Telephone call | | | 3/3/2011 | | DONE |
Tisha Gallop
|
|
|
Audited final value to take out value of pool cover ($2,800) that was installed after project was completed. Spoke with Laurie/Pristine Pools.
|
First Notice | 10/29/2010 | 10/29/2010 | 3/2/2011 | | DONE |
Dave Hannah
|
|
|
This permit finaled on the web by Laurie Hoelscher
|
BLD-Final | 10/28/2010 | 10/29/2010 | 10/29/2010 | A | PASS |
Dave Hannah
|
|
|
lori Phone #: ###-####
|
DOC - Permit Finaled | 10/29/2010 | 10/29/2010 | 10/29/2010 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 10/28/2010 | 10/28/2010 | 10/28/2010 | P | PASS |
Forrest France
|
|
|
Life safety finaled.
|
FIRE-Final Inspection | 10/26/2010 | 10/27/2010 | 10/28/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety approved pending adjustment at the mag lock delay.
|
BLD-Final | 10/22/2010 | 10/26/2010 | 10/26/2010 | P | CANC |
Dave Hannah
|
|
|
lori Phone #: ###-#### - please call for access Inspection cancelled from web by: Laurie Hoelscher
|
FIRE-Final Inspection | 10/22/2010 | 10/25/2010 | 10/26/2010 | P | FAIL |
Forrest France
|
|
|
Delay at the mag locks must be set for a min. of 30 seconds per code requirements.
|
BLD-Final | 10/5/2010 | 10/6/2010 | 10/6/2010 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by Laurie Hoelscher need p$z sign off as well as fire and mech permit and sign off. contractor to resch. upon completing insp.
|
BLD-Conference | 8/4/2010 | 8/5/2010 | 8/6/2010 | P | PASS |
Dave Hannah
|
|
|
Pool Rebar inspection Phone #: ###-#### >> Inspection requested via web by Laurie Hoelscher
|
BLD-Other | 8/4/2010 | 8/4/2010 | 8/4/2010 | P | CANC |
Dave Hannah
|
|
|
Rebar on Pool inspection Phone #: ###-#### >> Inspection requested via web by Laurie Hoelscher Inspection cancelled from web by: Laurie Hoelscher
|
Inspection Record Card- Bld | | | 7/22/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/22/2010 | | DONE |
|
|
|
|
Telephone call | | | 7/22/2010 | | DONE |
|
|
|
Called Jamie and told her that permit is ready & fees due on 7-22-10 @ 9:15am
|
Issue PAID IN FULL permit | | | 7/22/2010 | | DONE |
|
|
|
|
Routing - FIRE | 7/20/2010 | | 7/21/2010 | | PASS |
Scott Arellano
|
|
|
Hazardous materials are below MAQ's. No seperate fire review comments attached.
|
Plan assigned to (SRZ) | 7/16/2010 | | 7/21/2010 | | PASS |
Sam Zahorka
|
|
|
7/21/2010 16:23:05 SRZ - activity updated through activity BLDA022 from case BLD10-01603.
|
1st review completed | | | 7/21/2010 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/21/2010 | | 7/21/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 7/16/2010 | | 7/20/2010 | | PASS |
Dan Stuart
|
|
|
|
Case Summary (BLD) | | | 7/20/2010 | | DONE |
Sam Zahorka
|
|
|
|
Meeting | | | 7/19/2010 | | DONE |
Sam Zahorka
|
|
|
Attended meeting with John on the status of this permit. He was unaware the permit was started only 3 working days ago. He also stated plans were in acurate and the design has changed. I asked for updated drawings prior to starting my 1st review. He said he would have the updated plans submitted today. Waiting for updated plans with the changes he spoke about. SRZ
|
Plan resubmittals received | | | 7/19/2010 | | DONE |
Tisha Gallop
|
|
|
received list of chemicals, MSDS sheets and two copies of plan sheets AQ1.2 (11"x17"); taken to Sam Z.
|
Plan assigned to (DRS) | 7/14/2010 | 7/14/2010 | 7/16/2010 | | CANC |
Dan Stuart
|
|
|
Plan reassigned to Sam Zahorka.
|
Routing - PLUMBING | 7/16/2010 | | 7/16/2010 | | PASS |
Bill VanDegrift
|
|
|
cartridge filters no plumbing
|
Routing - PLANNING | 7/16/2010 | | 7/16/2010 | | PASS |
Sarah Schafer
|
|
|
DRH10-00004 Sarah Schafer
|
Routing - PUBLIC WORKS | 7/14/2010 | | 7/16/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Erosion and Sediment | 7/16/2010 | | 7/16/2010 | | PASS |
Steven Webb
|
|
|
ESC plan for permit number ESC10-00025 is applicable for the pool as well as the community building. Approved according to the ESC plan and ESC permit conditions. John Cloninger with Brighton Homes is the Responsible Person.
|
Routing PW Sewer Rating | 7/15/2010 | | 7/15/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 7/14/2010 | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/14/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 7/14/2010 | | PASS |
Tisha Gallop
|
|
|
|
Routing - PLANNING Land Div | 7/14/2010 | | 7/14/2010 | | PASS |
Dave Abo
|
|
|
Lot 1, Block 1 of River Heights Subd. #1
|
Zoning Approval | 10/25/2010 | 10/25/2010 | | | |
Sarah Schafer
|
|
|
This sign off is for the pool only. Club house, landscape and remainder of project need a DR modification before sign off can be obtained and occupancy granted.