Second Notice | | 5/20/2011 | 5/25/2011 | | DONE |
Christina Prado
|
|
|
Faxed 5-25-2011. Done 6/6/11
|
First Notice | | 5/2/2011 | 5/10/2011 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/22/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Forrest France
|
|
|
gary Phone #: ###-####
|
BLD-Final | 4/22/2011 | 4/22/2011 | 4/22/2011 | P | PASS |
Mike Jordan
|
|
|
Mike, with any luck we can do this at least for a temp. I will have Forrest call you when the fire is completed. I need to do this before 2:00 or after 3:00. Thanks Phone #:. ###-#### >> Inspection requested via web by Gary Simon. Ok for perm occ.
|
Permanent Occupancy UNPAID FEE | | | 4/22/2011 | | DONE |
Christina Prado
|
|
|
|
FIRE-Final Inspection | 4/20/2011 | 4/21/2011 | 4/21/2011 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to final when the project related fire alarm and fire sprinkler permits are finaled. No hazardous materials are currently being stored.
|
FIRE-Final Inspection | 4/14/2011 | 4/15/2011 | 4/15/2011 | A | CANC |
Troy Cobbley
|
|
|
No inspection was performed. The project related fire alarm and fire sprinkler permits need to inspected/finaled. The fire alarm plans are currently still in the "review" status.
|
Zoning Approval | 4/6/2011 | 4/6/2011 | 4/6/2011 | | PASS |
Josh Wilson
|
|
|
|
PubWorks Occupancy Approval | 4/4/2011 | 4/4/2011 | 4/4/2011 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Other | 3/14/2011 | 3/14/2011 | 3/14/2011 | P | PASS |
Mike Jordan
|
|
|
Hard lids in office of shop. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 3/14/2011 | 3/15/2011 | 3/14/2011 | A | CANC |
Mike Jordan
|
|
|
Hard ceiling in warehouse of the shop office. Phone #: ###-#### >> Inspection requested via web by Gary Simon Inspection cancelled from web by: Gary Simon
|
BLD-Other | 2/7/2011 | 2/8/2011 | 2/8/2011 | A | NR |
Mike Jordan
|
|
|
Ceiling cover in the Ad.Min area of the shop. (hard lids) Phone #: ###-#### >> Inspection requested via web by Gary Simon. Needs fire sprinkler rough in inspection.
|
BLD-Energy code compliance | 1/10/2011 | 1/10/2011 | 1/10/2011 | P | PASS |
Mike Jordan
|
|
|
Mike, I should be ready by early pm. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Energy code compliance | 12/27/2010 | 12/29/2010 | 12/29/2010 | P | CANC |
Mike Jordan
|
|
|
Mike, I probably will not be onsite. You are looking at the insulation and vapor barrier in the ad-min. area of the shop building. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Cancelled by contractor via phone call.
|
BLD-Conference | 12/22/2010 | 12/22/2010 | 12/22/2010 | P | DONE |
Mike Jordan
|
|
|
Mike, I would like to go over the firewalls on the shop building. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Framing/Rough-in | 12/22/2010 | 12/22/2010 | 12/22/2010 | P | PASS |
Mike Jordan
|
|
|
Mike, I would like to go over the firewalls on the shop building. Phone #: ###-#### >> Inspection requested via web by Gary Simon. All framing issues have been resolved.
|
BLD-Framing/Rough-in | 12/20/2010 | 12/20/2010 | 12/20/2010 | P | PART |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gary Simon. Interior wood framed walls only. Needs to provide putty pads on steel electrical boxes on east and south 1hr. walls, provide 5/8 type x rock behind shower stall on south wall and draft stop around pipes in concelled areas.
|
BLD-Concrete | 11/3/2010 | 11/4/2010 | 11/4/2010 | A | PART |
Mike Jordan
|
|
|
Mike, we are pouring the wash bay tomorrow at9:00 am tomorrow. MTI will look at the vapor barrier and mesh. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Work in progress, Pending special inspection.
|
BLD-Other | 10/28/2010 | 10/28/2010 | 10/28/2010 | P | PART |
Mike Jordan
|
|
|
cmu inspection. Grout at 1:00pm Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Framing/Rough-in | 10/28/2010 | 10/28/2010 | 10/28/2010 | P | PASS |
Mike Jordan
|
|
|
Mike, we are sheeting the mansard trusses and need a inspection. We can also look at the roof nailing. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Nailpattern for exterior shearwalls and roof diapragm ok.
|
Meeting | | | 10/28/2010 | | DONE |
Scott Arellano
|
|
|
Site visit with Fire Marshal. Electronic Gate will NOT include Opticom system. Proposed alternative has been approved by the Fire Marshal, Mark Senteno.
