Permanent Occupancy | | | 8/24/2010 | | |
|
|
|
|
BLD-Final | 8/18/2010 | 8/18/2010 | 8/18/2010 | P | PASS |
Jim Sly
|
|
|
Nancy Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 8/18/2010 | 8/18/2010 | 8/18/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 8/11/2010 | 8/11/2010 | 8/11/2010 | P | DONE |
Troy Cobbley
|
|
|
I met the door hardware contractor on site to verify hardware on the main exit.
|
BLD-Final | 7/20/2010 | 7/21/2010 | 7/21/2010 | A | NR |
Mike Jordan
|
|
|
NANCY Phone #: ###-####. Life/safety failed.
|
FIRE-Final Inspection | 7/20/2010 | 7/20/2010 | 7/20/2010 | P | FAIL |
Troy Cobbley
|
|
|
Repair or remove both of the exit signs, remove the thumbturn lock on the east exit door, provide approved single action hardware on the east exit door, provide automatic flush bolts and sticker on one pair of the north exit doors. The other pair shall have no locking device, including manual flush bolts. Single action hardware for both leaves of doors would be ok.
|
Issue PAID IN FULL permit | | | 7/20/2010 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 7/19/2010 | | 7/19/2010 | | PASS |
Tim L. Woodard
|
|
|
7/19/2010 13:23:33 TLW - activity updated through activity BLDA022 from case BLD10-01551.
|
Routing - PLAN CHECK | 7/19/2010 | | 7/19/2010 | | PASS |
Tim L. Woodard
|
|
|
Approved with notes and redlines on plans. TLW
|
Intake Approval | | | 7/19/2010 | | PASS |
Tim L. Woodard
|
|
|
applicant emailed new floor plan with demensions. TLW
|
1st review completed | | | 7/19/2010 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Case Summary (BLD) | | | 7/19/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 7/19/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/19/2010 | | |
|
|
|
|
Telephone call | | | 7/19/2010 | | DONE |
|
|
|
Left message for Nancy Brannen that permit is ready on 7-419-10 @ 3:50pm BAS
|
Application received | | 7/6/2010 | 7/6/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/6/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 7/6/2010 | | FAIL |
Tim L. Woodard
|
|
|
No demensions on floor plan. Told applicant to email me a demensioned floor plan.
|
First Notice | | 9/3/2010 | | | |
|
|
|
|