Second Notice | | 12/17/2010 | 12/7/2010 | | DONE |
|
|
|
|
Third Notice | | 12/12/2010 | 12/7/2010 | | DONE |
|
|
|
|
First Notice | | 11/14/2010 | 12/7/2010 | | DONE |
|
|
|
|
BLD-Final | 11/3/2010 | 11/4/2010 | 11/4/2010 | A | PASS |
Tom Arcoraci
|
|
|
Ramsey Phone #: ###-####
|
Permanent Occupancy UNPAID FEE | | | 11/4/2010 | | DONE |
|
|
|
|
Additional plans submitted | | | 11/4/2010 | | PASS |
|
|
|
Architect Barbara Beier e-mailed copy of handrail detail for stairs at NW exterior corner of CENTRAL RENT TO OWN, extending the return to the wall such that required clearances are maintained between the electrical conduit and the handrail. Copy of e-mail forwarded to inspector, Tom Arcoracci.
|
BLD-Final | 11/2/2010 | 11/3/2010 | 11/3/2010 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 11/3/2010 | 11/3/2010 | 11/3/2010 | P | PASS |
Troy Cobbley
|
|
|
life safety passed.
|
BLD-Final | 11/1/2010 | 11/2/2010 | 11/2/2010 | P | NR |
Tom Arcoraci
|
|
|
Ramsey Phone #: ###-####
|
FIRE-Final Inspection | 11/1/2010 | 11/2/2010 | 11/2/2010 | A | FAIL |
Troy Cobbley
|
|
|
Provide annual inspection for all fire extinguishers, provide exit discharge lights at the three exits, provide correct remote annunciators or meet the exception of IMC 606.2
|
BLD-Other | 10/21/2010 | 10/21/2010 | 10/21/2010 | P | PASS |
Tom Arcoraci
|
|
|
ramsey - suspended ceiling grid Phone #: ###-####
|
Case Summary (BLD) | | | 10/21/2010 | | DONE |
|
|
|
|
BLD-Framing/Rough-in | 10/8/2010 | 10/8/2010 | 10/8/2010 | P | PASS |
Tom Arcoraci
|
|
|
anthony Phone #: ###-####
|
Plan assigned to (DRS) | 9/7/2010 | | 10/7/2010 | | PASS |
Dan Stuart
|
|
|
|
Routing - FIRE | 10/6/2010 | | 10/7/2010 | | PASS |
Scott Arellano
|
|
|
Please, see attached review.
|
Routing - PLAN CHECK | 10/7/2010 | | 10/7/2010 | | PASS |
Dan Stuart
|
|
|
Plans to permit desk to issue permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/2010 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/7/2010 | | DONE |
|
|
|
|
Telephone call | | | 10/7/2010 | | DONE |
|
|
|
t/c w barbara at ###-#### - permit ready and fees given
|
Permit Ready to Issue | | | 10/7/2010 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/7/2010 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/29/2010 | | 10/6/2010 | | PASS |
Dan Stuart
|
|
|
Resubmittals received and inserted into plans for review. Plans approved to include red-lined notes on plans and all attached plan reviews by all reviewing government agencies. Routing back to fire code analyst for review.
|
Plan resubmittals received | | | 10/5/2010 | | |
Dan Stuart
|
|
|
rec'd sheets A-1; A-2; A-3; A-4; E-1; E-2; E-3 - taken to Dan S
|
1st review completed | | | 9/29/2010 | | DONE |
|
|
|
Failed - Plan Check, Fire
|
Telephone call | | | 9/29/2010 | | DONE |
|
|
|
Call from Barbara Bierer to discuss plan review and energy code analysis.
|
Routing - FIRE | 9/28/2010 | | 9/29/2010 | | FAIL |
Scott Arellano
|
|
|
See attached review
|
Routing - PLAN CHECK | 9/10/2010 | | 9/27/2010 | | FAIL |
Dan Stuart
|
|
|
Resubmittals required. Copy of plan review e-mailed to architect. Plans routed to fire code analyst.
|
Plan resubmittals requested | | | 9/27/2010 | | DONE |
|
|
|
Copy of plan review e-mailed to architect for response.
|
Routing - PUBLIC WORKS | 9/7/2010 | | 9/10/2010 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Design Review | 9/10/2010 | | 9/10/2010 | | PASS |
Sarah Schafer
|
|
|
Sarah Schafer - two new exterior doors in storefront
Approved with this building permit.
|
Routing - Addressing | 9/9/2010 | | 9/9/2010 | | PASS |
April Wing
|
|
|
|
Application received | | 9/3/2010 | 9/7/2010 | | DONE |
Tisha Gallop
|
|
|
|
Intake Approval | | | 9/3/2010 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/3/2010 | | DONE |
Tisha Gallop
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/3/2010 | | DONE |
Tisha Gallop
|
|
|
|
Pending Assignment by JCB | 9/7/2010 | | | | |
Jason Blais
|
|
|
|