|
BLD-Other | 10/14/2010 | 10/15/2010 | 10/15/2010 | P | PASS |
Mike Jordan
|
|
|
Topping off cmu wall on gridline B of the shop. Special inspection at 12:00pm Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 10/13/2010 | 10/14/2010 | 10/14/2010 | P | DEFR |
Mike Jordan
|
|
|
grouting cmu wall for the shop @ 12'' at 2:00pm. Phone #: ###-#### >> Inspection requested via web by Gary Simon
|
BLD-Other | 10/13/2010 | 10/14/2010 | 10/14/2010 | A | DEFR |
Mike Jordan
|
|
|
Grouting cmu @ 8'' at 10;00am Phone #: ###-#### >> Inspection requested via web by Gary Simon. Special inspector on site.
|
BLD-Other | 10/13/2010 | 10/13/2010 | 10/13/2010 | P | DEFR |
Dave Hannah
|
|
|
We are grouting the cmu walls at 8'' on gridline b of the shop bldg at 12:00pm Phone #: ###-#### >> Inspection requested via web by Gary Simon spec inspection used
|
BLD-Other | 10/12/2010 | 10/13/2010 | 10/13/2010 | A | PART |
Jim Sly
|
|
|
We are grouting the top of gridlines a and 3 for the shop building at 8:00am. Special inspection has been called. Phone #: ###-#### >> Inspection requested via web by Gary Simon OK pending special insp, tests and approvals.
|
BLD-Other | 10/8/2010 | 10/11/2010 | 10/11/2010 | A | PASS |
Tom Arcoraci
|
|
|
We are grouting cmu @ 24'' at 10:00am. Phone #: ###-#### >> Inspection requested via web by Gary Simon pending spec insp ok
|
BLD-Other | 10/7/2010 | 10/7/2010 | 10/7/2010 | P | PASS |
Mike Jordan
|
|
|
We will be grouting cmu again at 3:00 pm Phone #: ###-#### >> Inspection requested via web by Gary Simon. South east and west cmu walls 20ft. elevation.
|
BLD-Other | 10/6/2010 | 10/7/2010 | 10/7/2010 | A | PART |
Mike Jordan
|
|
|
Mike, we are going to grout the cmu wall at 9:30 am on the east and north ends of the shop bldg. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Pending special inspections.
|
BLD-Concrete | 10/5/2010 | 10/7/2010 | 10/7/2010 | A | PART |
Mike Jordan
|
|
|
cmu inspection and wire mesh and vapor barrier for slab. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Work inprogress on south portion of salb.
|
BLD-Other | 10/4/2010 | 10/5/2010 | 10/5/2010 | A | CANC |
Mike Jordan
|
|
|
We are grouting cmu wall at 10:30am. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Griut placement was cancelled due to wheather.
|
BLD-Other | 9/30/2010 | 10/1/2010 | 10/1/2010 | A | PASS |
Tom Arcoraci
|
|
|
Mike, we are grouting again at 8:00am >> Inspection requested via web by Gary Simon
|
BLD-Other | 9/30/2010 | 10/1/2010 | 10/1/2010 | P | CANC |
Mike Jordan
|
|
|
Grouting again at 2:00 pm Phone #: ###-#### >> Inspection requested via web by Gary Simon Inspection cancelled from web by: Gary Simon
|
BLD-Other | 9/29/2010 | 9/30/2010 | 9/30/2010 | A | PART |
Mike Jordan
|
|
|
Early am grout scheduled Phone #: ###-#### >> Inspection requested via web by Gary Simon. Masonry walls, 4ft. to 8ft. elevation, North, sout and east walls. Pending special inspection.
|
BLD-Foundation | 9/21/2010 | 9/22/2010 | 9/22/2010 | A | PART |
Mike Jordan
|
|
|
Late am if possible Phone #: ###-#### >> Inspection requested via web by Gary Simon. Interior stemwalls for interior cmu walls.
|
BLD-Foundation | 9/20/2010 | 9/21/2010 | 9/21/2010 | A | PART |
Mike Jordan
|
|
|
Late am if possible Phone #: ###-#### >> Inspection requested via web by Gary Simon. South stemwalls.
|
BLD-Foundation | 9/16/2010 | 9/17/2010 | 9/17/2010 | A | PART |
Mike Jordan
|
|
|
Late am if possible Phone #: ###-#### >> Inspection requested via web by Gary Simon. Stemwall, north half.
|
BLD-Footing | 9/14/2010 | 9/15/2010 | 9/15/2010 | A | PASS |
Mike Jordan
|
|
|
Late am would be great. Concrete scheduled for 1:00pm. Phone #: ###-#### >> Inspection requested via web by Gary Simon. Permiter footings.
