Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD10-01853
StatusFinaled
Name UNION CORNER CONSTRUCTION
Site Address 501 W FRONT ST
Project NameConcordia University Law Schoo
Customer Number 
ePlanReviewNo
Description
Concordia University - To construct a 32,565 square foot, three story addition on the west side of an existing 17,565 square foot, two story building. The interior of first floor of the existing building will be entirely demolished, with the exception of the existing accessible restrooms, shower room, mechanical, electrical and copy/fax rooms. The remaining portion of the existing first floor will be remodeled for 6 foot library book stacks, reading areas, small offices, study rooms and library circulation desk and work areas. The existing mezzanine will be expanded to create a 5,310 square foot second floor that will be used primarily for 6 foot book stacks. This second floor area will also contain a small reading area, small conference room, IT Tech area and three small shared study rooms. The first floor of the new addition will contain two large classrooms, a large waiting area, accessible restrooms, two small study rooms, and four storage areas for various types of storage. The second floor of the new addition will contain four classrooms of varing sizes, a student lounge, a faculty lounge, two accessible restrooms, a chapel, four small conference rooms, a mechanical room and four storage rooms. The third floor of the new addition contains primarily administrative and faculty offices, with one classroom, two large accessible restrooms and unisex accessible restroom. This floor also contains a mechanical room and janitor closet. The foundation was constructed under building permit BLD10-01393. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  3/8/2012 DONE
Print Statement  3/2/2012 DONE
Third Notice 3/1/20122/13/2012 DONE
Second Notice 11/17/201111/21/2011 DONE
DetailsChristina Prado
Telephone call  11/14/2011 DONE
t/c w rick porter - still getting change orders in
First Notice 11/4/201111/7/2011 DONE
Permanent Occupancy  10/25/2011 DONE
DetailsBarbara Stitt
BLD-Final10/18/201110/18/201110/18/2011PPASS
DetailsDave Hannah
rick - lowered a sink Phone #: ###-#### ok for perm occ
FIRE-Final Inspection10/3/201110/4/201110/4/2011APASS
DetailsForrest France
Adjustments at two exit signs and one EM light repaired while on site. Remainder of fire life safety inspection passed.
BLD-Final10/3/201110/4/201110/4/2011APART
DetailsDave Hannah
RICK Phone #: ###-#### ok for temp occ ok for perm occ after they lower the sink on seond floor
Second Notice 9/18/20119/22/2011 DONE
DetailsChristina Prado
BLD-Final9/9/20119/12/20119/12/2011ANR
DetailsDave Hannah
ron hill - 10:00 Phone #: ###-####
FIRE-Final Inspection9/9/20119/12/20119/12/2011APART
DetailsForrest France
ron hill - 10:00 Phone #: ###-####
BLD-Final8/30/20118/30/20119/12/2011PCANC
DetailsDave Hannah
rick Phone #: ###-####
BLD-Final8/26/20118/26/20119/12/2011PCANC
DetailsDave Hannah
rick Phone #: ###-####
CHANGE STATUS TO (ISS)  9/9/2011 DONE
DetailsRita DeYoung
Permit not final per Dave H
DOC - Permit Finaled9/7/20119/7/20119/7/2011PPASS
DetailsDave Hannah
FIRE-Conference9/6/20119/6/20119/6/2011ADONE
DetailsForrest France
FIRE-Final Inspection8/18/20118/19/20118/19/2011ANR
DetailsForrest France
Final pending project related fire alarm and sprinkler permit finals. Also noted missing exit signs at the 2nd and 3rd floors, need to add discharge lighting at the south exit, discussed project schedule.
PubWorks Occupancy Approval8/19/20118/19/20118/19/2011 DONE
DetailsTiffany Lowery
BLD-Final8/11/20118/12/20118/12/2011ANR
DetailsDave Hannah
rick Phone #: ###-#### walked project with rick he will keep working to get everything finished
Zoning Approval8/3/20118/3/20118/3/2011 DONE
DetailsAndrea Tuning
BLD-Other7/21/20117/22/20117/22/2011PPASS
DetailsDave Hannah
partial ceiling insp (stairwells)//Steve Phone #: ###-####
BLD-Other7/21/20117/21/20117/22/2011PPASS
DetailsDave Hannah
ceiling insp//Rick Phone #: ###-#### ok to cover third floor
BLD-Other7/14/20117/15/20117/15/2011PPART
DetailsDave Hannah
celing inspection//Rick ###-#### Third floor offices ok to cover
BLD-Other7/1/20117/5/20117/5/2011APASS
DetailsTom Arcoraci
Ceiling Grid---Steve Phone #: ###-#### 2nd floor patch stair tower grid ok
BLD-Other6/6/20116/6/20116/7/2011PPART
DetailsDave Hannah
Steve Phone #: ###-#### ok to cover ceiling in the two lecture rooms first floor
FIRE-Sprinkler Rough-in5/9/20115/9/20115/9/2011APART
DetailsForrest France
Overhead fire sprinkler work approved for ceiling cover at the 2nd floor computer room.
