BLD-Final | 7/26/2010 | 7/27/2010 | 7/27/2010 | A | PASS |
Tom Arcoraci
|
|
|
Hasmukh Phone #: ###-####
|
Permanent Occupancy UNPAID FEE | | | 7/27/2010 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/26/2010 | 7/26/2010 | 7/26/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 7/20/2010 | 7/21/2010 | 7/21/2010 | P | NR |
Tom Arcoraci
|
|
|
Hasmukh Phone #: ###-#### needs fire sign off
|
FIRE-Final Inspection | 7/20/2010 | 7/21/2010 | 7/21/2010 | A | FAIL |
Troy Cobbley
|
|
|
Remove the thumbturn lock from the main exit, provide automatic flush bolts at the main exit and remove the manual flush bolts, provide exit signs and emergency lights as per the approved plans, lower the fire extinguisher to less than 5', provide an additional fire extinguisher in the retail area or relocate the existing fire extinguishers so that travel does not exceed 75', repair the emergency light in the basement, the secondary exit door is required to swing out, have compliant hardware and have the dead bolts removed. I also noted that a motorized conveyor is installed on the stairs to the basement storage area and the required 36" minimum egress is gone.
|
Plan assigned to (TLW) | 6/30/2010 | | 7/20/2010 | | PASS |
Tim L. Woodard
|
|
|
7/20/2010 11:11:35 TLW - activity updated through activity BLDA022 from case BLD10-01505.
|
Routing - PLAN CHECK | 7/20/2010 | | 7/20/2010 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/20/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 7/20/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 7/20/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/20/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/20/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan Reviewer's activity | | | 7/19/2010 | | DONE |
Tim L. Woodard
|
|
|
Conducted site visit. No Exit signs rear door had bar across it. No emergency lighting.
|
Telephone call | | | 7/9/2010 | | DONE |
Tim L. Woodard
|
|
|
Called applicant. We talked about why a mechanical engineer and architect are required to submit TI plans to install a class I hood. Applicant doesn't want to install hood so is going to have Dixie Fellows conduct site visit to see that he is just heating up food. TLW
|
Routing - PLAN CHECK | 7/7/2010 | | 7/8/2010 | | FAIL |
Tim L. Woodard
|
|
|
needs TI in order to install class I hood system. TLW
|
1st review completed | | | 7/8/2010 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLUMBING | 7/7/2010 | | 7/7/2010 | | PASS |
Bill VanDegrift
|
|
|
provide stops at hand sink. waste service sinkinto new floor sink. additional cross connection protection may be required, service line. any water supplied equipment, etc.
|
Routing PW Sewer Rating | 7/6/2010 | | 7/6/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/30/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/30/2010 | | 6/30/2010 | | PEND |
Tim L. Woodard
|
|
|
Sent to public works review first.
|
Routing - PUBLIC WORKS | 6/30/2010 | | 6/30/2010 | | PASS |
Tim L. Woodard
|
|
|
Connie approved plan based on it being in Bench District. Sheet attached to documents. TLW
|
Routing - Addressing | 6/30/2010 | | 6/30/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 6/30/2010 | | | |
|
|
|
|