Third Notice | | 3/31/2011 | 3/31/2011 | | DONE |
|
|
|
faxed & called
|
Third Notice | | 3/17/2011 | 3/17/2011 | | DONE |
|
|
|
faxed
|
Third Notice | | 2/9/2011 | 3/3/2011 | | DONE |
|
|
|
faxed
|
Second Notice | | 1/30/2011 | 2/4/2011 | | DONE |
|
|
|
|
First Notice | | 1/14/2011 | 1/20/2011 | | DONE |
|
|
|
|
BLD-Final | 1/3/2011 | 1/4/2011 | 1/4/2011 | A | PASS |
Dave Hannah
|
|
|
To complete C of O--no need to go out to site
|
Permanent Occupancy | | | 1/4/2011 | | DONE |
Christina Prado
|
|
|
|
BLD-Aging Inspection | 12/30/2010 | 12/30/2010 | 1/3/2011 | | PASS |
Dave Hannah
|
|
|
|
Temporary Occupancy UNPAID FEE | | | 10/29/2010 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 10/28/2010 | 10/28/2010 | 10/28/2010 | P | PART |
Dave Hannah
|
|
|
Jerry Phone #: ###-#### ok for temp occ ok for perm occ after other trades go perm
|
BLD-Final | 10/26/2010 | 10/27/2010 | 10/27/2010 | P | NR |
Dave Hannah
|
|
|
Jerry Phone #: ###-#### needs other trades finaled first
|
FIRE-Final Inspection | 10/26/2010 | 10/27/2010 | 10/27/2010 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection completed satisfactory. PFE and ceiling tile to be installed as discussed prior to structural final.
|
FIRE-Conference | 10/19/2010 | 10/19/2010 | 10/20/2010 | P | DONE |
Forrest France
|
|
|
On site visit with contractor regarding existing fire alarm notification appliance locations. If the system is modified an FIR permit will be required-see review notes. However, existing coverage appears adequate.
|
FIRE-Sprinkler Rough-in | 10/19/2010 | 10/19/2010 | 10/19/2010 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work is approved for cover at the drop ceilings. Noted one upright head covered by foil- to be removed prior to final.
|
BLD-Conference | 10/18/2010 | 10/19/2010 | 10/19/2010 | A | PASS |
Dave Hannah
|
|
|
jerry Phone #: ###-####
|
BLD-Framing/Rough-in | 9/21/2010 | 9/21/2010 | 9/21/2010 | P | PASS |
Dave Hannah
|
|
|
Jerry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/7/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - FIRE | 9/1/2010 | 9/1/2010 | 9/3/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Plan assigned to (SRZ) | 8/19/2010 | | 9/3/2010 | | PASS |
Sam Zahorka
|
|
|
9/3/2010 14:27:59 SRZ - activity updated through activity BLDA022 from case BLD10-01899.
|
Case Summary (BLD) | | | 9/3/2010 | | DONE |
Sam Zahorka
|
|
|
|
Routing - PLAN CHECK | 9/3/2010 | | 9/3/2010 | | PASS |
Sam Zahorka
|
|
|
|
1st review completed | | | 9/3/2010 | | FAIL |
|
|
|
Failed Plan Check
|
Routing - PLAN CHECK | 9/3/2010 | | 9/3/2010 | | PASS |
Sam Zahorka
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/3/2010 | | DONE |
Sam Zahorka
|
|
|
|
Print Occupancy Form | | | 9/3/2010 | | DONE |
Barbara Stitt
|
|
|
|
Permit Ready to Issue | | | 9/3/2010 | | DONE |
Barbara Stitt
|
|
|
|
Telephone call | | | 9/3/2010 | | DONE |
Barbara Stitt
|
|
|
Called Stan Cole and told him that permit is ready and fees due on 9-3-10 @ 4:00pm
|
Route to Impact Fee Review | 9/1/2010 | 9/7/2010 | 9/2/2010 | | PASS |
Cindy M. Gould
|
|
|
Tenant improvement no impact fees
|
Plan resubmittals received | | | 9/2/2010 | | DONE |
Tisha Gallop
|
|
|
received transmittal and two copes of plan sheets A0.1, A2.1, A3.0, A3.1, A4.0; taken to Sam Zahorka
|
Routing - PLAN CHECK | 8/26/2010 | | 9/1/2010 | | FAIL |
Sam Zahorka
|
|
|
|
Routing - PLUMBING | 8/25/2010 | | 8/26/2010 | | PASS |
Bill VanDegrift
|
|
|
required floor drainage in the kitchen to floor sinks.
|
Routing - PUBLIC WORKS | 8/19/2010 | | 8/25/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing PW Environmental | 8/25/2010 | | 8/25/2010 | | PASS |
Walt Baumgartner
|
|
|
No grease abatement requied at this time (sandwich shop) per Terry Alber
|
Routing - Erosion and Sediment | 8/25/2010 | | 8/25/2010 | | PASS |
Steven Webb
|
|
|
ESC plan waiver is approved according to the ESC permit conditions. ESC10-00630
|
Routing - Addressing | 8/23/2010 | | 8/23/2010 | | PASS |
April Wing
|
|
|
|
Pending Assignment by JCB | 8/18/2010 | | 8/19/2010 | | DONE |
Jason Blais
|
|
|
|
Plan Reviewer's activity | | | 8/19/2010 | | DONE |
Jason Blais
|
|
|
Emailed architect Stan Cole letting him know to contact ACHD to provide them needed documents for evaluation of any impact fees. Written verification is required to be provided to our Permit Counter prior to the building permit being issued.
|
Intake Approval | | | 8/18/2010 | | PASS |
|
|
|
OK to submit for permit
|
Plans ACCEPTED BY PLAN TECH | | | 8/18/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/18/2010 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 8/11/2010 | 8/11/2010 | | DONE |
Alexandra L. DeYoung
|
|
|
|
Intake Approval | | | 8/11/2010 | | FAIL |
|
|
|
Missing some items.
|