BLD-Final | 11/23/2010 | 11/24/2010 | 11/24/2010 | A | PASS |
Mike Jordan
|
|
|
sergy Phone #: ###-####
|
DOC - Permit Finaled | 11/24/2010 | 11/24/2010 | 11/24/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of completion was issued.
|
BLD-Final | 11/23/2010 | 11/23/2010 | 11/23/2010 | P | NR |
Mike Jordan
|
|
|
Sergy Phone #: ###-####. Needs mechanical final.
|
BLD-Framing/Rough-in | 10/1/2010 | 10/1/2010 | 10/1/2010 | P | PASS |
Jim Sly
|
|
|
Sergey Phone #: ###-####
|
BLD-Framing/Rough-in | 9/27/2010 | 9/28/2010 | 9/28/2010 | A | PART |
Mike Jordan
|
|
|
sergey Phone #: ###-####. Needs to complete air seal package, Provide straps on lvl at front addition. Pending mechanical rough in inspection. ok to insulate. Correction notice issued.
|
BLD-Foundation | 9/3/2010 | 9/7/2010 | 9/7/2010 | A | PART |
Mike Jordan
|
|
|
Sergy Phone #: ###-####. Work in progress on placing reinforcement placement. Mono placement.
|
BLD-Footing | 9/3/2010 | 9/7/2010 | 9/7/2010 | A | PART |
Mike Jordan
|
|
|
Sergy Phone #: ###-####. Work in progress on reinforcement placement. Mono placement.
|
OVERRIDE | | | 8/26/2010 | | |
|
|
|
|
Routing Walk-In (Zoning) | 8/26/2010 | 8/26/2010 | 8/26/2010 | A | PASS |
Colleen T Carroll
|
|
|
|
Routing Walk-In (BLD) | 8/26/2010 | 8/26/2010 | 8/26/2010 | A | DONE |
Perry Paine
|
|
|
8/26/2010 11:39:45 PEP - activity updated through activity BLDA022 from case BLD10-02039.
|
Plan assigned to (PEP) | 8/26/2010 | 8/26/2010 | 8/26/2010 | | PASS |
Perry Paine
|
|
|
8/26/2010 11:39:44 PEP - activity updated through activity BLDA022 from case BLD10-02039.
|
Case Summary (BLD) | | | 8/26/2010 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/26/2010 | | |
|
|
|
|
1st review completed | | | 8/26/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2010 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/26/2010 | | DONE |
Tisha Gallop
|
|
|
|
Issue PAID IN FULL permit | | | 8/26/2010 | | DONE |
Tisha Gallop
|
|
|
|
Application received | | 8/26/2010 | | | |
|
|
|
|