Second Notice | | 12/4/2010 | 12/8/2010 | | DONE |
|
|
|
|
First Notice | | 11/22/2010 | 11/24/2010 | | DONE |
|
|
|
|
Permanent Occupancy UNPAID FEE | | | 11/12/2010 | | DONE |
Tisha Gallop
|
|
|
|
BLD-Final | 11/5/2010 | 11/5/2010 | 11/5/2010 | P | PASS |
Jim Sly
|
|
|
matt Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 11/4/2010 | 11/5/2010 | 11/5/2010 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
Case Summary (BLD) | | | 11/5/2010 | | |
|
|
|
|
BLD-Framing/Rough-in | 10/5/2010 | 10/6/2010 | 10/6/2010 | A | PASS |
Jim Sly
|
|
|
Matt Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/29/2010 | | DONE |
Tisha Gallop
|
|
|
|
Additional plans submitted | | | 9/28/2010 | | PASS |
|
|
|
Received e-mail copy of ACHD approval report from Stan Cole Architect. Copy to Tisha Gallop and attached copy to permit.
|
Print Occupancy Form | | | 9/22/2010 | | DONE |
|
|
|
|
Telephone call | | | 9/22/2010 | | DONE |
|
|
|
left vm for stan at ###-#### - permit ready and fees given - also need ACHD receipt
|
Permit Ready to Issue | | | 9/22/2010 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 8/30/2010 | | 9/21/2010 | | PASS |
Dan Stuart
|
|
|
9/21/2010 14:13:11 DRS - activity updated through activity BLDA022 from case BLD10-02033.
|
Routing - Design Review | 9/21/2010 | | 9/21/2010 | | PASS |
Josh Wilson
|
|
|
Josh Wilson - CZC10-00181
|
Routing - FIRE | 9/17/2010 | | 9/21/2010 | | PASS |
Scott Arellano
|
|
|
Attached IFC comments to plans
|
Routing - PLAN CHECK | 9/21/2010 | | 9/21/2010 | | PEND |
Dan Stuart
|
|
|
Plans approved by fire code analyst. Routing plans to Planning for re-review.
|
Routing - PLAN CHECK | 9/21/2010 | | 9/21/2010 | | PASS |
Dan Stuart
|
|
|
Approved as noted on plans and allattached plan review conditions as part of the plans requiring compliance. To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2010 | | PASS |
|
|
|
As noted on plans and attached plan reviews
|
Routing - PLAN CHECK | 9/14/2010 | | 9/17/2010 | | PASS |
Dan Stuart
|
|
|
Inserted new plan sheet A0.1 provided in response to fire code analyst review; attached data provided by Stan Cole concerning the counter height; attached plan review conditions as part of the reviewed approved plans, copies of CISCA 0-2 & 3-4 installation Guideleines and ASCE 7-05, Sec. 13.5.6 for contractors use to provide code compliance.
|
Plan resubmittals received | | | 9/17/2010 | | DONE |
Tisha Gallop
|
|
|
received transmittal and two copies of plan sheet A0.1; taken to Dan Stuart
|
Routing - FIRE | 9/8/2010 | | 9/14/2010 | | FAIL |
Scott Arellano
|
|
|
Faxed and emailed resubmittal items to architect.
|
1st review completed | | | 9/14/2010 | | FAIL |
|
|
|
Failed Planning, Plan Check, Fire
|
Plan resubmittals requested | | | 9/8/2010 | | DONE |
|
|
|
Copy of 1st review to architect for resubmittals.
|
Routing - PLAN CHECK | 8/30/2010 | | 9/8/2010 | | FAIL |
Dan Stuart
|
|
|
Copy of plan review e-mailed to architect for resubmittals. Routing plans to fire code analyst for review.
|
Plan Reviewer's activity | | | 8/31/2010 | | DONE |
Jason Blais
|
|
|
Emailed architect Stan Cole to let him know the review process had to change to a Major Level 3 review because it is a change in occupancy. Also reminded him to contact ACHD for any requirements or evaluation of impact fees. Written verification will need to be provided to our Permit Counter prior to permit issuance.
|
Plan assigned to (TLW) | 8/26/2010 | | 8/30/2010 | | DEFR |
Tim L. Woodard
|
|
|
Deffered Review to Dan Stuart. This project is actually a Level 3 Tenant Improvement project. TLW
|
Routing - PLANNING | 8/30/2010 | | 8/30/2010 | | FAIL |
Josh Wilson
|
|
|
CZC Not approved yet. TLW
Will need to route to Josh Wilson in Design Review for review and approval of CZC10-00181.
|
Routing - PUBLIC WORKS | 8/26/2010 | | 8/27/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 8/27/2010 | | 8/27/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 8/25/2010 | 8/26/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/25/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/25/2010 | | DONE |
Tisha Gallop
|
|
|
|