(DA DAVIDSON & COMPANY - US Bank Building - Ste#1801 - 18th Floor) PLAN MODIFICATION 7-22-10 - Modification submitted to reconfigure office and work stations layout. The reconfiguring of the space will also spark ceiling and lighting changes. **TLW** Permit is to remodel a 9,126 sqaure foot portion of an existing office tenant space (Stole Rives - BLD04-00029. Approval contingent upon adhering to the approved plans on file and attached engineering. Work to include: construction of interior non-bearing walls to create multiple additional office use areas, a conference room (432 square feet), demo / infill existing open stairway, install spray on fire-proofing, installation of new plumbing, installation of new doors / hardware, relocating / removing existing lighting, and finishes in compliance with chapter 8 of the 2006 IBC. This building is fully fire sprinklered any alterations or modifications to the sprinkler system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA #13 as regulated by the fire department. Racking that exceeds 8 ft. in height requires a separate Building Permit be submitted and approved before installation. PLAN MODIFICATION 7-22-10 - Modification submitted to reconfigure office and work stations layout. The reconfiguring of the space will also spark ceiling and lighting changes. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 12/26/201012/21/2010 DONE
Second Notice 12/18/201012/21/2010 DONE
First Notice 11/26/201012/8/2010 DONE
Permanent Occupancy UNPAID FEE  11/16/2010 DONE
DetailsTisha Gallop
BLD-Final11/12/201011/12/201011/12/2010PPASS
DetailsTom Arcoraci
sam Phone #: ###-####
BLD-Aging Inspection11/9/201011/9/201011/9/2010 PART
DetailsDave Hannah
waiting on plumbing
BLD-Final9/9/20109/9/20109/9/2010PPASS
DetailsTony Young
sam Phone #: ###-####,, temp occ. ok to move in,, waiting on cabinets,, then need final plumbing inspection
FIRE-Final Inspection9/8/20109/9/20109/9/2010APASS
DetailsForrest France
Fire life safety completed acceptable, inspection passed.
BLD-Framing/Rough-in8/23/20108/23/20108/24/2010PPART
DetailsDave Hannah
Sam-Cover inspection please Phone #: ###-#### ok to cover ceiling
BLD-Wall cover7/23/20107/23/20107/26/2010PPASS
DetailsDave Hannah
duane Phone #: ###-####
Print Occupancy Form  7/23/2010 DONE
Permit Ready to Issue  7/23/2010 DONE
Telephone call  7/23/2010 DONE
Called Martin Hahle and told him that permit is ready & fees due on 7-23-10
CHANGE STATUS TO (ISS)  7/23/2010 DONE
(F) Reprint permit  7/23/2010  
Plan assigned to (TLW)7/9/2010 7/22/2010 PASS
DetailsTim L. Woodard
7/22/2010 14:10:50 TLW - activity updated through activity BLDA022 from case BLD10-01203.
Routing - PLAN CHECK7/22/2010 7/22/2010 PASS
DetailsTim L. Woodard
Plan mod. approved to reconfigure the 18th floor approved floor plan. The layout changes spark lighting and cieling changes as well. TLW
PLANS/APPL TAKEN TO FRONT DESK  7/22/2010 DONE
DetailsTim L. Woodard
Case Summary (BLD)  7/22/2010 DONE
DetailsTim L. Woodard
Plan Modification Accepted  7/9/2010 DONE
DetailsTisha Gallop
Plan modification accepted for Bld10-01203 (DA Davidson & Company) to revise layout of rooms 1837, 1835, 1834, 1833A and 1833B. Added rooms 1836B, 1836A, and 1835A. Added additional electrical receptacles/telephone & data. Reconfigured lighting in above mentioned areas. Submitted on plan sheets A0.1, A0.2, A1.1, A1.2, A2.1, A3.1, A5.1, A5.2, A6.1, A9.1, A9.2, E2.1, E2.2, E3.1; routed to Tim Woodard
Issue PAID IN FULL permit  6/23/2010 DONE
Permit Ready to Issue  6/10/2010 DONE
Telephone call  6/10/2010 DONE
called Martin Hahle permit ready and fee given Also need GC # 6-10-10 ///dld
Routing - FIRE  6/9/2010 PASS
DetailsTim L. Woodard
1st review completed  6/9/2010 DONE
DetailsTim L. Woodard
PLANS/APPL TAKEN TO FRONT DESK  6/9/2010 DONE
DetailsTim L. Woodard
Case Summary (BLD)  6/9/2010 DONE
DetailsTim L. Woodard
Case Summary (BLD)  6/9/2010 DONE
DetailsTim L. Woodard
Print Occupancy Form  6/9/2010 DONE
Plan assigned to (TLW)6/1/2010 6/9/2010 PASS
DetailsTim L. Woodard
6/9/2010 14:13:16 TLW - activity updated through activity BLDA022 from case BLD10-01203.
Routing - PLAN CHECK6/4/2010 6/9/2010 PASS
DetailsTim L. Woodard
Approved
Routing - PUBLIC WORKS6/1/2010 6/4/2010 PASS
DetailsConnie Baumgartner
Routing PW Sewer Rating6/2/2010 6/3/2010 PASS
DetailsConnie Baumgartner
Routing - Addressing6/2/2010 6/2/2010 PASS
DetailsApril Wing
Plans ACCEPTED BY PLAN TECH  6/1/2010 DONE
ok per Tim Woodard to take in as a level 2
Recd Pcfee & Taken To Pln CK  6/1/2010 DONE
Application received 5/28/20105/28/2010 DONE
DetailsBarbara Stitt