Second Notice | | 11/20/2010 | 11/22/2010 | | DONE |
|
|
|
|
First Notice | | 10/30/2010 | 11/10/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/20/2010 | | DONE |
|
|
|
|
Permanent Occupancy | | | 10/20/2010 | | |
|
|
|
|
BLD-Final | 10/18/2010 | 10/19/2010 | 10/19/2010 | A | PASS |
Jim Storey
|
|
|
Terry Phone #: ###-####
|
FIRE-Final Inspection | 10/18/2010 | 10/18/2010 | 10/18/2010 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed, covers at extinguisher cabinets removed while on site, some doors and hardware not yet installed to be verified at structural final.
|
BLD-Other | 9/22/2010 | 9/23/2010 | 9/23/2010 | A | PASS |
Jim Storey
|
|
|
terry grid ceiling Phone #: ###-####
|
BLD-Framing/Rough-in | 8/3/2010 | 8/4/2010 | 8/4/2010 | A | PASS |
Tom Arcoraci
|
|
|
Terry Phone #: ###-#### check 1????? hr wall at grid inspection
|
Issue PAID IN FULL permit | | | 6/28/2010 | | |
|
|
|
|
Telephone call | | | 6/25/2010 | | DONE |
|
|
|
t/c w matt at ###-#### - permit ready and fees given - also need gc name and rce#
|
Permit Ready to Issue | | | 6/25/2010 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 6/3/2010 | 6/3/2010 | 6/24/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/7/2010 | | 6/24/2010 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 6/24/2010 | | DONE |
|
|
|
|
Routing - FIRE | | | 6/24/2010 | | PASS |
|
|
|
Verify in field CDM
|
Case Summary (BLD) | | | 6/24/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/2010 | | |
|
|
|
|
Print Occupancy Form | | | 6/24/2010 | | DONE |
|
|
|
|
Routing PW Sewer Rating | 6/7/2010 | | 6/7/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Flood Plain | 6/7/2010 | | 6/7/2010 | | PASS |
Jim Wyllie
|
|
|
Building is not in the floodplain as per LOMR of March 7, 2003.
|
Routing - PUBLIC WORKS | 6/3/2010 | | 6/7/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 6/4/2010 | | 6/4/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 6/3/2010 | 6/3/2010 | | DONE |
Darla L Downs
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/3/2010 | | DONE |
|
|
|
ok per Carl Madsen to take in as a level 2
|
Recd Pcfee & Taken To Pln CK | | | 6/3/2010 | | DONE |
|
|
|
|