BLD-Final | 1/19/2011 | 1/20/2011 | 1/20/2011 | P | PASS |
Jim Storey
|
|
|
chad Phone #: ###-####
|
DOC - Permit Finaled | 1/20/2011 | 1/20/2011 | 1/20/2011 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 1/19/2011 | 1/19/2011 | 1/19/2011 | P | DEFR |
Jim Storey
|
|
|
chad Phone #: ###-####
|
BLD-Aging Inspection | 12/23/2010 | 12/23/2010 | 12/23/2010 | | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 10/20/2010 | 10/21/2010 | 10/21/2010 | A | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 10/20/2010 | 10/20/2010 | 10/21/2010 | P | NR |
Jim Storey
|
|
|
Chad Phone #: ###-####
|
BLD-Conference | 10/19/2010 | 10/19/2010 | 10/19/2010 | A | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 10/18/2010 | 10/19/2010 | 10/19/2010 | P | CANC |
Jim Storey
|
|
|
chad Phone #: ###-####
|
BLD-Framing/Rough-in | 10/18/2010 | 10/18/2010 | 10/18/2010 | P | PART |
Jim Storey
|
|
|
Chad Phone #: ###-#### truss brace/ load points three ply bearing area/ truss hanger/row blk i joist top chord.
|
BLD-Foundation | 9/23/2010 | 9/23/2010 | 9/23/2010 | P | PASS |
Jim Storey
|
|
|
hyrum Phone #: ###-####
|
BLD-Foundation | 9/21/2010 | 9/22/2010 | 9/22/2010 | A | PASS |
Jim Storey
|
|
|
Hyrum-pour scheduled for 11:30 Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/21/2010 | | DONE |
Tisha Gallop
|
|
|
|
OVERRIDE | | | 9/14/2010 | | |
|
|
|
|
Plan assigned to (CDM) | 9/13/2010 | 9/13/2010 | 9/14/2010 | | DONE |
Carl D Madsen
|
|
|
|
Plan assigned to (CDM) | 8/17/2010 | 8/17/2010 | 9/14/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/23/2010 | | 9/14/2010 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 9/14/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/14/2010 | | DONE |
|
|
|
|
Telephone call | | | 9/14/2010 | | DONE |
|
|
|
left vm for chad at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/14/2010 | | DONE |
|
|
|
|
1st review completed | | | 9/13/2010 | | FAIL |
|
|
|
Failed per planning approval
|
Routing - PLANNING | 9/13/2010 | | 9/13/2010 | | PASS |
Colleen T Carroll
|
|
|
|
Plan resubmittals received | | | 9/1/2010 | | DONE |
Tisha Gallop
|
|
|
received two copies full set of plans, two copies upper floor framing plan with material list, one copy of truss layout and engineering; taken to Carl Madsen
|
Route to Impact Fee Review | 8/16/2010 | 8/19/2010 | 8/24/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - Addressing | 8/17/2010 | | 8/19/2010 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 8/19/2010 | | 8/19/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Application received | | 8/16/2010 | 8/17/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/17/2010 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/17/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/17/2010 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 8/19/2010 | | | | FAIL |
Colleen T Carroll
|
|
|
Garage interior needs to be 20' x 20'
|