BLD-Framing/Rough-in4/12/20114/13/20114/14/2011APASS
DetailsDave Hannah
2nd floor-Rick Phone #: ###-#### ok to cover second and thrid floors walls but plumbing to firestop floors
FIRE-Conference4/13/20114/13/20114/13/2011PDONE
DetailsForrest France
Regarding new SW head locations at the covered entry east side.
BLD-Framing/Rough-in3/31/20113/31/20114/1/2011PPART
DetailsDave Hannah
Steve Phone #: ###-#### ok to cover first floor
BLD-Other3/23/20113/24/20113/31/2011APART
DetailsDave Hannah
shaft insp//Rick Phone #: ###-####
FIRE-Sprinkler Rough-in3/30/20113/30/20113/30/2011APART
DetailsForrest France
Supply line flush okayed
BLD-Framing/Rough-in3/9/20113/10/20113/11/2011APART
DetailsDave Hannah
exterior insulation and framing insp--Rick Phone #: ###-#### ok to cover ext and int on ext bldg
FIRE-Sprinkler Rough-in3/7/20113/7/20113/8/2011APART
DetailsForrest France
Beam clamps and retainers at the 2nd floor okayed.
BLD-Framing/Rough-in2/23/20112/24/20112/24/2011APART
DetailsDave Hannah
exterior framing and sheathing insp South side//Rick Phone #: ###-#### ok to cover south ext
BLD-Framing/Rough-in2/17/20112/18/20112/18/2011APART
DetailsDave Hannah
rick Phone #: ###-#### ok to cover east ext end of bldg
BLD-Framing/Rough-in2/15/20112/16/20112/16/2011APART
DetailsDave Hannah
Rick Phone #: ###-#### east ext wall ok to cover ext
FIRE-Sprinkler Rough-in2/14/20112/14/20112/14/2011PPART
DetailsForrest France
Inspection for beam clamps/retainers and seismic brace attatchments at the 3rd floor okayed pre fireproof coating application.
BLD-Concrete1/21/20111/24/20111/24/2011APART
DetailsDave Hannah
rick Phone #: ###-#### mti on site doing concrete and slab reinfocement for the third floor pour
FIRE-Sprinkler Rough-in1/12/20111/12/20111/12/2011APART
DetailsForrest France
Beam clamps and seismic straps at overhead sprinkler main line hangers on the first floor okayed.
BLD-Concrete1/4/20111/5/20111/5/2011PPART
DetailsDave Hannah
Reinforcing inspection please-Rick Phone #: ###-#### second floor deck ok to pour
Print Occupancy Form  11/23/2010 DONE
DetailsBarbara Stitt
Issue PAID IN FULL permit  11/22/2010  
Plan assigned to (JCM)8/4/20108/4/201011/19/2010 PASS
DetailsJohn Menard
Routing - PLAN CHECK11/16/2010 11/19/2010 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  11/19/2010 DONE
DetailsJohn Menard
Print Occupancy Form  11/19/2010 DONE
Telephone call  11/19/2010 DONE
left vm for jeff humphreys - permit ready and fees given - also need ACHD receipt
Permit Ready to Issue  11/19/2010 DONE
Details
Plan resubmittals received  11/17/2010  
11-17-10 received 2 response/ hvac load analysis and 2 copies of sheets A2.1,A5.1,A6.1,A6.2,A7.1,A7.2,A7.3,P0.2,P2.1,P2.3 inserted by Rick from union corner construction.
Routing - PLUMBING11/10/2010 11/16/2010 PASS
DetailsBill VanDegrift
if the state elevator inspector requires a pump in the elevator pit a resubmited plan will be required.
