(IDAHO STATE LIQUOR STORE) Remodel of an existing 2,200 sq. ft. space and adding 800 sq. ft. for new retail liquor store. New total area of the space will be 3,000 sq. ft. Work includes select interior demolition of interior non-bearing walls, and exterior storefront window system; construct new interior walls to create an office, partial walls at break/work room, cooler room and wing walls at drinking fountains; infill two exterior door openings and relocate one of front entry door in new storefront / window systems; new work / service counter to divide to entry lobbies; interior finishes, limited SAT & new lighting / controls, electrical, mechanical & plumbing, all per reviewed plans, red-line notes and all attached plan review comments & conditions as part of the approved plans. This is an occupancy use change from "B" to "M" occupancy group. drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 12/4/201012/8/2010 DONE
First Notice 11/22/201011/24/2010 DONE
Permanent Occupancy UNPAID FEE  11/12/2010 DONE
DetailsTisha Gallop
BLD-Final11/5/201011/5/201011/5/2010PPASS
DetailsJim Sly
matt Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection11/4/201011/5/201011/5/2010APASS
DetailsTroy Cobbley
life safety passed
Case Summary (BLD)  11/5/2010  
BLD-Framing/Rough-in10/5/201010/6/201010/6/2010APASS
DetailsJim Sly
Matt Phone #: ###-####
Issue PAID IN FULL permit  9/29/2010 DONE
DetailsTisha Gallop
Additional plans submitted  9/28/2010 PASS
Received e-mail copy of ACHD approval report from Stan Cole Architect. Copy to Tisha Gallop and attached copy to permit.
Print Occupancy Form  9/22/2010 DONE
Telephone call  9/22/2010 DONE
left vm for stan at ###-#### - permit ready and fees given - also need ACHD receipt
Permit Ready to Issue  9/22/2010 DONE
Details
Plan assigned to (DRS)8/30/2010 9/21/2010 PASS
DetailsDan Stuart
9/21/2010 14:13:11 DRS - activity updated through activity BLDA022 from case BLD10-02033.
Routing - Design Review9/21/2010 9/21/2010 PASS
DetailsJosh Wilson
Josh Wilson - CZC10-00181
Routing - FIRE9/17/2010 9/21/2010 PASS
DetailsScott Arellano
Attached IFC comments to plans
Routing - PLAN CHECK9/21/2010 9/21/2010 PEND
DetailsDan Stuart
Plans approved by fire code analyst. Routing plans to Planning for re-review.
Routing - PLAN CHECK9/21/2010 9/21/2010 PASS
DetailsDan Stuart
Approved as noted on plans and allattached plan review conditions as part of the plans requiring compliance. To permit desk to issue.
PLANS/APPL TAKEN TO FRONT DESK  9/21/2010 PASS
As noted on plans and attached plan reviews
Routing - PLAN CHECK9/14/2010 9/17/2010 PASS
DetailsDan Stuart
Inserted new plan sheet A0.1 provided in response to fire code analyst review; attached data provided by Stan Cole concerning the counter height; attached plan review conditions as part of the reviewed approved plans, copies of CISCA 0-2 & 3-4 installation Guideleines and ASCE 7-05, Sec. 13.5.6 for contractors use to provide code compliance.
Plan resubmittals received  9/17/2010 DONE
DetailsTisha Gallop
received transmittal and two copies of plan sheet A0.1; taken to Dan Stuart
Routing - FIRE9/8/2010 9/14/2010 FAIL
DetailsScott Arellano
Faxed and emailed resubmittal items to architect.
1st review completed  9/14/2010 FAIL
Failed Planning, Plan Check, Fire
Plan resubmittals requested  9/8/2010 DONE
Copy of 1st review to architect for resubmittals.
Routing - PLAN CHECK8/30/2010 9/8/2010 FAIL
DetailsDan Stuart
Copy of plan review e-mailed to architect for resubmittals. Routing plans to fire code analyst for review.
Plan Reviewer's activity  8/31/2010 DONE
DetailsJason Blais
Emailed architect Stan Cole to let him know the review process had to change to a Major Level 3 review because it is a change in occupancy. Also reminded him to contact ACHD for any requirements or evaluation of impact fees. Written verification will need to be provided to our Permit Counter prior to permit issuance.
Plan assigned to (TLW)8/26/2010 8/30/2010 DEFR
DetailsTim L. Woodard
Deffered Review to Dan Stuart. This project is actually a Level 3 Tenant Improvement project. TLW
Routing - PLANNING8/30/2010 8/30/2010 FAIL
DetailsJosh Wilson
CZC Not approved yet. TLW
Will need to route to Josh Wilson in Design Review for review and approval of CZC10-00181.
Routing - PUBLIC WORKS8/26/2010 8/27/2010 PASS
DetailsBeverly Mountain
Routing - Addressing8/27/2010 8/27/2010 PASS
DetailsApril Wing
Application received 8/25/20108/26/2010 DONE
DetailsTisha Gallop
Plans ACCEPTED BY PLAN TECH  8/25/2010 DONE
DetailsTisha Gallop
Recd Pcfee & Taken To Pln CK  8/25/2010 DONE
DetailsTisha Gallop