First Notice | | 6/2/2011 | 6/6/2011 | | DONE |
Christina Prado
|
|
|
Done
|
BLD-Final | 5/23/2011 | 5/23/2011 | 5/23/2011 | P | PASS |
Mike Jordan
|
|
|
gary Phone #: ###-####. All issues were resolved. Ok for perm occ.
|
Permanent Occupancy | | | 5/23/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 4/21/2011 | 4/21/2011 | 4/21/2011 | P | PART |
Mike Jordan
|
|
|
Early pm if possible. Call if you know when you are close. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Ok for teemp occ. Needs to reinstall vertical grab bars in restroom, 1st. floor and install ada butoon in vesibule at south addition, 1st. floor.
|
FIRE-Final Inspection | 4/20/2011 | 4/21/2011 | 4/21/2011 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Temporary Occupancy UNPAID FEE | | | 4/21/2011 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 4/19/2011 | 4/20/2011 | 4/20/2011 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be able to be finaled when the exit discharge light at the east exit door is repaired.
|
FIRE-Final Inspection | 4/14/2011 | 4/15/2011 | 4/15/2011 | A | CANC |
Troy Cobbley
|
|
|
Life safety inspection not performed until the project related fire alarm and fire sprinkler permits have been finaled. Per the electrician two emergency lights have failed and are currently scheduled to be replaced.
|
BLD-Other | 4/7/2011 | 4/7/2011 | 4/7/2011 | P | PASS |
Mike Jordan
|
|
|
South addition ceilings. Early pm if possible. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Remainder of 2ndfloor ceiling grid at south addition.
|
BLD-Other | 4/5/2011 | 4/6/2011 | 4/6/2011 | A | PART |
Mike Jordan
|
|
|
Stair ceiling cover. partial Phone #: ###-#### >> Inspection requested via web by Gary Simon. Grid downstairs adn upper portion of 2nd. floor.
|
Zoning Approval | 4/6/2011 | 4/6/2011 | 4/6/2011 | | PASS |
Josh Wilson
|
|
|
|
PubWorks Occupancy Approval | 4/4/2011 | 4/4/2011 | 4/4/2011 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Card not on site to sign | 3/25/2011 | 3/28/2011 | 3/28/2011 | P | PASS |
Mike Jordan
|
|
|
Accoustical ceiling grid, 2nd floor. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Energy code compliance | 3/23/2011 | 3/24/2011 | 3/24/2011 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gary Simon. South addition ok.
|
BLD-Wall cover | 3/22/2011 | 3/22/2011 | 3/22/2011 | P | PASS |
Mike Jordan
|
|
|
South addition framing. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 3/18/2011 | 3/18/2011 | 3/18/2011 | P | PASS |
Mike Jordan
|
|
|
Grid ceiling in large room of the remodel. (1st floor) Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 3/14/2011 | 3/14/2011 | 3/14/2011 | P | PASS |
Mike Jordan
|
|
|
Grid ceiling inspection. Phone #: ###-#### >> Inspection requested via web by Gary Simon. 1st. floor only.
|
BLD-Other | 3/14/2011 | 3/15/2011 | 3/14/2011 | A | CANC |
Mike Jordan
|
|
|
Ceiling grid inspection 1st floor. Phone #: ###-#### >> Inspection requested via web by Gary Simon Inspection cancelled from web by: Gary Simon
|
BLD-Framing/Rough-in | 2/23/2011 | 2/24/2011 | 2/24/2011 | A | PASS |
Mike Jordan
|
|
|
Mike, I need you to inspect the roof sheeting on the addition and look at a existing handrail. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Inspected roof diaphragm attatchment at new entryway, also inspected exisiting handrail, will bring to code.
|
BLD-Framing/Rough-in | 2/11/2011 | 2/11/2011 | 2/11/2011 | P | PASS |
Mike Jordan
|
|
|
Soffits in emodel for cover Phone #: ###-#### >> Inspection requested via web by Gary Simon. Interior metal stud soffits at 1st. floor conferance room.
|
BLD-Framing/Rough-in | 1/20/2011 | 1/20/2011 | 1/20/2011 | P | PART |
Mike Jordan
|
|
|
Mike, this is for the 2nd floor of the remodel. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Interior wood framed walls for 2nd. floor only. Pending plumbing rough in inspection.
|
BLD-Framing/Rough-in | 11/23/2010 | 11/23/2010 | 11/23/2010 | P | PART |
Mike Jordan
|
|
|
Ist floor of the remodel. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Permiter walls and interior wood frsmed walls only.
|
BLD-Framing/Rough-in | 11/12/2010 | 11/15/2010 | 11/15/2010 | A | PASS |
Mike Jordan
|
|
|
Mike, I need an inspection for the elevator ceiling so I can sheetrock before the scaffling is removed. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Roof infill and joist modification above new elevator shaft.
|
BLD-Footing | 11/1/2010 | 11/2/2010 | 11/2/2010 | A | PASS |
Mike Jordan
|
|
|
Mike, we are pouring the south elevation addition ftgs. at 12:00pm Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
Issue PAID IN FULL permit | | | 8/16/2010 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 6/7/2010 | 6/7/2010 | 7/22/2010 | | PASS |
Dan Stuart
|
|
|
7/22/2010 08:40:02 JCB - activity updated through activity BLDA022 from case BLD10-01256.