Routing - PLAN CHECK10/13/2010 11/10/2010  
DetailsJohn Menard
Routing PW Environmental11/10/2010 11/10/2010 PASS
DetailsWalt Baumgartner
Reviewed resubmittal plumbing sheets. Elevator drainage eliminated. OK
Routing - PUBLIC WORKS11/10/2010 11/10/2010 PASS
DetailsBeverly Mountain
Plan resubmittals requested  11/9/2010 DONE
DetailsJohn Menard
E-mailed the architect a letter requesting additional plan revisions. JCM
Plan resubmittals received  11/3/2010  
DetailsBarbara Stitt
Received 2 copies of plan review response letter addressing #1 & 2, #8, #13, 2 copies of sheets T1.1, A 1.1,A 2.1,A 2.2, A2.3, A5.1, A6.1, A6.2, A6.3, A7.2, A7.3, A9.1, S2.2, S2.3, S2.4, M0.2, E0.3, E2.1, E2.2, E3.1, E3.2, E3.3, E5.2, T2.2, T2.3, P2.1, P2.1A, P2.2, P2.3 inserted into plans by ay architects office then returned to John Menards office
Routing - FIRE10/8/201010/8/201010/13/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
1st review completed  10/13/2010 FAIL
Failed Public Works,Structural, Plumbing, Planning, Plan Check
Route to Impact Fee Review10/8/201010/13/201010/8/2010 PASS
DetailsCindy M. Gould
Plan resubmittals requested  10/8/2010 DONE
DetailsJohn Menard
E-mailed the architect a copy of the plan review requesting revisions. JCM
Routing - PLAN CHECK8/19/2010 10/8/2010 FAIL
DetailsJohn Menard
John Menard
Routing Off Site - STRUCTURAL9/10/2010 9/15/2010 PASS
DetailsJohn Menard
Received letter from consulting engineer approving the structural revisions with one advisery note not requiring a response. JCM
Plan resubmittals received  9/10/2010  
DetailsJohn Menard
rec'd three copies of response, calcs, and sheets S1.1, S2.3; S5.2 - two sets inserted and one set send out to outside eng
Plan resubmittals requested  8/25/2010 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural review requesting revisions. JCM
Routing Off Site - STRUCTURAL8/5/2010 8/25/2010 FAIL
DetailsJohn Menard
Received comment list from the consulting structural engineer requesting revisions. JCM
Plan resubmittals received  8/20/2010 DONE
DetailsTisha Gallop
received three copies of plan sheets M0.2, E0.3; taken to John Menard
Routing - PLANNING8/17/2010 8/19/2010 PASS
DetailsJosh Wilson
OK with redlines Sheet A3.1 JGW
Routing - PLUMBING8/13/2010 8/17/2010 FAIL
DetailsBill VanDegrift
ceiling is a return air plenum, use of approved material is required. domestic hot water heat exchanger must be a double wall with leak detection. pass public works pretreatment review prior to plumbing plan approval. provide a sewer maintenance easement for adjacent property prior toplumbing plan approval.
Routing - Addressing8/12/2010 8/16/2010 PASS
DetailsApril Wing
Issue resolved.
Routing - Erosion and Sediment8/10/2010 8/13/2010 PASS
DetailsSteven Webb
reference ESC10-00496 (approved with the G/D phase)
Routing - PUBLIC WORKS8/5/2010 8/10/2010 FAIL
DetailsConnie Baumgartner
Failed by Walter Baumgartner ###-####
Routing PW Environmental8/9/2010 8/10/2010 FAIL
DetailsWalt Baumgartner
Require clarification on presence of floor drain in dumpster room w/ hose bib indicated. Elevator pit sump pump indicated with discharge to 2nd floor mop sink. Foundation dewatering, groundwater or subsurface drainage discharge to sewer must comply with 8-14-4.03 City Pretreatment Ordinance. If approved pretreatment device will be required. Call ###-####
Routing PW Sewer Rating8/9/2010 8/9/2010 PASS
DetailsConnie Baumgartner
Routing PW Solid Waste8/9/2010 8/9/2010 PASS
DetailsPeter J. McCullough
Application received 8/4/20108/5/2010 DONE
DetailsTisha Gallop
Routing - PLANNING Land Div8/5/2010 8/5/2010 PASS
DetailsDave Abo
Parcel "B" on ROS #5927.
Telephone call  8/5/2010 DONE
DetailsTisha Gallop
called Action Couriers for pick up
Plans ACCEPTED BY PLAN TECH  8/4/2010 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  8/4/2010 DONE
DetailsTisha Gallop
Intake Approval  8/4/2010 PASS
DetailsTisha Gallop