BLD-Final | 9/22/2010 | 9/24/2010 | 9/24/2010 | A | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 9/24/2010 | 9/24/2010 | 9/24/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/21/2010 | 9/22/2010 | 9/21/2010 | A | CANC |
Mike Jordan
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 9/2/2010 | 9/3/2010 | 9/3/2010 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####
|
Routing Walk-In (BLD) | 9/3/2010 | 9/3/2010 | 9/3/2010 | A | DONE |
Alexandra L. DeYoung
|
|
|
9/3/2010 11:41:05 ALR - activity updated through activity BLDI252 from case BLD10-01516.
|
Routing Walk-In (BLD) | 9/3/2010 | 9/3/2010 | 9/3/2010 | A | PASS |
Perry Paine
|
|
|
|
BLD-Concrete | 8/16/2010 | 8/17/2010 | 8/17/2010 | P | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####. INterior column pad footings. ok. Wiil be placed with interior slab on grade.
|
BLD-Footing | 8/11/2010 | 8/12/2010 | 8/12/2010 | A | PASS |
Mike Jordan
|
|
|
Mike Phone #: ###-####South footing and stemwall.
|
BLD-Concrete | 8/9/2010 | 8/10/2010 | 8/10/2010 | A | PASS |
Mike Jordan
|
|
|
Michael Phone #: ###-####. Perimeter stemwalls ok.
|
BLD-Footing | 8/4/2010 | 8/6/2010 | 8/6/2010 | A | PART |
Mike Jordan
|
|
|
CJ Pierce- around 11:30-12 if possible please Phone #: ###-####. Permiter footing ok, work inprogress on installing reinforcment at column pad footings.
|
OVERRIDE | | | 7/2/2010 | | |
|
|
|
|
Routing Walk-In (BLD) | 7/2/2010 | 7/2/2010 | 7/2/2010 | A | DONE |
Perry Paine
|
|
|
7/2/2010 10:15:45 PEP - activity updated through activity BLDA022 from case BLD10-01516.
|
Plan assigned to (PEP) | 7/1/2010 | 7/1/2010 | 7/2/2010 | | PASS |
Perry Paine
|
|
|
7/2/2010 10:15:45 PEP - activity updated through activity BLDA022 from case BLD10-01516.
|
Case Summary (BLD) | | | 7/2/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/2/2010 | | |
|
|
|
|
1st review completed | | | 7/2/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/2/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/2/2010 | | DONE |
|
|
|
|
Application received | | 7/1/2010 | 7/1/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Routing Walk-In (Zoning) | 7/1/2010 | 7/1/2010 | 7/1/2010 | P | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 7/1/2010 | 7/1/2010 | 7/1/2010 | P | FAIL |
Perry Paine
|
|
|
need engineering for long wall
|
1st review completed | | | 7/1/2010 | | FAIL |
|
|
|
|