|
Issue PAID IN FULL permit | | | 8/16/2010 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/10/2010 | | DONE |
|
|
|
|
Telephone call | | | 8/10/2010 | | DONE |
|
|
|
left vm for scott at ###-#### - permit ready and fees given - also need ACHD receipt, gc name, rce# and rp name
|
Permit Ready to Issue | | | 8/10/2010 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 6/4/2010 | | 8/9/2010 | | PASS |
John Menard
|
|
|
8/9/2010 16:27:27 JCM - activity updated through activity BLDA022 from case BLD10-01261.
|
Routing - PLAN CHECK | 8/5/2010 | | 8/9/2010 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/9/2010 | | DONE |
John Menard
|
|
|
|
Routing - FIRE | 8/4/2010 | | 8/5/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 7/27/2010 | | 8/4/2010 | | |
John Menard
|
|
|
|
Routing - FIRE | 7/21/2010 | 7/21/2010 | 7/27/2010 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 7/27/2010 | | FAIL |
|
|
|
Failed Public Works, Structural, Fire
|
Route to Impact Fee Review | 7/21/2010 | 7/26/2010 | 7/23/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan Reviewer's activity | | | 7/21/2010 | | PASS |
John Menard
|
|
|
Reviewed and approved final two outstanding structural items. JCM
|
Routing - PLAN CHECK | 6/21/2010 | | 7/21/2010 | | PASS |
John Menard
|
|
|
Passsed with attached comments for field verification. JCM
|
Plan resubmittals received | | | 7/20/2010 | | DONE |
|
|
|
received 1 letter of transmittal, 1 review comments , and 3 copies of sheet TS7.1 taken to John M.
|
Routing Off Site - STRUCTURAL | 7/8/2010 | | 7/19/2010 | | FAIL |
John Menard
|
|
|
Received comment list from consulting strucltural engineer requesting additional revisions. JCM
|
Plan resubmittals requested | | | 7/19/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the second structural comment letter from the consulting structural engineer. JCM
|
Plan resubmittals received | | | 7/7/2010 | | |
John Menard
|
|
|
rec'd response letter and two copies of sheets TS0.1; TS0.3; TS1.1; TS5.1; TS7.1 - inserted and taken to John M
|
Routing - PUBLIC WORKS | 6/25/2010 | | 6/25/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Solid Waste | | | 6/24/2010 | | PASS |
Peter J. McCullough
|
|
|
|
Routing PW Drainage | 6/22/2010 | | 6/24/2010 | | PASS |
Brian Murphy
|
|
|
|
Plan resubmittals requested | | | 6/22/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural review requesting revisions. JCM
|
Routing - Design Review | 6/21/2010 | | 6/21/2010 | | PASS |
Andrea Tuning
|
|
|
DRH10-00043 A. Tuning
|
Routing - PLANNING | 6/18/2010 | | 6/21/2010 | | PASS |
Joshua Johnson
|
|
|
CUP10-00002
|
Routing Off Site - STRUCTURAL | 6/4/2010 | | 6/21/2010 | | FAIL |
John Menard
|
|
|
|
Routing - PLUMBING | 6/15/2010 | | 6/18/2010 | | PASS |
Bill VanDegrift
|
|
|
verify water purveyor will allow service to both buildings being tie together.
|
Routing - Erosion and Sediment | 6/14/2010 | | 6/15/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC10-00463
|
Routing - PUBLIC WORKS | 6/8/2010 | | 6/14/2010 | | FAIL |
Connie Baumgartner
|
|
|
|
Routing PW Environmental | | | 6/14/2010 | | PASS |
Walt Baumgartner
|
|
|
reviewed, shop and truck park bay trench drains route to 1500 gallon flamm interceptor. OK
|
Routing PW Sewer Rating | 6/14/2010 | | 6/14/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing PW Drainage | | | 6/11/2010 | | FAIL |
Brian Murphy
|
|
|
NEEDS GEOTECH AND REVSIONS BRIAN MURPHY ###-####
|
Routing PW Sewer Design | 6/9/2010 | | 6/11/2010 | | PASS |
Jon R. Gunnerson
|
|
|
Sewer Tap permit required under BLD10-01256.
|
Routing - Addressing | 6/9/2010 | | 6/9/2010 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 6/4/2010 | | 6/8/2010 | | PASS |
Todd Tucker
|
|
|
|
Application received | | 6/4/2010 | 6/4/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Pending Assignment by JCM | 6/4/2010 | | 6/4/2010 | | BLDA |
John Menard
|
|
|
6/4/2010 14:48:29 JCM - activity updated through activity BLDA166 from case BLD10-01261.
|
Plans ACCEPTED BY PLAN TECH | | | 6/4/2010 | | DONE |
|
|
|
|