Permanent Occupancy | | | 7/29/2010 | | DONE |
|
|
|
|
BLD-Final | 7/28/2010 | 7/28/2010 | 7/28/2010 | P | PASS |
Tom Arcoraci
|
|
|
kraig Phone #: ###-####
|
FIRE-Final Inspection | 7/27/2010 | 7/28/2010 | 7/28/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 7/21/2010 | 7/22/2010 | 7/22/2010 | A | NR |
Mike Jordan
|
|
|
after 9am // Kraig Phone #: ###-####. Life/safety failed.
|
FIRE-Final Inspection | 7/21/2010 | 7/21/2010 | 7/21/2010 | P | FAIL |
Troy Cobbley
|
|
|
Provide sticker at the main exit, provide additional fire extinguisher near the rear of the warehouse, the sprinkler heads are being obstructed by the insulation at the roof deck. I also noted that part of the mezzanine is missing a railing.
|
Issue PAID IN FULL permit | | | 7/21/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (TLW) | 7/9/2010 | | 7/19/2010 | | PASS |
Tim L. Woodard
|
|
|
7/19/2010 14:29:34 TLW - activity updated through activity BLDA022 from case BLD10-01572.
|
Routing - PLAN CHECK | 7/9/2010 | | 7/19/2010 | | PASS |
Tim L. Woodard
|
|
|
Application approved with comments. TLW
|
1st review completed | | | 7/19/2010 | | DONE |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/19/2010 | | DONE |
Tim L. Woodard
|
|
|
|
Print Occupancy Form | | | 7/19/2010 | | DONE |
|
|
|
|
Telephone call | | | 7/19/2010 | | DONE |
|
|
|
left message w sophia for kraig at ###-#### - permit ready
|
Permit Ready to Issue | | | 7/19/2010 | | DONE |
|
|
|
|
Application received | | 7/9/2010 | | | |
|
|
|
|