BLD-Final | 12/28/2010 | 12/28/2010 | 12/28/2010 | P | PASS |
Jim Storey
|
|
|
larry Phone #: ###-####
|
DOC - Permit Finaled | 12/28/2010 | 12/28/2010 | 12/28/2010 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 11/15/2010 | 11/15/2010 | 11/15/2010 | P | PASS |
Jim Storey
|
|
|
LARRY Phone #: ###-####
|
BLD-Framing/Rough-in | 11/15/2010 | 11/15/2010 | 11/15/2010 | P | PASS |
Jim Storey
|
|
|
LARRY Phone #: ###-#### recieved engineering c/n made ok
|
BLD-Framing/Rough-in | 11/8/2010 | 11/8/2010 | 11/8/2010 | P | PART |
Jim Storey
|
|
|
Larry Phone #: ###-#### need engineering iield review o tall walls as built for compliance./ blk brace pannels/ missing i joist hangers at garage-house ceilling/ double king studs mlb support . ok to insulate.
|
BLD-Foundation | 10/1/2010 | 10/4/2010 | 10/4/2010 | A | PASS |
Jim Storey
|
|
|
Bill Phone #: ###-####
|
BLD-Footing | 9/29/2010 | 9/30/2010 | 9/30/2010 | P | PASS |
Jim Storey
|
|
|
bill Phone #: ###-####
|
OVERRIDE | | | 9/27/2010 | | |
|
|
|
|
Telephone call | | | 9/27/2010 | | DONE |
Barbara Stitt
|
|
|
Spoke with Mike Smith and told him that permit is ready & emailed him fees due on 9-27-10///9-27-10 @ 12:18pm
|
Issue PAID IN FULL permit | | | 9/27/2010 | | DONE |
Tisha Gallop
|
|
|
|
Permit Ready to Issue | | | 9/27/2010 | | DONE |
Barbara Stitt
|
|
|
|
Plan assigned to (CDM) | 8/24/2010 | 8/24/2010 | 9/23/2010 | | DONE |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/30/2010 | | 9/23/2010 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 9/17/2010 | | 9/23/2010 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/23/2010 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/24/2010 | 8/27/2010 | 9/20/2010 | | PASS |
Cindy M. Gould
|
|
|
credit given for removal of mobile homes is this subdivsion
|
Routing - PLANNING | 9/16/2010 | | 9/17/2010 | | PASS |
Susan Riggs
|
|
|
|
Case Summary (BLD) | | | 9/16/2010 | | DONE |
|
|
|
|
1st review completed | | | 9/15/2010 | | FAIL |
|
|
|
Fail pending planning approval
Engineering on tall wall and sheer wall at the north master bedroom and beam sizes on spec beams. CDM
|
Routing - PLANNING | 8/27/2010 | | 8/30/2010 | | FAIL |
Colleen T Carroll
|
|
|
cup07-32 & cup1035. Plans failed, need bond for amenities, applicant will be in this week.
|
Routing - PUBLIC WORKS | 8/26/2010 | | 8/27/2010 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 8/24/2010 | | 8/26/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 8/24/2010 | 8/24/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/24/2010 | | PASS |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/24/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/24/2010 | | DONE |
Tisha Gallop
|
|
|
|