BLD-Final | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hour before. Thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
DOC - Permit Finaled | 1/21/2011 | 1/21/2011 | 1/21/2011 | P | PASS |
Mike Jordan
|
|
|
Residential certificate of occupancy was issued.
|
BLD-Aging Inspection | 11/29/2010 | 11/29/2010 | 11/29/2010 | | PASS |
Mike Jordan
|
|
|
work in progress.
|
Additional plans submitted | | | 10/4/2010 | | DONE |
Tisha Gallop
|
|
|
received Alternate Method request; taken to Jason Blais.
|
BLD-Wall cover | 9/29/2010 | 9/29/2010 | 9/29/2010 | P | PASS |
Mike Jordan
|
|
|
drywall nailing Phone #: ###-#### >> Inspection requested via web by James Larkin. Nailing for 1hr. wall at propertyline.
|
BLD-Energy code compliance | 9/27/2010 | 9/27/2010 | 9/27/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 9/27/2010 | 9/27/2010 | 9/27/2010 | A | NR |
Mike Jordan
|
|
|
please call 1/2 hour before. Thanks jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Energy code compliance | 9/23/2010 | 9/23/2010 | 9/23/2010 | P | NR |
Mike Jordan
|
|
|
please call 1 hour before. thanks Jim Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Framing/Rough-in | 9/22/2010 | 9/22/2010 | 9/22/2010 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. All framing issues have been resolved. ok to insulate.
|
BLD-Framing/Rough-in | 9/21/2010 | 9/21/2010 | 9/21/2010 | P | NR |
Mike Jordan
|
|
|
Please call 1/2n hour before Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Framing/Rough-in | 9/20/2010 | 9/21/2010 | 9/21/2010 | A | CANC |
Mike Jordan
|
|
|
please call 1/2 houir before Phone #: ###-#### >> Inspection requested via web by James Larkin Inspection cancelled from web by: James Larkin
|
BLD-Framing/Rough-in | 9/16/2010 | 9/17/2010 | 9/17/2010 | A | FAIL |
Mike Jordan
|
|
|
Jim Phone #: ###-####. See posted correction notice.
|
BLD-Footing | 8/24/2010 | 8/24/2010 | 8/24/2010 | P | CANC |
Mike Jordan
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 8/24/2010 | 8/24/2010 | 8/24/2010 | A | PASS |
Mike Jordan
|
|
|
footings in slab Phone #: ###-#### >> Inspection requested via web by James Larkin. Interior footings ok.
|
BLD-Energy code compliance | 8/19/2010 | 8/19/2010 | 8/19/2010 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Larkin
|
BLD-Footing | 8/18/2010 | 8/18/2010 | 8/18/2010 | P | CANC |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Foundation | 8/18/2010 | 8/18/2010 | 8/18/2010 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####
|
BLD-Footing | 8/17/2010 | 8/17/2010 | 8/17/2010 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
OVERRIDE | | | 8/17/2010 | | |
|
|
|
|
Plan assigned to (CDM) | 8/3/2010 | 8/3/2010 | 8/17/2010 | | DONE |
Carl D Madsen
|
|
|
|
1st review completed | | | 8/17/2010 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/17/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/17/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/17/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/17/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/17/2010 | | |
|
|
|
|
Routing - PLAN CHECK | 8/4/2010 | | 8/17/2010 | | PASS |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 8/3/2010 | 8/6/2010 | 8/6/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 8/3/2010 | | 8/4/2010 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 8/4/2010 | | 8/4/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - PLANNING | 8/4/2010 | | 8/4/2010 | | PASS |
Colleen T Carroll
|
|
|
Construction must comply with CUP10-00036
|
Application received | | 8/3/2010 | 8/3/2010 | | DONE |
|
|
|
|
Intake Approval | | | 8/3/2010 | | PASS |
Alexandra L. DeYoung
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/3/2010 | | DONE |
|
|
|
|