(Ada County Paramedics T.I.) Remodel an existing 15,791sq. ft., 2 story office building proposed for use as Ada County Paramedic office and training facility. Building to be fully sprinklered with a fire alarm system as part of remodel. Sprinkler system is used for allowable area increase and added story for compliance of "A3" occupancy in 2 story building. Addition of 555 sq. ft. 2 story enclosed stair /vestibule / entry and new interior elevator and elevator equipment room. Work includes select demolition at exterior and throughout interior of both floors. Construct new alls to create offices, training rooms, reception, common use and support areas; interior finishes, millwork, electrical, mechanical, plumbing, sprinkler and alarm work, all per reviewed plans. Post maximum occupant load sign of 107, Room 110; 100, Room 11; and 217 when room combined into one room for assembly) drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
First Notice 6/2/20116/6/2011 DONE
DetailsChristina Prado
Done
BLD-Final5/23/20115/23/20115/23/2011PPASS
DetailsMike Jordan
gary Phone #: ###-####. All issues were resolved. Ok for perm occ.
Permanent Occupancy  5/23/2011 DONE
DetailsChristina Prado
BLD-Final4/21/20114/21/20114/21/2011PPART
DetailsMike Jordan
Early pm if possible. Call if you know when you are close. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Ok for teemp occ. Needs to reinstall vertical grab bars in restroom, 1st. floor and install ada butoon in vesibule at south addition, 1st. floor.
FIRE-Final Inspection4/20/20114/21/20114/21/2011APASS
DetailsTroy Cobbley
life safety passed
Temporary Occupancy UNPAID FEE  4/21/2011 DONE
DetailsTisha Gallop
FIRE-Final Inspection4/19/20114/20/20114/20/2011PFAIL
DetailsTroy Cobbley
Life safety will be able to be finaled when the exit discharge light at the east exit door is repaired.
FIRE-Final Inspection4/14/20114/15/20114/15/2011ACANC
DetailsTroy Cobbley
Life safety inspection not performed until the project related fire alarm and fire sprinkler permits have been finaled. Per the electrician two emergency lights have failed and are currently scheduled to be replaced.
BLD-Other4/7/20114/7/20114/7/2011PPASS
DetailsMike Jordan
South addition ceilings. Early pm if possible. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Remainder of 2ndfloor ceiling grid at south addition.
BLD-Other4/5/20114/6/20114/6/2011APART
DetailsMike Jordan
Stair ceiling cover. partial Phone #: ###-#### >> Inspection requested via web by Gary Simon. Grid downstairs adn upper portion of 2nd. floor.
Zoning Approval4/6/20114/6/20114/6/2011 PASS
DetailsJosh Wilson
PubWorks Occupancy Approval4/4/20114/4/20114/4/2011 DONE
DetailsTiffany Lowery
BLD-Card not on site to sign3/25/20113/28/20113/28/2011PPASS
DetailsMike Jordan
Accoustical ceiling grid, 2nd floor. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Energy code compliance3/23/20113/24/20113/24/2011APASS
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Gary Simon. South addition ok.
BLD-Wall cover3/22/20113/22/20113/22/2011PPASS
DetailsMike Jordan
South addition framing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Other3/18/20113/18/20113/18/2011PPASS
DetailsMike Jordan
Grid ceiling in large room of the remodel. (1st floor) Phone #: ###-#### >> Inspection requested via web by Gary Simon
BLD-Other3/14/20113/14/20113/14/2011PPASS
DetailsMike Jordan
Grid ceiling inspection. Phone #: ###-#### >> Inspection requested via web by Gary Simon. 1st. floor only.
BLD-Other3/14/20113/15/20113/14/2011ACANC
DetailsMike Jordan
Ceiling grid inspection 1st floor. Phone #: ###-#### >> Inspection requested via web by Gary Simon Inspection cancelled from web by: Gary Simon
BLD-Framing/Rough-in2/23/20112/24/20112/24/2011APASS
DetailsMike Jordan
Mike, I need you to inspect the roof sheeting on the addition and look at a existing handrail. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Inspected roof diaphragm attatchment at new entryway, also inspected exisiting handrail, will bring to code.
BLD-Framing/Rough-in2/11/20112/11/20112/11/2011PPASS
DetailsMike Jordan
Soffits in emodel for cover Phone #: ###-#### >> Inspection requested via web by Gary Simon. Interior metal stud soffits at 1st. floor conferance room.
BLD-Framing/Rough-in1/20/20111/20/20111/20/2011PPART
DetailsMike Jordan
Mike, this is for the 2nd floor of the remodel. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Interior wood framed walls for 2nd. floor only. Pending plumbing rough in inspection.
BLD-Framing/Rough-in11/23/201011/23/201011/23/2010PPART
DetailsMike Jordan
Ist floor of the remodel. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Permiter walls and interior wood frsmed walls only.
BLD-Framing/Rough-in11/12/201011/15/201011/15/2010APASS
DetailsMike Jordan
Mike, I need an inspection for the elevator ceiling so I can sheetrock before the scaffling is removed. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Roof infill and joist modification above new elevator shaft.