|
Routing - PLAN CHECK | 7/20/2010 | | 7/22/2010 | | PASS |
Jason Blais
|
|
|
Plans approved by all review disciplines and taken to permit counter for processing.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2010 | | DONE |
Jason Blais
|
|
|
|
Print Occupancy Form | | | 7/22/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/22/2010 | | |
|
|
|
|
Telephone call | | | 7/22/2010 | | |
|
|
|
Called Scott Wendell and told him that the permit is ready, fees due, need ACHD, GC, RCE/T & RP info on 7-22-10 @ 3:00 pm
|
Routing - PLUMBING | 7/15/2010 | | 7/20/2010 | | PASS |
Bill VanDegrift
|
|
|
individual water meters will be required. approved per plumbing resubmittals dated 6/29/10.
|
Routing PW Solid Waste | | | 7/16/2010 | | PASS |
Peter J. McCullough
|
|
|
|
Routing - FIRE | 7/9/2010 | 7/9/2010 | 7/15/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan resubmittals received | | | 7/15/2010 | | |
Dan Stuart
|
|
|
rec'd response letter and two copies of sheets .0.0; A0.1; A2.10; A2.20; A3.0; A3.1; A3.2; A8.0; M3.01 - taken to Dan S
|
1st review completed | | | 7/15/2010 | | FAIL |
|
|
|
Failed Public Works, Plumbing
|
Routing - PLAN CHECK | 7/15/2010 | | 7/15/2010 | | PASS |
Dan Stuart
|
|
|
Deferred submittals as listed on cover sheet required to be submitted and reviewed for approval before any work can proceed on these items. Routing plans back to plumbing for review.
|
Route to Impact Fee Review | 7/9/2010 | 7/14/2010 | 7/9/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan resubmittals requested | | | 7/9/2010 | | DONE |
|
|
|
Copy of plan review e-mailed to architect for response through plan resubmittals to show code compliance.
|
Routing - PLAN CHECK | 6/28/2010 | | 7/9/2010 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review comments routed to architect for response for code compliance. Routing plans to fire code analyst for review.
|
Routing Off Site - STRUCTURAL | 7/7/2010 | | 7/9/2010 | | PASS |
Dan Stuart
|
|
|
Received e-mail stating structural review resubmittals resolved questions and concerns and structural review is approved.
|
Plan resubmittals received | | | 7/7/2010 | | |
Dan Stuart
|
|
|
rec'd response letter and two copies of sheets S0.1and S5.2 - taken to Dan S
|
Plan resubmittals received | | | 6/29/2010 | | DONE |
Tisha Gallop
|
|
|
received two copies of plan sheets P1.01, P1.02, P2.01; taken to Dan Stuart
|
Routing - PLUMBING | 6/25/2010 | | 6/28/2010 | | FAIL |
Bill VanDegrift
|
|
|
need resubmittals
|
Routing - PUBLIC WORKS | 6/25/2010 | | 6/25/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Drainage | 6/22/2010 | | 6/24/2010 | | PASS |
Brian Murphy
|
|
|
Plans picked up by Brian. He had received resubmittals for re-review.
|
Plan resubmittals requested | | | 6/22/2010 | | DONE |
|
|
|
Copy of Structural Plan Review corrections e-mailed to Steve simmons & Scott wendell, LCA Arch.
|
Routing Off Site - STRUCTURAL | 6/8/2010 | | 6/21/2010 | | FAIL |
Dan Stuart
|
|
|
Copy of structural plan review items needing to be addressed e-mailed to Steve Simmons & Scott Wendell, LCA Arch.
|
Routing - PLAN CHECK | 6/18/2010 | | 6/18/2010 | | PEND |
Dan Stuart
|
|
|
Plans retrieved by Brian Murphy for review of resubmittals received regarding drainage.
|
Routing - PLUMBING | 6/15/2010 | | 6/18/2010 | | FAIL |
Bill VanDegrift
|
|
|
waste line to the second floor is undersized. looks like you missed he waste to the janitor sink on the second floor, the S-2 in storage room 109, and the S-1 in room 112. and piping to shower. verify the water purveyor will allow both buildings on the same service.
|
Routing - PLANNING | 6/18/2010 | | 6/18/2010 | | PASS |
Andrea Tuning
|
|
|
|
Routing - Erosion and Sediment | 6/14/2010 | | 6/15/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions. Certified RP is required prior to start of work. Inform Boise City Building Department of RP at ###-####. ESC10-00463
|
Routing - PUBLIC WORKS | 6/7/2010 | | 6/14/2010 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | | | 6/11/2010 | | FAIL |
Brian Murphy
|
|
|
NEEDS REVISIONS AND GEOTECH BRIAN MRPHY ###-####
|
Routing PW Street Lights | 6/11/2010 | | 6/11/2010 | | PASS |
Hank Alarcon
|
|
|
|
Routing PW Sewer Design | 6/8/2010 | | 6/9/2010 | | PASS |
Jon R. Gunnerson
|
|
|
Sewer Tap Permit Required. Connect into SSMH 561L
|
Routing - Addressing | 6/8/2010 | | 6/8/2010 | | PASS |
April Wing
|
|
|
|
Routing PW Sewer Rating | 6/8/2010 | | 6/8/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/7/2010 | | |
|
|
|
|
Application received | | 6/4/2010 | 6/4/2010 | | DONE |
|
|
|
|
Intake Approval | | | 6/4/2010 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/4/2010 | | DONE |
|
|
|
|