BLD-Final | 3/15/2011 | 3/15/2011 | 3/15/2011 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 3/15/2011 | 3/15/2011 | 3/15/2011 | P | PASS |
Mike Jordan
|
|
|
Residential certificate of occupancy was issued.
|
BLD-Final | 3/14/2011 | 3/15/2011 | 3/15/2011 | A | NH |
Mike Jordan
|
|
|
STEVE PLEASE CALL FOR ACCESS Phone #: ###-####
|
BLD-Aging Inspection | 3/7/2011 | 3/7/2011 | 3/7/2011 | | DONE |
Mike Jordan
|
|
|
Appears that work is completed. Still needs plumbing final. Called steve with Hunter hiomes and left him a messsage to get plumbing final and to get building final before permit expires.
|
BLD-Energy code compliance | 10/12/2010 | 10/12/2010 | 10/12/2010 | P | PASS |
Jim Storey
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 10/8/2010 | 10/11/2010 | 10/11/2010 | A | PASS |
Jim Sly
|
|
|
DAVID Phone #: ###-####
|
BLD-Foundation | 9/14/2010 | 9/14/2010 | 9/14/2010 | P | PASS |
Mike Jordan
|
|
|
Lito Phone #: ###-####
|
BLD-Footing | 9/13/2010 | 9/14/2010 | 9/13/2010 | P | PASS |
Mike Jordan
|
|
|
Lito Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/8/2010 | | |
|
|
|
|
OVERRIDE | | | 9/7/2010 | | |
|
|
|
|
Telephone call | | | 9/7/2010 | | DONE |
|
|
|
left vm for steve at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 9/7/2010 | | DONE |
|
|
|
|
Plan assigned to (PEP) | 9/3/2010 | 9/3/2010 | 9/3/2010 | | PASS |
Perry Paine
|
|
|
9/3/2010 09:43:27 PEP - activity updated through activity BLDA022 from case BLD10-02041.
|
Plan assigned to (CDM) | 8/26/2010 | 8/26/2010 | 9/3/2010 | | DEFR |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/30/2010 | | 9/3/2010 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 9/3/2010 | | |
|
|
|
|
1st review completed | | | 9/3/2010 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/3/2010 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/3/2010 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/26/2010 | 8/31/2010 | 9/2/2010 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 8/27/2010 | | 8/30/2010 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 8/26/2010 | | 8/27/2010 | | PASS |
April Wing
|
|
|
|
Routing - PUBLIC WORKS | 8/27/2006 | | 8/27/2010 | | PASS |
Beverly Mountain
|
|
|
|
Application received | | 8/26/2010 | 8/26/2010 | | DONE |
Tisha Gallop
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/26/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/26/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 8/26/2010 | | PASS |
Tisha Gallop
|
|
|
|