Second Notice | | 2/27/2011 | 3/3/2011 | | DONE |
|
|
|
|
First Notice | | 2/10/2011 | 2/17/2011 | | DONE |
|
|
|
|
Permanent Occupancy | | | 1/31/2011 | | DONE |
|
|
|
|
FIRE-Final Inspection | 1/21/2011 | 1/24/2011 | 1/24/2011 | A | PASS |
Forrest France
|
|
|
Life safety inspection passed.
|
BLD-Final | 1/21/2011 | 1/24/2011 | 1/24/2011 | P | PASS |
Jim Storey
|
|
|
harvey Phone #: ###-####
|
PubWorks Occupancy Approval | 1/19/2011 | 1/19/2011 | 1/19/2011 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Conference | 12/27/2010 | 12/27/2010 | 12/28/2010 | A | DONE |
Forrest France
|
|
|
Regarding portable fire extinguisher locations per approved drawings and review notes.
|
BLD-Other | 12/27/2010 | 12/27/2010 | 12/27/2010 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 12/27/2010 | 12/27/2010 | 12/27/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Foundation | 10/26/2010 | 10/26/2010 | 10/26/2010 | P | PASS |
Jim Storey
|
|
|
harvey - wall Phone #: ###-####
|
BLD-Footing | 10/19/2010 | 10/21/2010 | 10/21/2010 | P | PASS |
Jim Storey
|
|
|
Harvey Phone #: ###-####
|
BLD-Footing | 10/19/2010 | 10/19/2010 | 10/19/2010 | P | DEFR |
Jim Storey
|
|
|
Harvey Phone #: ###-####10/21pm
|
BLD-Foundation | 10/8/2010 | 10/11/2010 | 10/11/2010 | A | PASS |
Jim Storey
|
|
|
harvey Phone #: ###-####
|
BLD-Footing | 10/6/2010 | 10/7/2010 | 10/7/2010 | A | PASS |
Jim Storey
|
|
|
Harvey Phone #: ###-#### placed with si verifacation.
|
Route to Impact Fee Review | 8/16/2010 | 8/19/2010 | 9/29/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Route to Impact Fee Review | 9/20/2010 | 9/23/2010 | 9/27/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Print Occupancy Form | | | 9/27/2010 | | DONE |
|
|
|
|
Telephone call | | | 9/27/2010 | | DONE |
Tisha Gallop
|
|
|
spoke to Rocky and told him permit is ready, fees and need ACHD.
|
Permit Ready to Issue | | | 9/27/2010 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 9/27/2010 | | DONE |
Barbara Stitt
|
|
|
|
Routing - PLAN CHECK | 9/24/2010 | | 9/24/2010 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/24/2010 | | DONE |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 9/23/2010 | | 9/24/2010 | | PASS |
Beverly Mountain
|
|
|
|
Plan assigned to (JCM) | 8/17/2010 | | 9/24/2010 | | PASS |
John Menard
|
|
|
9/24/2010 14:28:14 JCM - activity updated through activity BLDA022 from case BLD10-01936.
|
Routing - FIRE | 9/20/2010 | 9/20/2010 | 9/23/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing PW Drainage | 9/23/2010 | | 9/23/2010 | | PASS |
Brian Murphy
|
|
|
|
1st review completed | | | 9/23/2010 | | FAIL |
|
|
|
Failed Public Works
|
Plan Reviewer's activity | | | 9/20/2010 | | PASS |
John Menard
|
|
|
Reviewed and approved structural revisions and nonstructural review without comments. JCM
|
Routing - PLAN CHECK | 8/30/2010 | | 9/20/2010 | | PASS |
John Menard
|
|
|
John Menard
|
Plan resubmittals received | | | 9/8/2010 | | |
|
|
|
received 1 comments,3 calcs & 3 copies of sheets A1 inserted by Tom from Design resources. sent to John M.
|
Received Certificate of Value | | | 9/3/2010 | | DONE |
Tisha Gallop
|
|
|
Received revised cert of value to split out restroom addition into seperate permit Bld10-02093 for new project value of $375,782. The additional $120,000 value added to the project value by the architects rep submitting the plans is for permanent equipment.
|
Plan resubmittals requested | | | 8/31/2010 | | DONE |
John Menard
|
|
|
E-mailed the architect a copy of the structural comments and advised need for additional permit application for proposed restroom addition. JCM
|
Routing - PLANNING | 8/28/2010 | | 8/30/2010 | | PASS |
Josh Wilson
|
|
|
DRH10-00145 Josh Wilson
|
Routing - PLUMBING | 8/25/2010 | | 8/28/2010 | | PASS |
Bill VanDegrift
|
|
|
per plans and 2003 upc
|
Routing - PUBLIC WORKS | 8/18/2010 | | 8/25/2010 | | FAIL |
Beverly Mountain
|
|
|
failed by Brian Murphy
|
Routing - Erosion and Sediment | 8/25/2010 | | 8/25/2010 | | PASS |
Steven Webb
|
|
|
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC10-00623
|
Routing PW Sewer Design | 8/23/2010 | | 8/24/2010 | | PASS |
Jon R. Gunnerson
|
|
|
Connect onto existing service line.
|
Telephone call | | | 8/23/2010 | | DONE |
Sam Zahorka
|
|
|
left message with the Design Professional. Need separate submittals for restroom addition tom the existing building. Also need Grading and Drainage info per Brian Murphy.
|
Routing PW Drainage | 8/20/2010 | | 8/23/2010 | | FAIL |
Brian Murphy
|
|
|
need o and m and drainage report brian murphy ###-####
|
Routing - Addressing | 8/19/2010 | | 8/19/2010 | | PASS |
April Wing
|
|
|
|
Routing - PLANNING Land Div | 8/17/2010 | | 8/18/2010 | | PASS |
Todd Tucker
|
|
|
|
Pending Assignment by JCM | 8/16/2010 | | 8/17/2010 | | BLDA |
John Menard
|
|
|
8/17/2010 08:09:23 JCM - activity updated through activity BLDA166 from case BLD10-01936.
|
Plans ACCEPTED BY PLAN TECH | | | 8/16/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/16/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/16/2010 | | PASS |
Tisha Gallop
|
|
|
|
Application received | | 8/16/2010 | | | |
|
|
|
|