 5/28/2010 | 5/28/2010 | 5/28/2010 | A | PASS |
Terry Records
|
|
|
Footing subgrade must be approved by the applicants geotechnical engineer prior to scheduling the footing inspection
|
Routing Walk-In (Zoning) | 5/28/2010 | 5/28/2010 | 5/28/2010 | P | PASS |
Terry Records
|
|
|
|
Application received | | 5/28/2010 | | | |
|
|
|
|