BLD-Final | 10/14/2010 | 10/15/2010 | 10/15/2010 | A | PASS |
Mike Jordan
|
|
|
todd Phone #: ###-####
|
DOC - Permit Finaled | 10/15/2010 | 10/15/2010 | 10/15/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy was issued. HAndrail was repaired.
|
BLD-Final | 10/13/2010 | 10/14/2010 | 10/14/2010 | P | NR |
Mike Jordan
|
|
|
final electrical inspection to be at 1PM. Garage code is 2511 Phone #: ###-#### >> Inspection requested via web by Todd Blackwell. Elec. final failed, needs to raise handrail on lower flight of stairs.
|
BLD-Final | 10/12/2010 | 10/14/2010 | 10/13/2010 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Todd Blackwell Inspection cancelled from web by: Todd Blackwell
|
BLD-Final | 10/12/2010 | 10/13/2010 | 10/12/2010 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Todd Blackwell Inspection cancelled from web by: Todd Blackwell
|
BLD-Energy code compliance | 9/13/2010 | 9/13/2010 | 9/13/2010 | P | PASS |
Mike Jordan
|
|
|
key is in back light porch light box Phone #: ###-#### >> Inspection requested via web by Todd Blackwell
|
BLD-Framing/Rough-in | 9/13/2010 | 9/13/2010 | 9/13/2010 | P | PASS |
Mike Jordan
|
|
|
key is in back light porch light box Phone #: ###-#### >> Inspection requested via web by Todd Blackwell
|
BLD-Energy code compliance | 9/9/2010 | 9/13/2010 | 9/13/2010 | A | FAIL |
Mike Jordan
|
|
|
Todd Phone #: ###-####. No access, all doors were locked, no inspection done.
|
BLD-Framing/Rough-in | 9/9/2010 | 9/10/2010 | 9/10/2010 | P | PART |
Mike Jordan
|
|
|
Todd Phone #: ###-####. Complete lateral brcing on T10 and T11 trusses. Ok to insulate.
|
BLD-Foundation | 8/19/2010 | 8/20/2010 | 8/20/2010 | A | PART |
Mike Jordan
|
|
|
Todd Phone #: ###-####. Architect to fax paperwork regarding deletion of some reinforcement in footing and stemwall.
|
BLD-Footing | 8/18/2010 | 8/19/2010 | 8/19/2010 | A | PART |
Mike Jordan
|
|
|
Pat Phone #: ###-####. work in progress. Spoke to contractor, need paperwork regardingb the deletion of reinforcement.
|
Issue PAID IN FULL permit | | | 8/18/2010 | | DONE |
|
|
|
|
OVERRIDE | | | 8/17/2010 | | |
|
|
|
|
Plan assigned to (CDM) | 8/12/2010 | 8/12/2010 | 8/17/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/17/2010 | | 8/17/2010 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 8/16/2010 | | 8/17/2010 | | PASS |
David Moser
|
|
|
Approved as redlined, driveway shall be 33 foot wide max in front yard setback.
|
Inspection Record Card- Bld | | | 8/17/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2010 | | |
|
|
|
|
Permit Ready to Issue | | | 8/17/2010 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | | | 8/16/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 8/12/2010 | | 8/13/2010 | | PASS |
April Wing
|
|
|
|
Plan resubmittals received | | | 8/12/2010 | | DONE |
Tisha Gallop
|
|
|
Moved same house design to different lot/block. Received two copies of full size site plan, reduces size site plan, revised building and esc applicaitons, new reschecks; rerouted to addressing, pw, planning and plan check.
|
OVERRIDE | | | 7/27/2010 | | |
|
|
|
|
Route to Impact Fee Review | 7/21/2010 | 7/26/2010 | 7/27/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Plan assigned to (CDM) | 7/22/2010 | 7/22/2010 | 7/27/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 7/26/2010 | | 7/27/2010 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/27/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/27/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/27/2010 | | DONE |
|
|
|
|
Telephone call | | | 7/27/2010 | | DONE |
|
|
|
t/c w todd at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 7/27/2010 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 7/22/2010 | | 7/26/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 7/26/2010 | | 7/26/2010 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 7/22/2010 | | 7/22/2010 | | PASS |
April Wing
|
|
|
|
Intake Approval | | | 7/22/2010 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2010 | | DONE |
|
|
|
|
Application received | | 7/21/2010 | 7/21/2010 | | DONE |
Darla L Downs
|
|
|
|