Permit Information
Permit NumberBLD10-01936
StatusFinaled
Name K2 CONSTRUCTION
Site Address 6701 S BUSINESS WAY
Project NameWestern Trailer
Customer Number 
ePlanReviewNo
Description
Western Trailer - Blast Booth Building - To construct a new 3,150 square foot, one story, pre-engineered metal fabrication building and related site improvements. This building will be used for bead blasting and contains a complete bead blasting exhaust and recovery system. The required accessible restroom is being provided in the adjacent main fabrication building, approximately 250 feet away. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 2/27/20113/3/2011 DONE
First Notice 2/10/20112/17/2011 DONE
Permanent Occupancy  1/31/2011 DONE
FIRE-Final Inspection1/21/20111/24/20111/24/2011APASS
DetailsForrest France
Life safety inspection passed.
BLD-Final1/21/20111/24/20111/24/2011PPASS
DetailsJim Storey
harvey Phone #: ###-####
PubWorks Occupancy Approval1/19/20111/19/20111/19/2011 DONE
DetailsTiffany Lowery
FIRE-Conference12/27/201012/27/201012/28/2010ADONE
DetailsForrest France
Regarding portable fire extinguisher locations per approved drawings and review notes.
BLD-Other12/27/201012/27/201012/27/2010PPASS
DetailsJim Storey
BLD-Aging Inspection12/27/201012/27/201012/27/2010 PASS
DetailsJim Storey
BLD-Foundation10/26/201010/26/201010/26/2010PPASS
DetailsJim Storey
harvey - wall Phone #: ###-####
BLD-Footing10/19/201010/21/201010/21/2010PPASS
DetailsJim Storey
Harvey Phone #: ###-####
BLD-Footing10/19/201010/19/201010/19/2010PDEFR
DetailsJim Storey
Harvey Phone #: ###-####10/21pm
BLD-Foundation10/8/201010/11/201010/11/2010APASS
DetailsJim Storey
harvey Phone #: ###-####
BLD-Footing10/6/201010/7/201010/7/2010APASS
DetailsJim Storey
Harvey Phone #: ###-#### placed with si verifacation.
Route to Impact Fee Review8/16/20108/19/20109/29/2010 PASS
DetailsCindy M. Gould
Route to Impact Fee Review9/20/20109/23/20109/27/2010 PASS
DetailsCindy M. Gould
Print Occupancy Form  9/27/2010 DONE
Telephone call  9/27/2010 DONE
DetailsTisha Gallop
spoke to Rocky and told him permit is ready, fees and need ACHD.
Permit Ready to Issue  9/27/2010 DONE
DetailsTisha Gallop
Issue PAID IN FULL permit  9/27/2010 DONE
DetailsBarbara Stitt
Routing - PLAN CHECK9/24/2010 9/24/2010 PASS
DetailsJohn Menard
PLANS/APPL TAKEN TO FRONT DESK  9/24/2010 DONE
DetailsJohn Menard
Routing - PUBLIC WORKS9/23/2010 9/24/2010 PASS
DetailsBeverly Mountain
Plan assigned to (JCM)8/17/2010 9/24/2010 PASS
DetailsJohn Menard
9/24/2010 14:28:14 JCM - activity updated through activity BLDA022 from case BLD10-01936.
Routing - FIRE9/20/20109/20/20109/23/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing PW Drainage9/23/2010 9/23/2010 PASS
DetailsBrian Murphy
1st review completed  9/23/2010 FAIL
Failed Public Works
Plan Reviewer's activity  9/20/2010 PASS
DetailsJohn Menard
Reviewed and approved structural revisions and nonstructural review without comments. JCM
Routing - PLAN CHECK8/30/2010 9/20/2010 PASS
DetailsJohn Menard
John Menard
Plan resubmittals received  9/8/2010  
received 1 comments,3 calcs & 3 copies of sheets A1 inserted by Tom from Design resources. sent to John M.
Received Certificate of Value  9/3/2010 DONE
DetailsTisha Gallop
Received revised cert of value to split out restroom addition into seperate permit Bld10-02093 for new project value of $375,782. The additional $120,000 value added to the project value by the architects rep submitting the plans is for permanent equipment.
Plan resubmittals requested  8/31/2010 DONE
DetailsJohn Menard
E-mailed the architect a copy of the structural comments and advised need for additional permit application for proposed restroom addition. JCM
Routing - PLANNING8/28/2010 8/30/2010 PASS
DetailsJosh Wilson
DRH10-00145 Josh Wilson
Routing - PLUMBING8/25/2010 8/28/2010 PASS
DetailsBill VanDegrift
per plans and 2003 upc
Routing - PUBLIC WORKS8/18/2010 8/25/2010 FAIL
DetailsBeverly Mountain
failed by Brian Murphy
Routing - Erosion and Sediment8/25/2010 8/25/2010 PASS
DetailsSteven Webb
ESC plan is approved according to the ESC plan and ESC permit conditions. ESC10-00623
Routing PW Sewer Design8/23/2010 8/24/2010 PASS
DetailsJon R. Gunnerson
Connect onto existing service line.
Telephone call  8/23/2010 DONE
DetailsSam Zahorka
left message with the Design Professional. Need separate submittals for restroom addition tom the existing building. Also need Grading and Drainage info per Brian Murphy.
Routing PW Drainage8/20/2010 8/23/2010 FAIL
DetailsBrian Murphy
need o and m and drainage report brian murphy ###-####
Routing - Addressing8/19/2010 8/19/2010 PASS
DetailsApril Wing
Routing - PLANNING Land Div8/17/2010 8/18/2010 PASS
DetailsTodd Tucker
Pending Assignment by JCM8/16/2010 8/17/2010 BLDA
DetailsJohn Menard
8/17/2010 08:09:23 JCM - activity updated through activity BLDA166 from case BLD10-01936.
Plans ACCEPTED BY PLAN TECH  8/16/2010 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  8/16/2010 DONE
DetailsTisha Gallop
Intake Approval  8/16/2010 PASS
DetailsTisha Gallop
Application received 8/16/2010