BLD-Footing11/1/201011/2/201011/2/2010APASS
DetailsMike Jordan
Mike, we are pouring the south elevation addition ftgs. at 12:00pm Phone #: ###-#### >> Inspection requested via web by Gary Simon
Issue PAID IN FULL permit  8/16/2010 DONE
Plan assigned to (DRS)6/7/20106/7/20107/22/2010 PASS
DetailsDan Stuart
7/22/2010 08:40:02 JCB - activity updated through activity BLDA022 from case BLD10-01256.
Routing - PLAN CHECK7/20/2010 7/22/2010 PASS
DetailsJason Blais
Plans approved by all review disciplines and taken to permit counter for processing.
PLANS/APPL TAKEN TO FRONT DESK  7/22/2010 DONE
DetailsJason Blais
Print Occupancy Form  7/22/2010 DONE
Permit Ready to Issue  7/22/2010  
Telephone call  7/22/2010  
Called Scott Wendell and told him that the permit is ready, fees due, need ACHD, GC, RCE/T & RP info on 7-22-10 @ 3:00 pm
Routing - PLUMBING7/15/2010 7/20/2010 PASS
DetailsBill VanDegrift
individual water meters will be required. approved per plumbing resubmittals dated 6/29/10.
Routing PW Solid Waste  7/16/2010 PASS
DetailsPeter J. McCullough
Routing - FIRE7/9/20107/9/20107/15/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
Plan resubmittals received  7/15/2010  
DetailsDan Stuart
rec'd response letter and two copies of sheets .0.0; A0.1; A2.10; A2.20; A3.0; A3.1; A3.2; A8.0; M3.01 - taken to Dan S
1st review completed  7/15/2010 FAIL
Failed Public Works, Plumbing
Routing - PLAN CHECK7/15/2010 7/15/2010 PASS
DetailsDan Stuart
Deferred submittals as listed on cover sheet required to be submitted and reviewed for approval before any work can proceed on these items. Routing plans back to plumbing for review.
Route to Impact Fee Review7/9/20107/14/20107/9/2010 PASS
DetailsCindy M. Gould
Plan resubmittals requested  7/9/2010 DONE
Copy of plan review e-mailed to architect for response through plan resubmittals to show code compliance.
Routing - PLAN CHECK6/28/2010 7/9/2010 FAIL
DetailsDan Stuart
Resubmittals required. Copy of plan review comments routed to architect for response for code compliance. Routing plans to fire code analyst for review.
Routing Off Site - STRUCTURAL7/7/2010 7/9/2010 PASS
DetailsDan Stuart
Received e-mail stating structural review resubmittals resolved questions and concerns and structural review is approved.
Plan resubmittals received  7/7/2010  
DetailsDan Stuart
rec'd response letter and two copies of sheets S0.1and S5.2 - taken to Dan S
Plan resubmittals received  6/29/2010 DONE
DetailsTisha Gallop
received two copies of plan sheets P1.01, P1.02, P2.01; taken to Dan Stuart
Routing - PLUMBING6/25/2010 6/28/2010 FAIL
DetailsBill VanDegrift
need resubmittals
Routing - PUBLIC WORKS6/25/2010 6/25/2010 PASS
DetailsBeverly Mountain
Routing PW Drainage6/22/2010 6/24/2010 PASS
DetailsBrian Murphy
Plans picked up by Brian. He had received resubmittals for re-review.
Plan resubmittals requested  6/22/2010 DONE
Copy of Structural Plan Review corrections e-mailed to Steve simmons & Scott wendell, LCA Arch.
Routing Off Site - STRUCTURAL6/8/2010 6/21/2010 FAIL
DetailsDan Stuart
Copy of structural plan review items needing to be addressed e-mailed to Steve Simmons & Scott Wendell, LCA Arch.
Routing - PLAN CHECK6/18/2010 6/18/2010 PEND
DetailsDan Stuart
Plans retrieved by Brian Murphy for review of resubmittals received regarding drainage.
Routing - PLUMBING6/15/2010 6/18/2010 FAIL
DetailsBill VanDegrift
waste line to the second floor is undersized. looks like you missed he waste to the janitor sink on the second floor, the S-2 in storage room 109, and the S-1 in room 112. and piping to shower. verify the water purveyor will allow both buildings on the same service.
Routing - PLANNING6/18/2010 6/18/2010 PASS
DetailsAndrea Tuning
Routing - Erosion and Sediment6/14/2010 6/15/2010 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC plan and ESC permit conditions. Certified RP is required prior to start of work. Inform Boise City Building Department of RP at ###-####. ESC10-00463
Routing - PUBLIC WORKS6/7/2010 6/14/2010 FAIL
DetailsConnie Baumgartner
Routing PW Drainage  6/11/2010 FAIL
DetailsBrian Murphy
NEEDS REVISIONS AND GEOTECH BRIAN MRPHY ###-####
Routing PW Street Lights6/11/2010 6/11/2010 PASS
DetailsHank Alarcon
Routing PW Sewer Design6/8/2010 6/9/2010 PASS
DetailsJon R. Gunnerson
Sewer Tap Permit Required. Connect into SSMH 561L
Routing - Addressing6/8/2010 6/8/2010 PASS
DetailsApril Wing
Routing PW Sewer Rating6/8/2010 6/8/2010 PASS
DetailsConnie Baumgartner
Print Pending Permit.LaserJet4  6/7/2010  
Application received 6/4/20106/4/2010 DONE
Intake Approval  6/4/2010 PASS
Plans ACCEPTED BY PLAN TECH  6/4/2010 DONE