Third Notice | | 12/8/2010 | 12/1/2010 | | DONE |
|
|
|
|
Third Notice | | 10/26/2010 | 11/24/2010 | | DONE |
|
|
|
faxed
|
Second Notice | | 10/21/2010 | 10/21/2010 | | DONE |
|
|
|
|
First Notice | | 9/24/2010 | 10/11/2010 | | DONE |
|
|
|
|
BLD-Final | 9/13/2010 | 9/14/2010 | 9/14/2010 | A | PASS |
Mike Jordan
|
|
|
andy Phone #: ###-####. All issues were resolved. Ok for perm occupancy.
|
Permanent Occupancy | | | 9/14/2010 | | |
|
|
|
|
BLD-Final | 9/13/2010 | 9/13/2010 | 9/13/2010 | P | FAIL |
Mike Jordan
|
|
|
Andy Becker Phone #: ###-####. Exit discharge lighting ok. Needs to provide tacktile exit sign at main exit and mount vertical grab bars at correct locations in both restrooms.
|
FIRE-Final Inspection | 9/13/2010 | 9/13/2010 | 9/13/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed. The building inspector is going to verify the exit discharge lighting.
|
BLD-Final | 9/9/2010 | 9/13/2010 | 9/13/2010 | A | NR |
Mike Jordan
|
|
|
Andy Becker Phone #: ###-####. Life/safety inspection failed.
|
FIRE-Final Inspection | 9/10/2010 | 9/13/2010 | 9/13/2010 | A | FAIL |
Troy Cobbley
|
|
|
Provide exit discharge lighting.
|
Print Occupancy Form | | | 8/23/2010 | | DONE |
|
|
|
|
BLD-Other | 8/19/2010 | 8/19/2010 | 8/19/2010 | P | PASS |
Mike Jordan
|
|
|
ceiling grid ok.
|
BLD-Framing/Rough-in | 8/18/2010 | 8/18/2010 | 8/18/2010 | P | NR |
Mike Jordan
|
|
|
Ceiling Grid inspection please-Andy Becker Phone #: ###-####. Needs other trades rough in inspections first. Andy was notified.
|
BLD-Framing/Rough-in | 7/30/2010 | 7/30/2010 | 7/30/2010 | P | PASS |
Jim Sly
|
|
|
andy - please call 1/2 hr prior Phone #: ###-#### Hard ceiling OK to cover.
|
BLD-Framing/Rough-in | 7/19/2010 | 7/20/2010 | 7/20/2010 | P | PASS |
Mike Jordan
|
|
|
andy Phone #: ###-####. Interior steel stud framed walls only. No grid.
|
BLD-Framing/Rough-in | 7/19/2010 | 7/20/2010 | 7/19/2010 | P | CANC |
Tony Young
|
|
|
|
BLD-Framing/Rough-in | 7/19/2010 | 7/19/2010 | 7/19/2010 | P | NR |
Tony Young
|
|
|
andy Phone #: ###-####,, need trades 1st
|
BLD-Framing/Rough-in | 7/19/2010 | 7/19/2010 | 7/19/2010 | P | CANC |
Tony Young
|
|
|
andy Phone #: ###-####
|
Issue PAID IN FULL permit | | | 7/6/2010 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 6/3/2010 | 6/3/2010 | 7/1/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/21/2010 | | 7/1/2010 | | PASS |
Carl D Madsen
|
|
|
|
Plan resubmittals received | | | 7/1/2010 | | |
Carl D Madsen
|
|
|
Rec'd 2 copies of sheets E00.00; E02.01; E08.01 - taken to Carl M
|
Case Summary (BLD) | | | 7/1/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/1/2010 | | |
|
|
|
|
Print Occupancy Form | | | 7/1/2010 | | DONE |
|
|
|
|
Telephone call | | | 7/1/2010 | | DONE |
|
|
|
t/c w connie at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/1/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/7/2010 | | 6/21/2010 | | FAIL |
Carl D Madsen
|
|
|
New lighting compliance and lighting sheet is required. Sent E-Mail and left message for Megan at Kling Stubbins 6-21-10 CDM
|
Routing - FIRE | 6/21/2010 | | 6/21/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
1st review completed | | | 6/21/2010 | | FAIL |
|
|
|
|
Routing PW Sewer Rating | 6/7/2010 | | 6/7/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PUBLIC WORKS | 6/3/2010 | | 6/7/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 6/3/2010 | | 6/4/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 6/3/2010 | 6/3/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/3/2010 | | DONE |
|
|
|
|