Description
Boise City - City Hall West - Covered Motorcycle Parking - To construct (1) 1,188 sq.ft., Eight stall, free standing carport for motorcycle parking. The carport is a pre-engineered steel structure with supporting elements every 18ft on center. The carport complies with 406.1.2 of the 2006 IBC. All construction shall be per the approved plans and attached engineered drawings. DRH10-00031 **SRZ**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 11/20/201011/17/2010 DONE
First Notice10/21/201010/21/201011/10/2010 DONE
DetailsMike Jordan
BLD-Final10/21/201010/21/201010/21/2010PPASS
DetailsMike Jordan
DOC - Permit Finaled10/21/201010/21/201010/21/2010PPASS
DetailsMike Jordan
Letter of compliance was issued.
BLD-Final10/20/201010/21/201010/21/2010ACANC
DetailsMike Jordan
Dick Mckenna or cell ###-#### Phone #: ###-####. moved to pm.
FIRE-Final Inspection10/15/201010/18/201010/18/2010APASS
DetailsTroy Cobbley
life safety passed.
Zoning Approval10/18/201010/18/201010/18/2010 DONE
DetailsSarah Schafer
FIRE-Final Inspection10/13/201010/14/201010/14/2010AFAIL
DetailsTroy Cobbley
No city approved plans on site. No inspection performed.
BLD-Final10/13/201010/13/201010/13/2010PNR
DetailsJim Sly
dick - call for pass to get in Phone #: ###-#### or ###-####
Did not get required finals.......Per previous note.
BLD-Footing10/5/201010/6/201010/6/2010APASS
DetailsMike Jordan
Arthur Phone #: ###-####. Pier type footings for covered parking. Also noted to valley steel builders that life/safety, zoning and structural finals are all required.
Issue PAID IN FULL permit  8/31/2010 DONE
Route to Impact Fee Review8/25/20108/30/20108/30/2010 PASS
DetailsCindy M. Gould
Carport, no impact fees
Case Summary (BLD)  8/30/2010 DONE
DetailsSam Zahorka
Case Summary (BLD)  8/30/2010 DONE
DetailsSam Zahorka
PLANS/APPL TAKEN TO FRONT DESK  8/30/2010 DONE
DetailsSam Zahorka
Inspection Record Card- Bld  8/30/2010 DONE
Permit Ready to Issue  8/30/2010  
Telephone call  8/30/2010 DONE
8-30-10 called phillip permit ready and fee given
Plan assigned to (SRZ)8/12/2010 8/30/2010 PASS
DetailsSam Zahorka
8/30/2010 09:33:41 SRZ - activity updated through activity BLDA022 from case BLD10-01911.
Routing - FIRE8/25/20108/25/20108/27/2010 PASS
DetailsScott Arellano
Please, see attached review
Telephone call  8/27/2010 DONE
DetailsSam Zahorka
Received a telephone call from the applicant. Explained what I needed to complete my review (Dimensions on site plan from proposed carports to all existing builings, interior lot lines, and property lines). He stated he would verify in field and call me. I offered to red-line the plans for him. Plan are currently in Fire plan review.
Routing - PLAN CHECK8/27/2010 8/27/2010 PASS
DetailsSam Zahorka
1st review completed  8/27/2010 DONE
Failed - Plan Check
Telephone call  8/25/2010 DONE
DetailsSam Zahorka
I spoke with the Engineer Carlyle Briggs about the Engineering being re-used from a previous project and that his stamp date is from 2008. He stated he was OK with this contractor re-useing his engineering and that the structural loading/code year is still the same. I verified with him the Engineering calculations and drawings will work for a 66' X 18' Carport. He said they would and thanked me for the telephone call. SRZ
Routing - PLAN CHECK8/16/2010 8/25/2010 FAIL
DetailsSam Zahorka
Routing - Erosion and Sediment8/13/2010 8/16/2010 PASS
DetailsSteven Webb
ESC plan waiver is approved according to the ESC permit conditions. ESC10-00617
Routing - PLANNING8/16/2010 8/16/2010 PASS
DetailsSarah Schafer
Approved per DRH10-00031.
Routing - PLANNING Land Div8/12/2010 8/13/2010 PASS
DetailsTodd Tucker
Recd Pcfee & Taken To Pln CK  8/12/2010  
Plan routing begun/NEW & ADDTN  8/12/2010  
Pending Assignment by JCM8/12/2010 8/12/2010 BLDA
DetailsJohn Menard
8/12/2010 15:40:45 JCM - activity updated through activity BLDA160 from case BLD10-01911.
Application received 8/12/2010